Method statement · UK
Temporary works propping method statement
‘Stick some acrow in’ is not a method. If the sequence does not attach the TW design, name who can change it, and keep people out from under until load is in the props, it will fail the temporary-works coordinator.
Typical scope
- Design attached
- Coordinator permit
- Exclusion under the load
- Founded and plumb as drawn
- Inspect frequency
- Strike hold point
Quick answer
A temporary-works propping method statement is the sequence for installing, loading and striking designed props, needles or back-propping on a named opening. The design, exclusion under the load, and a strike that does not come out too early are the controls.
Primary topic: temporary works propping method statement. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.
What usually goes wrong
These are the operational gaps that make generic Word RAMS fail on the next site.
Scaffold method reused
No TW design.
Extra acrow because it 'felt light'
Not the drawing.
Strike at 05:00 because the GC asked
Hold point missed.
Example
Needles under a shopfront lintel
Built from one job description. You review and adjust every item before issuing it.
Job description
Install designed needles under the front lintel at 14 Silver Street, Bury. TW design attached, pavement exclusion, floor below the flat cleared, props founded and plumb, inspections daily, no strike until the new steel is signed.
Activities identified
- General site work
- Manual handling
- Plumbing and heating systems
Method (9 steps)
- 1.Arrive and sign in. Arrive at 14 Silver Street, Bury, report to the Silver Street Holdings site contact, sign in and complete any site induction.
- 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
- 3.Isolate and drain down. Isolate the water/heating supply, allow to cool and drain down the affected section. Confirm isolation before breaking into pipework.
- 4.Disconnect and remove existing equipment. Disconnect and remove the existing equipment. Lower or carry it using mechanical aids or team lifts as planned.
- 5.Install new equipment. Position and fix the new equipment to the manufacturer's instructions.
- 6.Install pipework. Install and connect pipework. Use press-fit or mechanical joints in place of hot works where possible.
- 7.Test and commission. Test and commission the installation. Record results.
- 8.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
- 9.Hand over and sign out. Hand over to the Silver Street Holdings site contact, report anything outstanding and sign out.
Main risks (3 in total)
Manual handling
Residual MediumWho: Operatives
- Use mechanical aids (trolleys, sack trucks, hoists) for heavy items
- Team lifts for items too heavy or awkward for one person
- Route planned and cleared before moving items
- Operatives trained in safe lifting techniques
- Gloves with good grip and safety footwear
Hot water, hot surfaces and flooding
Residual LowWho: Operatives, occupants
- System isolated, allowed to cool and drained down before work
- Isolation valves identified and tested before breaking into pipework
- Drip trays, buckets and wet vac available
- Gloves when handling recently isolated pipework
Stored pressure
Residual LowWho: Engineers
- Systems depressurised and drained down before breaking into pipework
- Gauges, hoses and valves inspected and rated for the system pressure
- Cylinders secured upright and transported with valves protected
- Eye protection worn when connecting or venting
What to get right on this document
The design is the method
Attach it.
Nobody under until loaded
Exclusion.
Strike is a hold point
Time or strength.
What this document has to cover
‘Stick some acrow in’ is not a method. If the sequence does not attach the TW design, name who can change it, and keep people out from under until load is in the props, it will fail the temporary-works coordinator.
A temporary works propping method statement only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.
Typical hazards to assess on this job
- Collapse of an opening that was never designed
- People under needles during install or strike
- Props not plumb, not founded, or not to the drawing
- Premature strike because the programme moved
- Dropped steel during landing
- Public or other trades in the exclusion
Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.
A method sequence that actually protects people
Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.
- Confirm the TW design and the coordinator’s permit before the first prop
- Set exclusion under the opening; protect the floor below
- Found, plumb and load props as drawn — no extra acrow ‘for luck’ without the designer
- Inspect after loading and at the specified frequency
- Do not strike until the specified strength, time or hold point
- Strike in the designed order with the exclusion held
Occupancy and other people
Occupied buildings have people on the floor below a chimney breast or a slab pour. Write that floor and that a furniture store under needles is still occupancy.
Substances and COSHH
An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:
- None typically from steel props
- Grout or packing if specified
- Paint on hired equipment
How SafeForJob helps
- Describe this job in plain English and get suggested activities, risks and method steps
- Edit every line before you download or issue
- Reuse a previous RAMS and catch old client or site names
- Attach or create COSHH assessments where hazardous substances appear
What this page is not
This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer temporary works propping method statement document for a named job. You remain responsible for reviewing and issuing it.
Related reading
See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.
Related pages
- RAMS by jobMass underpinning RAMSCreate a underpinning rams for a named UK site. Unique hazards, method sequence and occupancy notes you review before issue.
- GuidesHow to write a method statementA practical sequence for writing a method statement that a principal contractor will actually read.
- RAMS by tradeGroundworks RAMSCreate a groundworks or excavation RAMS online: buried services, trench collapse, plant movement and public interface. Review every suggestion before issue.
- Method statementsMethod statement for electrical worksWrite a method statement for electrical works for a named UK site. Clear sequence, interfaces and controls — review before issue.
- Method statementsHVAC installation method statementWrite a hvac installation method statement for a named UK site. Clear sequence, interfaces and controls — review before issue.
- Method statementsPlumbing method statementWrite a plumbing method statement for a named UK site. Clear sequence, interfaces and controls — review before issue.
- Method statementsRoofing method statementWrite a roofing method statement for a named UK site. Clear sequence, interfaces and controls — review before issue.
- Method statementsExcavation method statementWrite a excavation method statement for a named UK site. Clear sequence, interfaces and controls — review before issue.
- Method statementsFit-out method statementWrite a fit out method statement for a named UK site. Clear sequence, interfaces and controls — review before issue.
Questions
- Is this a scaffold method?
- Access may sit alongside. Propping is temporary works with a design and a coordinator.
- Can I add props on site?
- Only with the designer — extra steel can change the load path.
- Domestic chimney breast?
- Still TW if you are opening a wall — do not guess.
- Who inspects?
- The competent person at the frequency on the design.