Method statement · UK
Lightning protection method statement
An earthing-upgrade method that never goes on the roof, or a rooftop-antenna method that never mentions the lightning standard or a storm abort, is the wrong document.
Typical scope
- Design attached
- Storm abort
- Roof access named
- Bonds only at designed points
- Test values recorded
- Exclusion below
Quick answer
A lightning-protection method statement is the sequence for installing or testing air terminals, down conductors and bonds on a named structure. Roof edge, storm abort, and not improvising a bond on a gas service are the controls.
Primary topic: lightning protection method statement. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.
What usually goes wrong
These are the operational gaps that make generic Word RAMS fail on the next site.
Earthing-pit method reused
No roof, no air terminals.
Bond clamped to a gas meter as a shortcut
Wrong point.
Stayed up because ‘the cell was still distant’
Storm abort ignored.
Example
Down-conductor on a plant deck
Built from one job description. You review and adjust every item before issuing it.
Job description
Install a specified down-conductor on the plant deck at Parkside Health Centre, Bedford. Edge protection, storm abort, bonds to the specified bar only, values recorded, west entrance exclusion, roof door locked behind the team.
Activities identified
- General site work
- Roof work
- Manual handling
Method (8 steps)
- 1.Arrive and sign in. Arrive at Plant deck, Parkside Health Centre, Bedford, report to the Parkside Health Centre site contact, sign in and complete any site induction.
- 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
- 3.Set up exclusion zone below. Establish an exclusion zone below the work area with barriers and signage before any work at height starts.
- 4.Access the roof. Access the roof via the agreed route. Confirm edge protection is in place and identify any fragile areas before moving onto the roof.
- 5.Disconnect and remove existing equipment. Disconnect and remove the existing equipment. Lower or carry it using mechanical aids or team lifts as planned.
- 6.Install new equipment. Position and fix the new equipment to the manufacturer's instructions.
- 7.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
- 8.Hand over and sign out. Hand over to the Parkside Health Centre site contact, report anything outstanding and sign out.
Main risks (5 in total)
Fall from roof edge
Residual MediumWho: Operatives
- Plan work to be done from below or from a MEWP where possible
- Edge protection (guard rails) or parapet of adequate height in place before work starts
- Safe access route to the roof agreed with the site; roof hatch secured open
- Where collective protection isn't possible, use a fall-restraint system with suitable anchors
- Work stops in high winds, ice or heavy rain
Fall through fragile roof or rooflight
Residual MediumWho: Operatives
- Treat all roof sheets and rooflights as fragile unless confirmed otherwise by the site
- Rooflights covered or protected with suitable mesh or barriers
- Staging or crawling boards used; no walking directly on sheets
- Safety netting or fall arrest below where required
Falling objects
Residual LowWho: People below, other trades, public
- Exclusion zone set up below the work area with barriers and signage
- Tools tethered when working at height; materials kept away from edges
- Banksman or second person controls the area during lifts and removals
- Hard hats worn in the exclusion zone
Adverse weather
Residual LowWho: Operatives
- Forecast checked before work; work at height stopped in high winds
- Breaks, water and shade in hot weather; warm clothing in cold
- Sun protection on exposed work in summer
+ 1 more risks in the full RAMS.
What to get right on this document
The design names the route
Do not invent down-conductors.
Storm is a stop
Write it.
The roof is height
Access as for any roof job.
What this document has to cover
An earthing-upgrade method that never goes on the roof, or a rooftop-antenna method that never mentions the lightning standard or a storm abort, is the wrong document.
A lightning protection method statement only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.
Typical hazards to assess on this job
- Falls from the roof or through fragile lights
- Electric shock when bonding to existing services
- Struck by lightning if you stay up in a storm
- Dropped tools onto the public
- Hot works or exothermic weld at a bond
- Wrong bond point on a gas or lightning-incompatible service
Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.
A method sequence that actually protects people
Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.
- Confirm the design, roof access and a storm abort before you go up
- Set edge protection or a harness system; exclusion below
- Install terminals and down conductors as drawn — do not invent a route down a fire-escape handrail
- Bond only at designed points; control hot works if used
- Test and record values
- Close the roof door; do not leave a propped access
Occupancy and other people
High streets and hospital loops have people at the base. Write the spotter and that a thunderstorm is a stop, not a race.
Substances and COSHH
An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:
- Exothermic welding powders if used
- Bitumen or sealants at roof penetrations
- Paint on clips
How SafeForJob helps
- Describe this job in plain English and get suggested activities, risks and method steps
- Edit every line before you download or issue
- Reuse a previous RAMS and catch old client or site names
- Attach or create COSHH assessments where hazardous substances appear
What this page is not
This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer lightning protection method statement document for a named job. You remain responsible for reviewing and issuing it.
Related reading
See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.
Related pages
- RAMS by jobEarthing upgrade RAMSCreate a earthing upgrade rams for a named UK site. Unique hazards, method sequence and occupancy notes you review before issue.
- GuidesHow to write a method statementA practical sequence for writing a method statement that a principal contractor will actually read.
- RAMS by tradeElectrical RAMSCreate a site-specific electrical RAMS online. Describe the job, review suggested risks like safe isolation and work at height, and download a professional PDF.
- Method statementsMethod statement for electrical worksWrite a method statement for electrical works for a named UK site. Clear sequence, interfaces and controls — review before issue.
- Method statementsHVAC installation method statementWrite a hvac installation method statement for a named UK site. Clear sequence, interfaces and controls — review before issue.
- Method statementsPlumbing method statementWrite a plumbing method statement for a named UK site. Clear sequence, interfaces and controls — review before issue.
- Method statementsRoofing method statementWrite a roofing method statement for a named UK site. Clear sequence, interfaces and controls — review before issue.
- Method statementsExcavation method statementWrite a excavation method statement for a named UK site. Clear sequence, interfaces and controls — review before issue.
- Method statementsFit-out method statementWrite a fit out method statement for a named UK site. Clear sequence, interfaces and controls — review before issue.
Questions
- Is this an earthing upgrade?
- Related earth, different air terminals and roof work. Use that RAMS for rods in the ground.
- Can I test in the rain?
- Moisture changes readings; abort in a storm.
- Who owns the existing LPS?
- The dutyholder — do not cut their conductor.
- Exothermic weld?
- Add hot-works control; many bonds are clamped.