How to write a method statement (UK)
If the only control is ‘PPE will be worn’, you have not written a method.
On this page
- Order of work
- Named isolations
- Occupancy
- Tests
- Handover
- Site names
Quick answer
A method statement is the step-by-step ‘how’ that sits with your risk assessment. Write it so a competent stranger could brief the critical controls in order — isolation before work, test before restore, tidy before leave.
Primary topic: how to write a method statement. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.
What usually goes wrong
These are the operational gaps that make generic Word RAMS fail on the next site.
PPE as the method
Not a sequence.
Last week’s site
Copied.
No restore
System left unsafe.
What to get right on this document
Critical control first
Not last.
This site
Names.
Restore is a step
Always.
What this document has to cover
If the only control is ‘PPE will be worn’, you have not written a method.
A how to write a method statement only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.
Typical hazards to assess on this job
- Critical control buried at the end
- Copied plot numbers
- No occupancy
- No test/restore
- No waste/handover
Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.
A method sequence that actually protects people
Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.
- Name the job and site
- List isolations and permits first
- Access equipment
- The work
- Test and restore
- Waste and handover
Occupancy and other people
Occupied premises need extra steps: who is briefed, which route stays open.
Substances and COSHH
An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:
- Attach COSHH where substances appear
How SafeForJob helps
- Describe this job in plain English and get suggested activities, risks and method steps
- Edit every line before you download or issue
- Reuse a previous RAMS and catch old client or site names
- Attach or create COSHH assessments where hazardous substances appear
What this page is not
This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer how to write a method statement document for a named job. You remain responsible for reviewing and issuing it.
Related reading
See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.
Related pages
- GuidesRAMS vs method statementHow the risk assessment and method statement fit together, and when clients ask for a combined RAMS. Practical UK guidance for contractors — with links to free tools.
- GuidesHow to write a RAMSA practical sequence: describe the job, list hazards, choose controls, write the method, check names. Practical UK guidance for contractors — with links to free tools.
- GuidesWhat is a RAMS?RAMS means risk assessment and method statement — usually one site-specific pack for a construction or maintenance job. Practical UK guidance for contractors — with links to free tools.
- GuidesWhat is a COSHH assessment?COSHH assessments explain how you control hazardous substances for a real task, using the SDS. Practical UK guidance for contractors — with links to free tools.
- GuidesSDS vs COSHH assessmentWhy a safety data sheet informs but does not replace your COSHH assessment. Practical UK guidance for contractors — with links to free tools.
- GuidesWorking at height in RAMSHow to describe access equipment, fragile surfaces and rescue thinking inside a RAMS. Practical UK guidance for contractors — with links to free tools.
- GuidesCDM and RAMS responsibilitiesHow contractors use RAMS under CDM without pretending software assigns legal duties. Practical UK guidance for contractors — with links to free tools.
- GuidesRAMS for occupied premisesExtra controls when residents, staff, patients or customers stay in the building. Practical UK guidance for contractors — with links to free tools.
Questions
- Method vs RAMS?
- RAMS is risk assessment plus method. This page is the method half.
- How long should it be?
- Long enough that the critical control cannot be skipped — not an essay.
- Can software write it?
- It can draft. You review.
- Legal format?
- None mandated — clarity beats decoration.