Skip to content
SafeForJob

RAMS by job · UK

Mass underpinning RAMS

Underpinning is temporary works under a live structure, not a footing pour. A foundations RAMS that never mentions the sequence, props or how you stop a family using the room over an open pin will fail the temporary-works designer.

Typical scope

  • Designed sequence only
  • Rooms above excluded
  • No unplanned extra pins
  • Movement monitoring
  • Pins not left open overnight unless designed
  • Props as drawn

Quick answer

A mass-underpinning RAMS covers excavating and casting sequential pins under an existing foundation. Collapse of the building, confined pins and the occupants still living above are the critical harms.

Primary topic: underpinning rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.

What usually goes wrong

These are the operational gaps that make generic Word RAMS fail on the next site.

  • Foundations RAMS reused

    No sequence, no props.

  • Three pins open to ‘save time’

    Collapse.

  • Bedroom still used over pin 2

    Occupancy.

Example

Sequential pins under an occupied terrace

Built from one job description. You review and adjust every item before issuing it.

Job description

Mass-underpin the rear wall at 14 Alma Street, Sheffield. Temporary-works sequence, living room above closed, one pin at a time, no overnight open pin, movement readings AM and PM, family in the front rooms only.

Activities identified

  • General site work

Method (4 steps)

  1. 1.Arrive and sign in. Arrive at 14 Alma Street, Sheffield, report to the Private homeowner site contact, sign in and complete any site induction.
  2. 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
  3. 3.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
  4. 4.Hand over and sign out. Hand over to the Private homeowner site contact, report anything outstanding and sign out.

Main risks (0 in total)

What to get right on this document

The sequence is the method

Do not get ahead.

The rooms above are closed

Written.

Monitor and stop

Triggers, not hope.

What this document has to cover

Underpinning is temporary works under a live structure, not a footing pour. A foundations RAMS that never mentions the sequence, props or how you stop a family using the room over an open pin will fail the temporary-works designer.

An underpinning rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.

Typical hazards to assess on this job

  • Building movement or collapse if pins are opened out of sequence
  • Excavation collapse in a narrow pin
  • Occupants over an open pin
  • Services in and under the wall
  • Wet concrete in a confined pin
  • Spoil undermining an adjacent pin

Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.

A method sequence that actually protects people

Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.

  • Confirm the temporary-works design and sequence — no extra pins ‘to get ahead’
  • Prop as designed; exclude the rooms above
  • Excavate pin 1 only; inspect; cast; do not leave an open pin overnight unless designed
  • Cure, then the next pin in the designed order
  • Monitor movement as specified; stop if triggers hit
  • Hand over records and remaining restrictions

Occupancy and other people

The house stays lived in. Write which rooms are out and that a child will play in a closed pin if you leave it open.

Substances and COSHH

An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:

  • Wet concrete
  • Bentonite if used
  • Diesel from a mini-digger

How SafeForJob helps

  • Describe this job in plain English and get suggested activities, risks and method steps
  • Edit every line before you download or issue
  • Reuse a previous RAMS and catch old client or site names
  • Attach or create COSHH assessments where hazardous substances appear

What this page is not

This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer underpinning rams document for a named job. You remain responsible for reviewing and issuing it.

Related reading

See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.

Related pages

All rams by job · RAMS by trade · Free RAMS generator

Questions

Is this piling?
Piles are a different machine and sequence. This is sequential mass pins.
Who owns temporary works?
A designer — do not invent a pin layout.
Can the family stay?
Only in rooms the design allows — write them.
Party wall?
Legal process sits with the client; do not undermine the neighbour off-sequence.