Method statement · UK

Lifting operations method statement

‘Use a crane’ is not a method. The sequence should match the lift plan drawing.

Typical scope

  • Appointed person
  • Exclusion
  • Tackle inspection
  • Weather limit
  • Radios
  • Landing

Quick answer

A lifting operations method statement is the sequence that makes a lift plan happen on the day: exclusion, communications, weather abort and landing.

Primary topic: lifting operations method statement. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.

What usually goes wrong

These are the operational gaps that make generic Word RAMS fail on the next site.

  • Plan not attached

    Crew improvises.

  • People walking the radius

    No lookout.

  • Wind ignored

    No abort.

Example

Roof plant lift over a car park

Built from one job description. You review and adjust every item before issuing it.

Job description

Sunday crane lift of a chiller over a retail car park — exclusion, appointed person, wind limit.

Activities identified

  • General site work
  • Refrigerant handling
  • Lifting operations
  • Plant and vehicle movement
  • Occupied premises or public areas
  • Outdoor or exposed work

Method (11 steps)

  1. 1.Arrive and sign in. Arrive at Plant deck over car park, report to the Retail FM site contact, sign in and complete any site induction.
  2. 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
  3. 3.Set up the work area. Set up barriers and signage around the work area and keep it clear of other people.
  4. 4.Carry out the lift. Carry out lifts to the lift plan, with the exclusion zone in place and a trained slinger/signaller directing.
  5. 5.Recover refrigerant. Recover the refrigerant into a correctly rated, labelled recovery cylinder. Record quantities in line with F-gas requirements.
  6. 6.Install new equipment. Position and fix the new equipment to the manufacturer's instructions.
  7. 7.Pressure test and evacuate. Pressure test with oxygen-free nitrogen, then evacuate the system before charging.
  8. 8.Charge the system. Charge the system with refrigerant to the manufacturer's specification and leak test all joints.
  9. 9.Test and commission. Test and commission the installation. Record results.
  10. 10.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
  11. 11.Hand over and sign out. Hand over to the Retail FM site contact, report anything outstanding and sign out.

Main risks (6 in total)

Refrigerant release

Residual Low

Who: Engineers, building occupants

  • Refrigerant handled only by F-gas certified engineers
  • Refrigerant recovered into correctly rated, labelled recovery cylinders — never vented
  • Good ventilation; no recovery work in enclosed spaces without assessment
  • No ignition sources near flammable (A2L/A3) refrigerants; leak detector in use
  • Cryogenic-rated gloves and eye protection when connecting hoses

Stored pressure

Residual Low

Who: Engineers

  • Systems depressurised and drained down before breaking into pipework
  • Gauges, hoses and valves inspected and rated for the system pressure
  • Cylinders secured upright and transported with valves protected
  • Eye protection worn when connecting or venting

Lifting operations

Residual Medium

Who: Operatives, public, other trades

  • Lift planned by a competent person; lift plan in place
  • Lifting equipment and accessories have current LOLER thorough examination
  • Exclusion zone below the lift; nobody under suspended loads
  • Trained slinger/signaller directs the lift
  • Lifts stopped in high winds

Moving vehicles and plant

Residual Medium

Who: Operatives, public, site staff

  • Pedestrians segregated from vehicle and plant routes
  • Plant operated by trained, authorised operators only
  • Banksman used for reversing and manoeuvring
  • High-visibility clothing worn

+ 2 more risks in the full RAMS.

What to get right on this document

Attach the plan

The method is the plan in words.

Exclusion first

Before the hook is busy.

Abort criteria

Wind, visibility, comms failure.

What this document has to cover

‘Use a crane’ is not a method. The sequence should match the lift plan drawing.

A lifting operations method statement only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.

Typical hazards to assess on this job

  • Dropped load
  • Crushing
  • Overturn
  • Public below
  • Wind

Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.

A method sequence that actually protects people

Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.

  • Brief the lift plan
  • Set exclusion and radios
  • Inspect lifting tackle
  • Trial lift if required
  • Lift, travel, land
  • Break exclusion only when slings are slack and load stable

Occupancy and other people

If the radius covers a road or car park, that exclusion is the method.

Substances and COSHH

An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:

  • None typically
  • Hydraulic oil

How SafeForJob helps

  • Describe this job in plain English and get suggested activities, risks and method steps
  • Edit every line before you download or issue
  • Reuse a previous RAMS and catch old client or site names
  • Attach or create COSHH assessments where hazardous substances appear

What this page is not

This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer lifting operations method statement document for a named job. You remain responsible for reviewing and issuing it.

Related reading

See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.

Related pages

All method statements · RAMS by trade · Free RAMS generator

Questions

Is LOLER a RAMS?
LOLER is the law; this method shows how you will meet it on this lift.
Hired crane?
The RAMS still needs your exclusion and interface.
Tandem lifts?
Specialist — do not reuse a simple lift method.
People as lookouts?
Named, with radios.