RAMS by job · UK
Fan coil unit replacement RAMS
An FCU is a wet and electrical machine over someone’s desk. A VRF RAMS that never mentions drain pans, ceiling tiles or how you keep the room in use will fail the facilities manager.
Typical scope
- Electrical and water isolation
- Controlled drain
- Room exclusion
- Handling route named
- Drain pan commissioned
- Dirty pan bagged
Quick answer
A fan-coil replacement RAMS covers swapping an FCU in a ceiling void on a named floor. Isolation of electrics, water and condensate, the occupied room below, and a lift out through a live office are the usual controls.
Primary topic: fan coil replacement rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.
What usually goes wrong
These are the operational gaps that make generic Word RAMS fail on the next site.
VRF RAMS reused
No water, no pan.
Drained onto the desk
No container.
Grid used as a platform
Fall through.
Example
FCU swap over a trading floor
Built from one job description. You review and adjust every item before issuing it.
Job description
Replace FCU-14 above desk row D at Greyfriars House, Leicester. 18:00 start, electrics and valves isolated, coil drained to a drum, desks sheeted, unit out via the goods lift, drain tested, tiles back before 07:00.
Activities identified
- General site work
- Electrical isolation
- Manual handling
- Plumbing and heating systems
Method (12 steps)
- 1.Arrive and sign in. Arrive at Level 2, Greyfriars House, Leicester, report to the Greyfriars FM site contact, sign in and complete any site induction.
- 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
- 3.Isolate the electrical supply. Identify the relevant circuit, isolate, lock off and tag. Prove dead with an approved voltage indicator, proved before and after use.
- 4.Isolate and drain down. Isolate the water/heating supply, allow to cool and drain down the affected section. Confirm isolation before breaking into pipework.
- 5.Disconnect and remove existing equipment. Disconnect and remove the existing equipment. Lower or carry it using mechanical aids or team lifts as planned.
- 6.Install new equipment. Position and fix the new equipment to the manufacturer's instructions.
- 7.Install pipework. Install and connect pipework. Use press-fit or mechanical joints in place of hot works where possible.
- 8.Carry out electrical work. Carry out the electrical work on the isolated circuit to BS 7671.
- 9.Test and commission. Test and commission the installation. Record results.
- 10.Remove isolation and re-energise. Confirm the work is complete and everyone is clear, remove locks and re-energise.
- 11.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
- 12.Hand over and sign out. Hand over to the Greyfriars FM site contact, report anything outstanding and sign out.
Main risks (4 in total)
Electric shock or burns
Residual MediumWho: Operatives, building occupants
- Work carried out dead — no live working
- Safe isolation: isolate, lock off, tag, and prove dead with an approved voltage indicator (GS38) proved before and after
- Only competent, qualified electricians carry out electrical work
- Permit to work obtained where the site requires one
- Personal locks and keys retained by the person working
Manual handling
Residual MediumWho: Operatives
- Use mechanical aids (trolleys, sack trucks, hoists) for heavy items
- Team lifts for items too heavy or awkward for one person
- Route planned and cleared before moving items
- Operatives trained in safe lifting techniques
- Gloves with good grip and safety footwear
Hot water, hot surfaces and flooding
Residual LowWho: Operatives, occupants
- System isolated, allowed to cool and drained down before work
- Isolation valves identified and tested before breaking into pipework
- Drip trays, buckets and wet vac available
- Gloves when handling recently isolated pipework
Stored pressure
Residual LowWho: Engineers
- Systems depressurised and drained down before breaking into pipework
- Gauges, hoses and valves inspected and rated for the system pressure
- Cylinders secured upright and transported with valves protected
- Eye protection worn when connecting or venting
What to get right on this document
Two isolations
Power and water.
The room is occupied
Exclude or work out of hours.
The pan is hygiene
Do not splash it across the floor.
What this document has to cover
An FCU is a wet and electrical machine over someone’s desk. A VRF RAMS that never mentions drain pans, ceiling tiles or how you keep the room in use will fail the facilities manager.
A fan coil replacement rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.
Typical hazards to assess on this job
- Electric shock on a local isolator that was not proved dead
- Water damage from live LTHW or CHW left open
- Fall through a weak ceiling grid
- Manual handling of a unit through a live office
- Legionella risk in a dirty condensate pan
- Occupants under an open void with dust and tools
Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.
A method sequence that actually protects people
Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.
- Isolate electrical, close valves, drain the coil to a controlled container — not the carpet
- Set exclusion in the room; protect desks and detection
- Support the grid; lift the unit to the planned route
- Fit the new FCU, reconnect, fire-stop penetrations
- Commission airflow and check the drain
- Bag the old pan and filters as waste; reinstate tiles
Occupancy and other people
Offices stay at their desks if you let them. Write the local exclusion, the out-of-hours window, and that you do not drain into a waste-paper bin.
Substances and COSHH
An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:
- Coil water (treat as not potable)
- Old filter and pan residue
- Sealants and insulation off-cuts
How SafeForJob helps
- Describe this job in plain English and get suggested activities, risks and method steps
- Edit every line before you download or issue
- Reuse a previous RAMS and catch old client or site names
- Attach or create COSHH assessments where hazardous substances appear
What this page is not
This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer fan coil replacement rams document for a named job. You remain responsible for reviewing and issuing it.
Related reading
See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.
Related pages
- RAMS by tradeHVAC RAMSCreate HVAC and refrigeration RAMS online: rooftop units, split systems, refrigerant recovery and brazing. Suggested risks and method steps you review before issue.
- GuidesWhat is a RAMS?RAMS means risk assessment and method statement — usually one site-specific pack for a construction or maintenance job. Practical UK guidance for contractors — with links to free tools.
- Method statementsHVAC installation method statementWrite a hvac installation method statement for a named UK site. Clear sequence, interfaces and controls — review before issue.
- RAMS by jobConsumer unit replacement RAMSCreate a consumer unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEV charger installation RAMSCreate a ev charger installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobLighting rewire RAMSCreate a lighting rewire rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEICR testing RAMSCreate a eicr method statement for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobRooftop condenser replacement RAMSCreate a rooftop ac unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobSplit system installation RAMSCreate a split system installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
Questions
- Is this the same as a split system?
- No — FCUs are typically wet coils on LTHW/CHW, not refrigerant pipe.
- Do I need F-gas?
- Only if the unit is DX. Write the actual machine.
- Ceiling asbestos?
- Survey before lifting tiles in an older building.
- Can the desk owner stay?
- Not under an open void with a wet coil.