F-gas recovery method statement

A brazing method that never recovers, or an R32 COSHH sheet used as the whole method, will fail. Recovery is the step that stops a release; COSHH is not a method statement.

Typical scope

  • Competence and gas named
  • Recover, do not vent
  • Cylinder capacity
  • Prove residual before break-in
  • Occupier cooling outage
  • Recovered gas labelled

Quick answer

An F-gas recovery method statement is the sequence for recovering refrigerant from named equipment before opening the circuit: competence, recovery cylinder, residual pressure, and a live building that still needs cooling.

Primary topic: f gas recovery method statement. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.

What usually goes wrong

These are the operational gaps that make generic Word RAMS fail on the next site.

  • Brazing method with no recovery

    Release.

  • Kitchen cylinder with unknown residual

    Overfill.

  • R32 SDS taped in as the method

    SDS is not a method statement or a COSHH assessment.

Example

Recovery before an FCU swap

Built from one job description. You review and adjust every item before issuing it.

Job description

Recover R410A from FCU-07 on level 4, Ashlar House, Stamford. Saturday, competent person, dedicated recovery cylinder weighed in, electrics isolated, residual proved, occupier told cooling is off 08:00–14:00, recovered gas labelled.

Activities identified

  • General site work
  • Electrical isolation
  • Refrigerant handling
  • Manual handling
  • Plumbing and heating systems

Method (14 steps)

  1. 1.Arrive and sign in. Arrive at Level 4, Ashlar House, Stamford, report to the Ashlar House FM site contact, sign in and complete any site induction.
  2. 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
  3. 3.Isolate the electrical supply. Identify the relevant circuit, isolate, lock off and tag. Prove dead with an approved voltage indicator, proved before and after use.
  4. 4.Isolate and drain down. Isolate the water/heating supply, allow to cool and drain down the affected section. Confirm isolation before breaking into pipework.
  5. 5.Recover refrigerant. Recover the refrigerant into a correctly rated, labelled recovery cylinder. Record quantities in line with F-gas requirements.
  6. 6.Disconnect and remove existing equipment. Disconnect and remove the existing equipment. Lower or carry it using mechanical aids or team lifts as planned.
  7. 7.Install new equipment. Position and fix the new equipment to the manufacturer's instructions.
  8. 8.Install pipework. Install and connect pipework. Use press-fit or mechanical joints in place of hot works where possible.
  9. 9.Pressure test and evacuate. Pressure test with oxygen-free nitrogen, then evacuate the system before charging.
  10. 10.Charge the system. Charge the system with refrigerant to the manufacturer's specification and leak test all joints.
  11. 11.Test and commission. Test and commission the installation. Record results.
  12. 12.Remove isolation and re-energise. Confirm the work is complete and everyone is clear, remove locks and re-energise.
  13. 13.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
  14. 14.Hand over and sign out. Hand over to the Ashlar House FM site contact, report anything outstanding and sign out.

Main risks (5 in total)

Electric shock or burns

Residual Medium

Who: Operatives, building occupants

  • Work carried out dead — no live working
  • Safe isolation: isolate, lock off, tag, and prove dead with an approved voltage indicator (GS38) proved before and after
  • Only competent, qualified electricians carry out electrical work
  • Permit to work obtained where the site requires one
  • Personal locks and keys retained by the person working

Refrigerant release

Residual Low

Who: Engineers, building occupants

  • Refrigerant handled only by F-gas certified engineers
  • Refrigerant recovered into correctly rated, labelled recovery cylinders — never vented
  • Good ventilation; no recovery work in enclosed spaces without assessment
  • No ignition sources near flammable (A2L/A3) refrigerants; leak detector in use
  • Cryogenic-rated gloves and eye protection when connecting hoses

Stored pressure

Residual Low

Who: Engineers

  • Systems depressurised and drained down before breaking into pipework
  • Gauges, hoses and valves inspected and rated for the system pressure
  • Cylinders secured upright and transported with valves protected
  • Eye protection worn when connecting or venting

Manual handling

Residual Medium

Who: Operatives

  • Use mechanical aids (trolleys, sack trucks, hoists) for heavy items
  • Team lifts for items too heavy or awkward for one person
  • Route planned and cleared before moving items
  • Operatives trained in safe lifting techniques
  • Gloves with good grip and safety footwear

+ 1 more risks in the full RAMS.

What to get right on this document

Recover first

Then break in.

The gas type is written

Cylinders and gauges match.

Cooling is occupancy

Tell the building.

What this document has to cover

A brazing method that never recovers, or an R32 COSHH sheet used as the whole method, will fail. Recovery is the step that stops a release; COSHH is not a method statement.

A f gas recovery method statement only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.

Typical hazards to assess on this job

  • Refrigerant release to atmosphere or into an occupied plant room
  • Frost burns from liquid
  • Cylinder overfill
  • Electric shock on a unit that was not isolated
  • Oxygen displacement in a small plant room
  • Building overheating because cooling was taken down without notice

Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.

A method sequence that actually protects people

Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.

  • Confirm competence, gas type, charge and a recovery cylinder with remaining capacity
  • Isolate electrics; recover to the procedure — do not vent
  • Weigh off; do not overfill the cylinder
  • Prove residual pressure before breaking in; nitrogen purge if specified
  • Label recovered gas; leak-check when you recharge
  • Brief the occupier on the outage of cooling

Occupancy and other people

Offices and retail stay open. Write the outage of cooling and that a plant-room door wedged for a recovery unit is still a fire door.

Substances and COSHH

An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:

  • The specified refrigerant (R32, R410A or the actual)
  • Nitrogen if purging
  • Oil carried over in recovery

How SafeForJob helps

  • Describe this job in plain English and get suggested activities, risks and method steps
  • Edit every line before you download or issue
  • Reuse a previous RAMS and catch old client or site names
  • Attach or create COSHH assessments where hazardous substances appear

What this page is not

This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer f gas recovery method statement document for a named job. You remain responsible for reviewing and issuing it.

Related reading

See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.

Related pages

All method statements · RAMS by trade · Free RAMS generator

Questions

Is an SDS enough?
No. SDS informs COSHH; recovery still needs this method.
R32 vs R410A?
Write the actual gas — flammability and cylinders differ.
Can I vent ‘a bit’ to get the nut off?
No on this method.
Who owns F-gas records?
The operator — you still record what you recovered.