Resin flooring method statement
A paint method that never mentions the grind, the hardener or other trades walking tack will fail. Resin is a system with a clock.
Typical scope
- Cleanliness hold point
- Extract on the grind
- Two SDS, specified gloves
- Cure exclusion
- Ignition if solvent
- Traffic time from the system
Quick answer
A resin-flooring method statement is the sequence for preparing and laying a specified resin system on a named floor: grinding silica, two-pack COSHH, cure exclusion and a reopen that is not guessed.
Primary topic: resin flooring method statement. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.
What usually goes wrong
These are the operational gaps that make generic Word RAMS fail on the next site.
Paint method reused
No grind, no hardener.
Cotton gloves on a pour
Sensitisation.
FLT through tack at 04:00
Tracks everywhere.
Example
Epoxy aisle in a live warehouse
Built from one job description. You review and adjust every item before issuing it.
Job description
Lay specified epoxy in aisle G at Pennine Logistics, Huddersfield. Night shift, aisle closed, grind with extract, both SDS, chemical-resistant gloves, tack-free before 05:00, FLT diversion via F.
Activities identified
- General site work
- Hot works
- Power tools
- Using chemicals or products
- Lone working
Method (8 steps)
- 1.Arrive and sign in. Arrive at Aisle G, Pennine Logistics, Huddersfield, report to the Pennine Logistics site contact, sign in and complete any site induction.
- 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
- 3.Obtain hot works permit. Obtain a hot works permit from the site. Remove or protect combustibles and place an extinguisher at the point of work.
- 4.Drill and fix. Mark out, then drill and fix using on-tool dust extraction. Check for hidden cables and pipes before drilling.
- 5.Braze joints. Braze joints under the hot works permit with nitrogen purge. Maintain the fire watch during and after the work.
- 6.Apply products. Apply products as described on the Safety Data Sheet and COSHH assessment, with ventilation and the specified PPE.
- 7.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
- 8.Hand over and sign out. Hand over to the Pennine Logistics site contact, report anything outstanding and sign out.
Main risks (6 in total)
Fire from hot works
Residual MediumWho: Operatives, building occupants
- Use cold-work methods (press-fit, mechanical joints) instead of hot works where possible
- Hot works permit obtained from the site before starting
- Combustibles removed or protected with fire-resistant blankets
- Suitable fire extinguisher at the point of work
- Fire watch maintained during work and for at least 60 minutes after finishing
- Fire-resistant gloves and eye/face protection
Fumes from hot works
Residual MediumWho: Operatives, people nearby
- Work in well-ventilated areas; local exhaust ventilation for welding
- Keep the head out of the fume plume
- Suitable RPE (face-fit tested) where ventilation isn't adequate
Hand and power tools
Residual LowWho: Operatives
- Battery or 110V tools used; no 230V tools on site without RCD protection
- Tools inspected before use and PAT tested where applicable
- Guards fitted and used as designed
- Eye protection and gloves suitable for the task
Noise and hand-arm vibration
Residual MediumWho: Operatives, people nearby
- Low-vibration, low-noise tools selected
- Trigger times limited and rotated between operatives
- Noisy work scheduled to reduce disruption to occupants
- Hearing protection worn where noise is high
+ 2 more risks in the full RAMS.
What to get right on this document
Two SDS
Resin and hardener.
The grind is silica
Extract.
Traffic time is a number
From the system.
What this document has to cover
A paint method that never mentions the grind, the hardener or other trades walking tack will fail. Resin is a system with a clock.
A resin flooring method statement only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.
Typical hazards to assess on this job
- Silica from grinding the slab
- Skin sensitisation from resin and hardener
- Vapour in a poorly ventilated hall
- Slips on tacky resin
- Ignition of solvent-borne systems
- Failed floor if you coat over contamination
Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.
A method sequence that actually protects people
Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.
- Hold point on cleanliness and moisture — stop if it fails
- Grind with extract; exclusion for silica
- Mix to the SDS ratios in a ventilated bay; specified gloves, not cotton
- Lay; exclude until tack-free for the specified time
- Ignition control if solvent
- Reopen only when the system will take a tyre or a shoe
Occupancy and other people
Warehouses and food halls stay in use around you. Write the closed aisle and that tacky resin in a fork-truck route is a claim.
Substances and COSHH
An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:
- Resin and hardener (two SDS)
- Grinding dust / silica
- Solvent if in the system
How SafeForJob helps
- Describe this job in plain English and get suggested activities, risks and method steps
- Edit every line before you download or issue
- Reuse a previous RAMS and catch old client or site names
- Attach or create COSHH assessments where hazardous substances appear
What this page is not
This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer resin flooring method statement document for a named job. You remain responsible for reviewing and issuing it.
Related reading
See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.
Related pages
- RAMS by jobCar-park deck coating RAMSCreate a car park deck coating rams for a named UK site. Unique hazards, method sequence and occupancy notes you review before issue.
- GuidesHow to write a method statementA practical sequence for writing a method statement that a principal contractor will actually read.
- RAMS by tradePainting & decorating RAMSCreate painting decorating rams online for UK sites. Suggested risks and method steps matched to the job — you review every item before issue.
- Method statementsMethod statement for electrical worksWrite a method statement for electrical works for a named UK site. Clear sequence, interfaces and controls — review before issue.
- Method statementsHVAC installation method statementWrite a hvac installation method statement for a named UK site. Clear sequence, interfaces and controls — review before issue.
- Method statementsPlumbing method statementWrite a plumbing method statement for a named UK site. Clear sequence, interfaces and controls — review before issue.
- Method statementsRoofing method statementWrite a roofing method statement for a named UK site. Clear sequence, interfaces and controls — review before issue.
- Method statementsExcavation method statementWrite a excavation method statement for a named UK site. Clear sequence, interfaces and controls — review before issue.
- Method statementsFit-out method statementWrite a fit out method statement for a named UK site. Clear sequence, interfaces and controls — review before issue.
Questions
- Is this MMA car-park deck?
- MMA is a different COSHH and odour story. Write the actual resin.
- Isocyanates in the finish?
- Write the actual product — PU changes COSHH.
- SDS pasted as COSHH?
- Clients reject that. Assess the task.
- Food factory?
- Add hygiene zoning and a catch on glass-risk lights.