Generator installation method statement

A UPS method never mentions diesel, a flue or a wet-stack. An LV-board method never lifts a 3 t set. If the sequence does not name the lift, bund and changeover, it is not a generator method.

Typical scope

  • Lift plan
  • All sources isolated
  • Bund and spill kit
  • Exhaust as designed
  • Load-owner transfer
  • E-stop handover

Quick answer

A generator-installation method statement is the sequence for landing, connecting and commissioning a named standby or prime generator: lift, fuel, exhaust, electrical isolation of the existing supply, and a test that does not surprise the load.

Primary topic: generator installation method statement. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.

What usually goes wrong

These are the operational gaps that make generic Word RAMS fail on the next site.

  • UPS method reused

    No fuel, no exhaust.

  • Test at 07:00 against bedrooms

    Noise occupancy.

  • Fuel line over a gully with no bund

    Pollution.

Example

400 kVA standby onto a live care home

Built from one job description. You review and adjust every item before issuing it.

Job description

Land a 400 kVA set at Oakwell Care Home, Barnsley. Sunday hoist, DNO isolation plus existing set lock-off, bunded base, exhaust as designed, spill kit, transfer test 14:00 with the manager, residents kept to the far wing.

Activities identified

  • General site work
  • Electrical isolation
  • Lifting operations
  • Occupied premises or public areas

Method (9 steps)

  1. 1.Arrive and sign in. Arrive at Oakwell Care Home, Barnsley, report to the Oakwell Care site contact, sign in and complete any site induction.
  2. 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
  3. 3.Set up the work area. Set up barriers and signage around the work area and keep it clear of other people.
  4. 4.Isolate the electrical supply. Identify the relevant circuit, isolate, lock off and tag. Prove dead with an approved voltage indicator, proved before and after use.
  5. 5.Carry out the lift. Carry out lifts to the lift plan, with the exclusion zone in place and a trained slinger/signaller directing.
  6. 6.Carry out electrical work. Carry out the electrical work on the isolated circuit to BS 7671.
  7. 7.Remove isolation and re-energise. Confirm the work is complete and everyone is clear, remove locks and re-energise.
  8. 8.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
  9. 9.Hand over and sign out. Hand over to the Oakwell Care site contact, report anything outstanding and sign out.

Main risks (3 in total)

Electric shock or burns

Residual Medium

Who: Operatives, building occupants

  • Work carried out dead — no live working
  • Safe isolation: isolate, lock off, tag, and prove dead with an approved voltage indicator (GS38) proved before and after
  • Only competent, qualified electricians carry out electrical work
  • Permit to work obtained where the site requires one
  • Personal locks and keys retained by the person working

Lifting operations

Residual Medium

Who: Operatives, public, other trades

  • Lift planned by a competent person; lift plan in place
  • Lifting equipment and accessories have current LOLER thorough examination
  • Exclusion zone below the lift; nobody under suspended loads
  • Trained slinger/signaller directs the lift
  • Lifts stopped in high winds

Members of the public and building occupants

Residual Low

Who: Public, customers, staff, residents

  • Work area segregated with barriers and clear signage
  • Work timed for quieter periods where possible, agreed with the site
  • Tools and materials never left unattended in public areas
  • Site contact informed of work areas and any disruption

What to get right on this document

Every source is isolated

Mains, set, UPS.

The load owner agrees the transfer

Named.

Fuel is COSHH and pollution

Bund and spill.

What this document has to cover

A UPS method never mentions diesel, a flue or a wet-stack. An LV-board method never lifts a 3 t set. If the sequence does not name the lift, bund and changeover, it is not a generator method.

A generator installation method statement only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.

Typical hazards to assess on this job

  • Dropped set on the lift
  • Electric shock on mains, generator and any UPS back-feed
  • Fuel spill to drains
  • Exhaust into an occupied intake or a neighbour
  • Noise at an occupied site during test
  • Unexpected load transfer

Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.

A method sequence that actually protects people

Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.

  • Lift plan and exclusion before the set leaves the trailer
  • Isolate mains, generator and alternative sources; prove dead
  • Land on the specified base/bund; connect fuel with spill kit
  • Exhaust and attenuation as designed — do not invent a route into a courtyard
  • Commission, including a planned transfer with the load owner present
  • Hand over isolation, emergency stop and spill briefing

Occupancy and other people

Hospitals and blocks cannot lose power as a surprise. Write who owns the test window and that a wet-stack test at 07:00 next to bedrooms is occupancy.

Substances and COSHH

An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:

  • Diesel / gas oil
  • Coolant / glycol
  • Battery electrolyte on the start batteries

How SafeForJob helps

  • Describe this job in plain English and get suggested activities, risks and method steps
  • Edit every line before you download or issue
  • Reuse a previous RAMS and catch old client or site names
  • Attach or create COSHH assessments where hazardous substances appear

What this page is not

This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer generator installation method statement document for a named job. You remain responsible for reviewing and issuing it.

Related reading

See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.

Related pages

All method statements · RAMS by trade · Free RAMS generator

Questions

Is this a UPS install?
Related resilience, different fuel and exhaust. Use this for the set.
Gas as fuel?
Write the actual fuel — gas competence and tightness differ.
Who talks to the DNO?
Name them.
Load-bank instead of building load?
Write it — still noise, exhaust and spill.