Method statement · UK
Modular building siting method statement
A mobile-crane method that never mentions the pad, fire exits of the unit, or pupils at a fence is only half the job. A module is a building delivered on a hook.
Typical scope
- Lift plan and appointed person
- Designed pad
- Hard exclusion that holds
- Immediate stability
- Services isolated for connect
- Fire exits before first use
Quick answer
A modular-siting method statement is the sequence for lifting and setting a prefabricated unit on a named pad: appointed person, designed bearers, exclusion, and services connected isolated.
Primary topic: modular siting method statement. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.
What usually goes wrong
These are the operational gaps that make generic Word RAMS fail on the next site.
Crane method with no pad
Unit on made ground.
Pupils at the fence for a look
Radius.
Steps ‘tomorrow’, staff in today
Fall at the door.
Example
Classroom module on a live primary
Built from one job description. You review and adjust every item before issuing it.
Job description
Land a double classroom at Trent Valley School, Newark, inset day. 80 t mobile, appointed person, playground closed, designed pads, immediate stability, electric and water isolated for connect, fire exits before the caretaker walk-round.
Activities identified
- General site work
- Electrical isolation
- Occupied premises or public areas
Method (8 steps)
- 1.Arrive and sign in. Arrive at Trent Valley School, Newark, report to the Trent Valley School site contact, sign in and complete any site induction.
- 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
- 3.Set up the work area. Set up barriers and signage around the work area and keep it clear of other people.
- 4.Isolate the electrical supply. Identify the relevant circuit, isolate, lock off and tag. Prove dead with an approved voltage indicator, proved before and after use.
- 5.Carry out electrical work. Carry out the electrical work on the isolated circuit to BS 7671.
- 6.Remove isolation and re-energise. Confirm the work is complete and everyone is clear, remove locks and re-energise.
- 7.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
- 8.Hand over and sign out. Hand over to the Trent Valley School site contact, report anything outstanding and sign out.
Main risks (2 in total)
Electric shock or burns
Residual MediumWho: Operatives, building occupants
- Work carried out dead — no live working
- Safe isolation: isolate, lock off, tag, and prove dead with an approved voltage indicator (GS38) proved before and after
- Only competent, qualified electricians carry out electrical work
- Permit to work obtained where the site requires one
- Personal locks and keys retained by the person working
Members of the public and building occupants
Residual LowWho: Public, customers, staff, residents
- Work area segregated with barriers and clear signage
- Work timed for quieter periods where possible, agreed with the site
- Tools and materials never left unattended in public areas
- Site contact informed of work areas and any disruption
What to get right on this document
The pad is temporary works
Do not guess it.
The radius includes the fence
Push exclusion out.
Exits before use
A module is a building.
What this document has to cover
A mobile-crane method that never mentions the pad, fire exits of the unit, or pupils at a fence is only half the job. A module is a building delivered on a hook.
A modular siting method statement only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.
Typical hazards to assess on this job
- Dropped module or crane overturn
- People in the radius — pupils, staff, deliveries
- Collapse of a pad that was never designed
- Services connected live
- Fire strategy of the host site changed by the unit’s position
- Steps missing so first users fall at the door
Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.
A method sequence that actually protects people
Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.
- Lift plan, appointed person and a hard exclusion
- Confirm the pad and bearers as designed before the hook comes on
- Lift, land, immediately make the unit stable
- Connect services isolated; test; no live tails
- Set steps, guards and fire exits before anyone ‘has a look’ inside
- Hand over load, fire exits and remaining punch-list exclusion
Occupancy and other people
Schools and hospitals stay occupied around the plot. Write the closed playground and that a parent at the fence is still in the radius.
Substances and COSHH
An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:
- Diesel from the crane
- Sealants at service penetrations
- Treated timber bearers
How SafeForJob helps
- Describe this job in plain English and get suggested activities, risks and method steps
- Edit every line before you download or issue
- Reuse a previous RAMS and catch old client or site names
- Attach or create COSHH assessments where hazardous substances appear
What this page is not
This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer modular siting method statement document for a named job. You remain responsible for reviewing and issuing it.
Related reading
See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.
Related pages
- RAMS by jobModular building siting RAMSCreate a modular building rams for a named UK site. Unique hazards, method sequence and occupancy notes you review before issue.
- GuidesHow to write a method statementA practical sequence for writing a method statement that a principal contractor will actually read.
- RAMS by tradeHighways RAMSCreate street works method statement online for UK sites. Suggested risks and method steps matched to the job — you review every item before issue.
- Method statementsMethod statement for electrical worksWrite a method statement for electrical works for a named UK site. Clear sequence, interfaces and controls — review before issue.
- Method statementsHVAC installation method statementWrite a hvac installation method statement for a named UK site. Clear sequence, interfaces and controls — review before issue.
- Method statementsPlumbing method statementWrite a plumbing method statement for a named UK site. Clear sequence, interfaces and controls — review before issue.
- Method statementsRoofing method statementWrite a roofing method statement for a named UK site. Clear sequence, interfaces and controls — review before issue.
- Method statementsExcavation method statementWrite a excavation method statement for a named UK site. Clear sequence, interfaces and controls — review before issue.
- Method statementsFit-out method statementWrite a fit out method statement for a named UK site. Clear sequence, interfaces and controls — review before issue.
Questions
- Is this only a lifting method?
- The lift plan sits in this sequence; the pad, services and school occupancy are why it is siting.
- Who designs the pad?
- A temporary-works designer — do not use sleepers as improvisation.
- Can pupils stay on site?
- Only if the exclusion holds.
- Planning / building control?
- Usually yes — this method does not replace that.