RAMS by job · UK
EICR testing RAMS
Carry out EICR or fault-finding with live testing risks separated from installation controls.
Typical scope
- Site and client named
- Critical isolations/access first
- People at risk identified
- Emergency arrangements
- Permit interfaces
- Clean handover
Carry out EICR or fault-finding with live testing risks separated from installation controls. Change the access, occupancy and services and the controls should change with them.
Quick answer
A eicr method statement is a site-specific risk assessment and method statement for that task. It should name the site, the people at risk, the critical controls (often isolation, access or segregation), and the order of work — not a generic trade paragraph.
Primary topic: eicr method statement. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.
What usually goes wrong
These are the operational gaps that make generic Word RAMS fail on the next site.
Copied from last site
Client and site names, access routes and permits still describe the previous job.
Sequence wrong
Critical controls happen after the risk is already present.
Interfaces missing
Other trades, the public or building users are not briefed in the method.
Example
EICR and electrical testing on a live site
Built from one job description. You review and adjust every item before issuing it.
Job description
Carry out EICR or fault-finding with live testing risks separated from installation controls. Include access equipment, who else is on site, and how you leave the area safe at the end of the shift.
Activities identified
- General site work
- Electrical testing
- Manual handling
Method (7 steps)
- 1.Arrive and sign in. Arrive at Example UK site, report to the Example client Ltd site contact, sign in and complete any site induction.
- 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
- 3.Disconnect and remove existing equipment. Disconnect and remove the existing equipment. Lower or carry it using mechanical aids or team lifts as planned.
- 4.Install new equipment. Position and fix the new equipment to the manufacturer's instructions.
- 5.Test and commission. Test and commission the installation. Record results.
- 6.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
- 7.Hand over and sign out. Hand over to the Example client Ltd site contact, report anything outstanding and sign out.
Main risks (2 in total)
Electric shock during testing
Residual HighWho: Operatives
- Test dead wherever possible; live testing only where essential
- GS38-compliant test leads and probes, inspected before use
- Barriers or screens to prevent others approaching exposed live parts
- Testing carried out by competent persons only
- Insulated gloves and eye protection where there is an arc-flash risk
Manual handling
Residual MediumWho: Operatives
- Use mechanical aids (trolleys, sack trucks, hoists) for heavy items
- Team lifts for items too heavy or awkward for one person
- Route planned and cleared before moving items
- Operatives trained in safe lifting techniques
- Gloves with good grip and safety footwear
What to get right on this document
Make the critical control obvious
If isolation, service location or edge protection is the difference between safe and unsafe, put it early in the method.
Write the occupancy
Occupied homes, retail, healthcare and warehouses each need different public-interface controls.
Close the job out
Testing, reinstatement, waste and handover belong in the document, not in someone's head.
Quick answer
A eicr method statement is a site-specific risk assessment and method statement for that task. It should name the site, the people at risk, the critical controls (often isolation, access or segregation), and the order of work — not a generic trade paragraph.
What good looks like on a UK site
Carry out EICR or fault-finding with live testing risks separated from installation controls. Change the access, occupancy and services and the controls should change with them. Name the site, the people at risk, and the sequence that keeps them safe. Generic paragraphs that could apply anywhere are the first thing a principal contractor rejects.
How SafeForJob helps
- Describe the job in plain English and get suggested activities, risks and method steps
- Edit every line before you download or issue
- Reuse a previous RAMS and catch old client or site names
- Attach or create COSHH assessments where hazardous substances appear
What this page is not
This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer eicr method statement document for a named job. You remain responsible for reviewing and issuing it.
Related reading
See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.
Related pages
- RAMS by tradeElectrical RAMSCreate a site-specific electrical RAMS online. Describe the job, review suggested risks like safe isolation and work at height, and download a professional PDF.
- GuidesWhat is a RAMS?RAMS means risk assessment and method statement — usually one site-specific pack for a construction or maintenance job. Practical UK guidance for contractors — with links to free tools.
- Method statementsConstruction method statementWrite a construction method statement for a named UK site. Clear sequence, interfaces and controls — review before issue.
- RAMS by jobConsumer unit replacement RAMSCreate a consumer unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEV charger installation RAMSCreate a ev charger installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobLighting rewire RAMSCreate a lighting rewire rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobRooftop condenser replacement RAMSCreate a rooftop ac unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobSplit system installation RAMSCreate a split system installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobHeat pump installation RAMSCreate a heat pump installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
Questions
- What should a eicr method statement include?
- Job description, site, hazards and who is affected, controls, step-by-step method, and emergency arrangements — specific to this location.
- Can I reuse last month's RAMS?
- Reuse the structure, but update site names, access, occupancy and anything that would look stale to a client.
- Is this legally approved?
- No. It is a drafting aid. You review and issue the document under your competence and contract duties.