Modular building siting RAMS

A module is a building delivered on a hook, not a container dropped in a yard. A mobile-crane RAMS that never mentions the pad, connections or how you keep pupils out of the radius will fail the headteacher.

Typical scope

  • Lift plan and appointed person
  • Designed pad
  • Hard exclusion that holds
  • Immediate stability on landing
  • Services isolated for connect
  • Fire exits before first use

Quick answer

A modular-building-siting RAMS covers lifting and setting a prefabricated classroom, office or welfare unit on a named plot. The lift, temporary works under the unit, and the school or yard still in use are the critical controls.

Primary topic: modular building rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.

What usually goes wrong

These are the operational gaps that make generic Word RAMS fail on the next site.

  • Crane RAMS reused with no pad

    Unit on made ground.

  • Pupils at the fence for a look

    Radius.

  • Steps ‘tomorrow’, staff in today

    Fall at the door.

Example

Classroom module on a live primary

Built from one job description. You review and adjust every item before issuing it.

Job description

Land a double classroom at Millfield Primary, Norwich, inset day. 80 t mobile, appointed person, playground closed, designed pads, immediate stability, electric and water isolated for connect, fire exits before the caretaker walk-round, parents kept at the far gate.

Activities identified

  • General site work
  • Electrical isolation

Method (7 steps)

  1. 1.Arrive and sign in. Arrive at Millfield Primary, Norwich, report to the Millfield Primary site contact, sign in and complete any site induction.
  2. 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
  3. 3.Isolate the electrical supply. Identify the relevant circuit, isolate, lock off and tag. Prove dead with an approved voltage indicator, proved before and after use.
  4. 4.Carry out electrical work. Carry out the electrical work on the isolated circuit to BS 7671.
  5. 5.Remove isolation and re-energise. Confirm the work is complete and everyone is clear, remove locks and re-energise.
  6. 6.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
  7. 7.Hand over and sign out. Hand over to the Millfield Primary site contact, report anything outstanding and sign out.

Main risks (1 in total)

Electric shock or burns

Residual Medium

Who: Operatives, building occupants

  • Work carried out dead — no live working
  • Safe isolation: isolate, lock off, tag, and prove dead with an approved voltage indicator (GS38) proved before and after
  • Only competent, qualified electricians carry out electrical work
  • Permit to work obtained where the site requires one
  • Personal locks and keys retained by the person working

What to get right on this document

The pad is temporary works

Do not guess it.

The radius includes the fence

Push exclusion out.

Exits before use

A module is a building.

What this document has to cover

A module is a building delivered on a hook, not a container dropped in a yard. A mobile-crane RAMS that never mentions the pad, connections or how you keep pupils out of the radius will fail the headteacher.

A modular building rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.

Typical hazards to assess on this job

  • Dropped module or crane overturn
  • People in the radius — pupils, staff, deliveries
  • Collapse of temporary supports or a pad that was never designed
  • Services connections — electric, water, drainage — done live
  • Fire strategy of the host site changed by the unit’s position
  • Public at a school boundary during the lift

Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.

A method sequence that actually protects people

Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.

  • Lift plan, appointed person and a hard exclusion — school in assembly or off-site if required
  • Confirm the pad and bearers as designed before the hook comes on
  • Lift, land, immediately make the unit stable — no parked module on two corners
  • Connect services isolated; test; do not leave tails live
  • Set steps, guards and fire exits before anyone ‘has a look’ inside
  • Hand over load, fire exits and remaining exclusion if punch-list remains

Occupancy and other people

Schools and hospitals stay occupied around the plot. Write the closed playground and that a parent at the fence is still in the radius if you have not pushed the exclusion out.

Substances and COSHH

An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:

  • Diesel from the crane
  • Sealants at service penetrations
  • Treated timber bearers

How SafeForJob helps

  • Describe this job in plain English and get suggested activities, risks and method steps
  • Edit every line before you download or issue
  • Reuse a previous RAMS and catch old client or site names
  • Attach or create COSHH assessments where hazardous substances appear

What this page is not

This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer modular building rams document for a named job. You remain responsible for reviewing and issuing it.

Related reading

See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.

Related pages

All rams by job · RAMS by trade · Free RAMS generator

Questions

Is this a crane lift RAMS?
The lift plan sits in this sequence; the pad, services and school occupancy are why it is a siting RAMS.
Who designs the pad?
A temporary-works designer — do not use sleepers as improvisation.
Can pupils stay on site?
Only if the exclusion holds — write assembly or off-site if it does not.
Planning / building control?
Usually yes — the RAMS does not replace that.