LV switchgear replacement RAMS
This is not a consumer-unit change. You are on a three-phase incoming, often with a generator or UPS interface, and a temporary-power RAMS that never names the authorised person or the lift will fail.
Typical scope
- AP isolation of all sources
- Life-safety during the outage
- Panel lift plan
- Torque and labels
- Tests before energise
- Updated drawing at handover
Quick answer
An LV switchgear replacement RAMS covers swapping a main or sub-main board on a named site. Isolation of the incoming supply, lifting the panel, and the building that must stay safe in the dark are the critical controls.
Primary topic: lv switchgear replacement rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.
What usually goes wrong
These are the operational gaps that make generic Word RAMS fail on the next site.
CU RAMS reused
Wrong incoming, no AP.
Generator left as a back-feed
Not isolated.
No temporary lights in the stair
Residents in the dark.
Example
Main LV swap in a care home
Built from one job description. You review and adjust every item before issuing it.
Job description
Replace the main LV panel at Beechcroft Care, Harrogate. Sunday 05:00–14:00, DNO isolation plus generator lock-off, temporary emergency lighting, panel on skates with a four-person plan, torque sheets, residents kept on the ground floor.
Activities identified
- General site work
- Electrical isolation
- Manual handling
- Occupied premises or public areas
- Fire alarm or security systems
Method (12 steps)
- 1.Arrive and sign in. Arrive at Beechcroft Care, Harrogate, report to the Beechcroft Care site contact, sign in and complete any site induction.
- 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
- 3.Set up the work area. Set up barriers and signage around the work area and keep it clear of other people.
- 4.Isolate the electrical supply. Identify the relevant circuit, isolate, lock off and tag. Prove dead with an approved voltage indicator, proved before and after use.
- 5.Agree fire system isolations. Agree with the responsible person which zones will be isolated and for how long. Put agreed fire-watch arrangements in place.
- 6.Disconnect and remove existing equipment. Disconnect and remove the existing equipment. Lower or carry it using mechanical aids or team lifts as planned.
- 7.Install or replace devices. Install or replace detectors, sounders or security devices in the isolated zones.
- 8.Install new equipment. Position and fix the new equipment to the manufacturer's instructions.
- 9.Restore fire system. Restore all isolated zones, test the system, inform the responsible person and update the log book.
- 10.Remove isolation and re-energise. Confirm the work is complete and everyone is clear, remove locks and re-energise.
- 11.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
- 12.Hand over and sign out. Hand over to the Beechcroft Care site contact, report anything outstanding and sign out.
Main risks (4 in total)
Electric shock or burns
Residual MediumWho: Operatives, building occupants
- Work carried out dead — no live working
- Safe isolation: isolate, lock off, tag, and prove dead with an approved voltage indicator (GS38) proved before and after
- Only competent, qualified electricians carry out electrical work
- Permit to work obtained where the site requires one
- Personal locks and keys retained by the person working
Manual handling
Residual MediumWho: Operatives
- Use mechanical aids (trolleys, sack trucks, hoists) for heavy items
- Team lifts for items too heavy or awkward for one person
- Route planned and cleared before moving items
- Operatives trained in safe lifting techniques
- Gloves with good grip and safety footwear
Members of the public and building occupants
Residual LowWho: Public, customers, staff, residents
- Work area segregated with barriers and clear signage
- Work timed for quieter periods where possible, agreed with the site
- Tools and materials never left unattended in public areas
- Site contact informed of work areas and any disruption
Fire alarm or protection out of service
Residual MediumWho: Building occupants
- Responsible person informed and isolations agreed before any part of the system is disabled
- Only the zones being worked on are isolated, for the shortest possible time
- Fire watch or alternative arrangements while protection is reduced
- System fully restored and tested before leaving; log book updated
What to get right on this document
Every source is isolated
Mains, genny, UPS.
The building still needs light
Temporary, agreed.
The panel is a lift
Plan, not a slide across the floor.
What this document has to cover
This is not a consumer-unit change. You are on a three-phase incoming, often with a generator or UPS interface, and a temporary-power RAMS that never names the authorised person or the lift will fail.
A lv switchgear replacement rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.
Typical hazards to assess on this job
- Electric shock and arc flash on an incoming that was not isolated
- Dropped panel crushing people in a tight plant room
- Building-wide blackout affecting life-safety circuits
- Stored energy in capacitors and UPS back-feeds
- Other trades walking into a dark stair
- Incorrect labelling so the next person isolates the wrong board
Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.
A method sequence that actually protects people
Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.
- Authorised person agrees the outage, isolates incoming and alternative sources, proves dead
- Set temporary lighting and life-safety provisions the client has approved
- Lift out the old panel; land the new one with a handling plan
- Terminate, torque, label, and keep covers on any live remainder
- Test, including earth and insulation, before re-energising
- Hand over drawings, labels and the remaining defects
Occupancy and other people
Care homes and blocks lose lifts and emergency lighting if you have not planned the outage. Write the hours, the temporary lights, and who walks the building in the dark.
Substances and COSHH
An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:
- Cleaning solvents on copper
- Grease on mechanisms
- Paint on new cubicles
How SafeForJob helps
- Describe this job in plain English and get suggested activities, risks and method steps
- Edit every line before you download or issue
- Reuse a previous RAMS and catch old client or site names
- Attach or create COSHH assessments where hazardous substances appear
What this page is not
This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer lv switchgear replacement rams document for a named job. You remain responsible for reviewing and issuing it.
Related reading
See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.
Related pages
- RAMS by tradeElectrical RAMSCreate a site-specific electrical RAMS online. Describe the job, review suggested risks like safe isolation and work at height, and download a professional PDF.
- GuidesWhat is a RAMS?RAMS means risk assessment and method statement — usually one site-specific pack for a construction or maintenance job. Practical UK guidance for contractors — with links to free tools.
- Method statementsMethod statement for electrical worksWrite a method statement for electrical works for a named UK site. Clear sequence, interfaces and controls — review before issue.
- RAMS by jobConsumer unit replacement RAMSCreate a consumer unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEV charger installation RAMSCreate a ev charger installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobLighting rewire RAMSCreate a lighting rewire rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEICR testing RAMSCreate a eicr method statement for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobRooftop condenser replacement RAMSCreate a rooftop ac unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobSplit system installation RAMSCreate a split system installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
Questions
- Is this the same as a three-phase board?
- Related, but incoming isolation, AP and building life-safety are heavier here.
- Who talks to the DNO?
- Name them — the RAMS should not assume a card in the van.
- Can we run on the generator?
- Only if the changeover is designed and isolated from the work. Write it.
- Old asbestos panel board?
- Survey before drilling or cutting a 1960s cubicle.