Method statement · UK
Fire-rated partitions method statement
A drylining method that never names the fire rating, the tested detail at the head, or how you leave an unfinished run will fail the fire engineer. This is a compartment, not a room divider.
Typical scope
- Specified system named
- Tested head/foot detail
- Same-visit close or approved temporary seal
- Photos before cover-up
- Escape kept
- Other-trade brief
Quick answer
A fire-rated-partition method statement is the sequence for building a specified fire-resisting wall on a named line: board type, penetrations closed the same visit, and not leaving a compartment open overnight.
Primary topic: fire rated partition method statement. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.
What usually goes wrong
These are the operational gaps that make generic Word RAMS fail on the next site.
Drylining method reused
No rating, no head detail.
Hole left overnight for cables
Compartment open.
Generic plasterboard in a 60-minute wall
Wrong board.
Example
Corridor compartment on a live office floor
Built from one job description. You review and adjust every item before issuing it.
Job description
Build a specified 60-minute partition on level 4 at Quayside Place, Leeds. Saturday, tested head detail, mineral wool as drawn, penetrations sealed the same visit, photos in the fire file, escape via the east stair.
Activities identified
- General site work
Method (4 steps)
- 1.Arrive and sign in. Arrive at Level 4, Quayside Place, Leeds, report to the Quayside Place FM site contact, sign in and complete any site induction.
- 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
- 3.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
- 4.Hand over and sign out. Hand over to the Quayside Place FM site contact, report anything outstanding and sign out.
Main risks (0 in total)
What to get right on this document
The rating is the method
Board, head, fixings.
Close the hole the same shift
Temporary seal if services are late.
Photograph the detail
Before it disappears.
What this document has to cover
A drylining method that never names the fire rating, the tested detail at the head, or how you leave an unfinished run will fail the fire engineer. This is a compartment, not a room divider.
A fire rated partition method statement only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.
Typical hazards to assess on this job
- Spread of fire or smoke through an open or wrongly boarded run
- Wrong board or omitted mineral wool at the head
- Penetrations left open for ‘the electrician tomorrow’
- Dust and work at height in a live corridor
- Manual handling of boards
- Other trades breaking a sealed wall the same week
Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.
A method sequence that actually protects people
Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.
- Confirm the fire strategy drawing and the specified system for that wall
- Set local exclusion; protect detection if dusting
- Build to the tested detail — head, foot, board type, fixings
- Close penetrations the same visit or fit an approved temporary seal
- Label the wall; photograph details before they are covered
- Brief other trades not to punch the compartment
Occupancy and other people
Hospitals and offices stay in use. A corridor that is a fire route cannot be a board store. Write the remaining escape.
Substances and COSHH
An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:
- Fire boards and jointing compounds
- Mineral wool at heads and voids
- Fire-stopping at penetrations
How SafeForJob helps
- Describe this job in plain English and get suggested activities, risks and method steps
- Edit every line before you download or issue
- Reuse a previous RAMS and catch old client or site names
- Attach or create COSHH assessments where hazardous substances appear
What this page is not
This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer fire rated partition method statement document for a named job. You remain responsible for reviewing and issuing it.
Related reading
See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.
Related pages
- RAMS by jobFire board encasement RAMSCreate a fire board encasement rams for a named UK site. Unique hazards, method sequence and occupancy notes you review before issue.
- GuidesHow to write a method statementA practical sequence for writing a method statement that a principal contractor will actually read.
- RAMS by tradeFire & security RAMSCreate RAMS for fire alarm, CCTV and access control installation: system isolations, ceiling work, occupied buildings. Review every suggestion before issue.
- Method statementsMethod statement for electrical worksWrite a method statement for electrical works for a named UK site. Clear sequence, interfaces and controls — review before issue.
- Method statementsHVAC installation method statementWrite a hvac installation method statement for a named UK site. Clear sequence, interfaces and controls — review before issue.
- Method statementsPlumbing method statementWrite a plumbing method statement for a named UK site. Clear sequence, interfaces and controls — review before issue.
- Method statementsRoofing method statementWrite a roofing method statement for a named UK site. Clear sequence, interfaces and controls — review before issue.
- Method statementsExcavation method statementWrite a excavation method statement for a named UK site. Clear sequence, interfaces and controls — review before issue.
- Method statementsFit-out method statementWrite a fit out method statement for a named UK site. Clear sequence, interfaces and controls — review before issue.
Questions
- Is this fire-stopping?
- Fire-stopping is penetrations in an existing wall. This method is building the wall.
- Can I use any ‘fire board’?
- Only the system tested for that rating and construction.
- Who inspects?
- Usually the fire engineer or clerk of works against the record.
- Do I need a hot-works permit?
- Not for typical boarding. Cutting that generates heat or dust still needs control.