Brickwork and blockwork method statement

A general-construction paragraph that never mentions daily raise limits, debris netting or wash-out of mortar will fail the first site manager. Masonry is a growing structure, not a decorating finish.

Typical scope

  • Daily raise vs design
  • Scaffold inspected
  • Exclusion and netting
  • Wet cut
  • Wash facilities for cement
  • Stable at knock-off

Quick answer

A brickwork-and-blockwork method statement is the sequence for raising masonry on a named elevation or wall: access, wet-cement COSHH, wall stability as it grows, and the public below.

Primary topic: brickwork method statement. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.

What usually goes wrong

These are the operational gaps that make generic Word RAMS fail on the next site.

  • Decorating method reused

    No stability, no cement burns.

  • Leaf left unrestrained overnight

    Collapse.

  • Dry chop-saw on the lift

    Silica onto the street.

Example

Garden wall on a live plot street

Built from one job description. You review and adjust every item before issuing it.

Job description

Build a 1.8 m brick garden wall at Plot 22, Willow Grange, Kettering. Scaffold to the neighbour’s side, exclusion on the shared path, wet cut in the plot garage, wash point, wall restrained at 1.2 m as drawn, no raise in frost.

Activities identified

  • General site work
  • Mobile tower or scaffold
  • Power tools

Method (6 steps)

  1. 1.Arrive and sign in. Arrive at Plot 22, Willow Grange, Kettering, report to the Willow Grange Developments site contact, sign in and complete any site induction.
  2. 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
  3. 3.Erect the tower. PASMA-trained operatives erect the mobile tower to the manufacturer's guide and inspect it before use.
  4. 4.Drill and fix. Mark out, then drill and fix using on-tool dust extraction. Check for hidden cables and pipes before drilling.
  5. 5.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
  6. 6.Hand over and sign out. Hand over to the Willow Grange Developments site contact, report anything outstanding and sign out.

Main risks (4 in total)

Fall from tower or scaffold, or collapse

Residual Medium

Who: Operatives, people nearby

  • Mobile towers erected by PASMA-trained persons to the manufacturer's guide
  • Scaffold erected by a competent scaffolder and tagged/inspected before use and every 7 days
  • Guard rails, toe boards and brick guards in place on working platforms
  • Castors locked and outriggers fitted; never moved while occupied

Falling objects

Residual Low

Who: People below, other trades, public

  • Exclusion zone set up below the work area with barriers and signage
  • Tools tethered when working at height; materials kept away from edges
  • Banksman or second person controls the area during lifts and removals
  • Hard hats worn in the exclusion zone

Hand and power tools

Residual Low

Who: Operatives

  • Battery or 110V tools used; no 230V tools on site without RCD protection
  • Tools inspected before use and PAT tested where applicable
  • Guards fitted and used as designed
  • Eye protection and gloves suitable for the task

Noise and hand-arm vibration

Residual Medium

Who: Operatives, people nearby

  • Low-vibration, low-noise tools selected
  • Trigger times limited and rotated between operatives
  • Noisy work scheduled to reduce disruption to occupants
  • Hearing protection worn where noise is high

What to get right on this document

The wall is a structure as it grows

Restraint.

Cement is COSHH

Wash point.

Below is the public

Netting and a walkway.

What this document has to cover

A general-construction paragraph that never mentions daily raise limits, debris netting or wash-out of mortar will fail the first site manager. Masonry is a growing structure, not a decorating finish.

A brickwork method statement only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.

Typical hazards to assess on this job

  • Collapse of an unrestrained leaf or a wall raised too high unpropped
  • Falls from scaffold lifts
  • Cement burns and mortar in eyes
  • Debris onto the public or a garden
  • Manual handling of packs on a lift
  • Silica if cutting blocks dry

Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.

A method sequence that actually protects people

Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.

  • Confirm the drawing, openings and any temporary restraint
  • Inspect the scaffold lift; exclusion and netting below
  • Raise to the specified lift; do not outrun restraint or the design
  • Cut wet or off-site; mix with wash facilities for cement
  • Protect fresh work; load-out waste via hoist, not over the eaves
  • Leave the wall stable at knock-off — no unrestrained overnight leaf

Occupancy and other people

Housing plots and high streets sit under the elevation. Write the walkway and that a wet mortar drop on a pushchair is a method failure.

Substances and COSHH

An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:

  • Mortar and cement
  • Block dust if cutting
  • Plasticisers / frostproofers if used

How SafeForJob helps

  • Describe this job in plain English and get suggested activities, risks and method steps
  • Edit every line before you download or issue
  • Reuse a previous RAMS and catch old client or site names
  • Attach or create COSHH assessments where hazardous substances appear

What this page is not

This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer brickwork method statement document for a named job. You remain responsible for reviewing and issuing it.

Related reading

See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.

Related pages

All method statements · RAMS by trade · Free RAMS generator

Questions

Is this pointing?
Pointing is a different access and COSHH story. This method is raising masonry.
Do I need a separate COSHH for mortar?
Yes — SDS is not a COSHH assessment. Attach it.
Party wall?
Legal process sits with the client; do not build off the neighbour’s foundation without it.
Frost?
Abort — write it.