Fire board encasement RAMS

Encasement is a tested board system, not ‘two layers of plasterboard’. A drylining RAMS that never names the system, the steel schedule or how you close a box the same shift will fail the fire engineer.

Typical scope

  • Specified system named
  • Fixing centres as tested
  • Dust control
  • Same-shift close in occupation
  • Penetrations detailed
  • Escape kept

Quick answer

A fire-board encasement RAMS covers boxing steel or a service in a specified fire-resisting board system. The tested build-up, dust, and not leaving a steel unprotected overnight in an occupied building are the core.

Primary topic: fire board encasement rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.

What usually goes wrong

These are the operational gaps that make generic Word RAMS fail on the next site.

  • Drylining RAMS reused

    No system, no steel schedule.

  • One layer because ‘it looks enough’

    Not the tested build-up.

  • Beam left open Friday in an office

    Strategy hole.

Example

Beam encasement over a live office

Built from one job description. You review and adjust every item before issuing it.

Job description

Encase three beams on level 2 at Greyfriars House, Leicester, Saturday. Specified board system, centres as tested, M-class cutting, each beam closed before 16:00, desks sheeted, no decorative wrap until photographed.

Activities identified

  • General site work
  • Power tools
  • Painting and decorating

Method (6 steps)

  1. 1.Arrive and sign in. Arrive at Level 2, Greyfriars House, Leicester, report to the Greyfriars FM site contact, sign in and complete any site induction.
  2. 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
  3. 3.Drill and fix. Mark out, then drill and fix using on-tool dust extraction. Check for hidden cables and pipes before drilling.
  4. 4.Prepare and decorate. Protect floors and furniture, prepare surfaces and apply coatings by brush or roller with the room ventilated.
  5. 5.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
  6. 6.Hand over and sign out. Hand over to the Greyfriars FM site contact, report anything outstanding and sign out.

Main risks (3 in total)

Hand and power tools

Residual Low

Who: Operatives

  • Battery or 110V tools used; no 230V tools on site without RCD protection
  • Tools inspected before use and PAT tested where applicable
  • Guards fitted and used as designed
  • Eye protection and gloves suitable for the task

Noise and hand-arm vibration

Residual Medium

Who: Operatives, people nearby

  • Low-vibration, low-noise tools selected
  • Trigger times limited and rotated between operatives
  • Noisy work scheduled to reduce disruption to occupants
  • Hearing protection worn where noise is high

Solvent vapours and spray mist

Residual Medium

Who: Operatives, building occupants

  • Water-based, low-VOC products used where possible
  • Rooms ventilated; brush or roller preferred to spraying indoors
  • No smoking or naked flames near solvent-based products
  • Suitable RPE when spraying

What to get right on this document

Name the system

Layers and centres.

Close it the same shift

If people stay.

Dust is COSHH

Cut in a bay.

What this document has to cover

Encasement is a tested board system, not ‘two layers of plasterboard’. A drylining RAMS that never names the system, the steel schedule or how you close a box the same shift will fail the fire engineer.

A fire board encasement rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.

Typical hazards to assess on this job

  • Fire protection missing because the system was substituted
  • Dust from cutting boards in a live hall
  • Falls from podiums while boarding a beam
  • Unprotected steel left overnight in occupation
  • Services buried without a fire-stopping detail
  • Manual handling of boards in a stair used as an escape

Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.

A method sequence that actually protects people

Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.

  • Confirm the specified system and steel schedule before a board is cut
  • Set exclusion and dust control; keep an escape
  • Fix to the tested centres and layers — no skipped noggins
  • Close each member the same shift if the building stays occupied
  • Fire-stop penetrations as the system
  • Label and photograph; do not hide a thin box behind a decorative wrap

Occupancy and other people

Offices stay in use. Write the local exclusion and that an open box on a beam over a desk is a strategy hole until it is closed.

Substances and COSHH

An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:

  • Board fibres / dust
  • Joint compounds and sealants of the system
  • Fixing adhesives if used

How SafeForJob helps

  • Describe this job in plain English and get suggested activities, risks and method steps
  • Edit every line before you download or issue
  • Reuse a previous RAMS and catch old client or site names
  • Attach or create COSHH assessments where hazardous substances appear

What this page is not

This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer fire board encasement rams document for a named job. You remain responsible for reviewing and issuing it.

Related reading

See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.

Related pages

All rams by job · RAMS by trade · Free RAMS generator

Questions

Is this fire-stopping?
Stopping is penetrations. This is encasement of a member.
Can I use any fire board?
Only the tested system on the schedule.
Do I need a drylining RAMS too?
Only if you are also lining rooms — do not blur the fire box.
Who inspects?
Usually the fire engineer or clerk of works against photos and labels.