Pump skid replacement RAMS

A skid is a lift plus a wet isolation, not a small circulator swap. A valve RAMS that never mentions the hoist, inertia bases or how you keep a hospital circuit up on the sister set will fail.

Typical scope

  • Sister set running
  • Lift plan
  • Isolation proved
  • Guards on before bump-run
  • Alignment recorded
  • Hatch exclusion below

Quick answer

A pump-skid RAMS covers lifting out and replacing a packaged pump set on LTHW, CHW or water. The lift, isolation of a live system and alignment on restart are the critical controls.

Primary topic: pump skid rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.

What usually goes wrong

These are the operational gaps that make generic Word RAMS fail on the next site.

  • Circulator RAMS reused

    No lift, no alignment.

  • Bump-run without a guard

    Coupling injury.

  • Both pumps isolated ‘to be sure’

    Building off.

Example

CHW skid through a plant hatch

Built from one job description. You review and adjust every item before issuing it.

Job description

Replace the CHW duty skid at Quayside Place, Leeds. Standby stays on, Saturday hoist through the hatch, lobby below excluded, isolations proved, laser alignment, guards on, vibration recorded before Monday.

Activities identified

  • General site work
  • Manual handling
  • Lifting operations

Method (7 steps)

  1. 1.Arrive and sign in. Arrive at Level-1 plant, Quayside Place, Leeds, report to the Quayside Place FM site contact, sign in and complete any site induction.
  2. 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
  3. 3.Carry out the lift. Carry out lifts to the lift plan, with the exclusion zone in place and a trained slinger/signaller directing.
  4. 4.Disconnect and remove existing equipment. Disconnect and remove the existing equipment. Lower or carry it using mechanical aids or team lifts as planned.
  5. 5.Install new equipment. Position and fix the new equipment to the manufacturer's instructions.
  6. 6.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
  7. 7.Hand over and sign out. Hand over to the Quayside Place FM site contact, report anything outstanding and sign out.

Main risks (2 in total)

Manual handling

Residual Medium

Who: Operatives

  • Use mechanical aids (trolleys, sack trucks, hoists) for heavy items
  • Team lifts for items too heavy or awkward for one person
  • Route planned and cleared before moving items
  • Operatives trained in safe lifting techniques
  • Gloves with good grip and safety footwear

Lifting operations

Residual Medium

Who: Operatives, public, other trades

  • Lift planned by a competent person; lift plan in place
  • Lifting equipment and accessories have current LOLER thorough examination
  • Exclusion zone below the lift; nobody under suspended loads
  • Trained slinger/signaller directs the lift
  • Lifts stopped in high winds

What to get right on this document

Keep a pump on

Named sister set.

The skid is a lift

Plan and hatch.

Guards before it turns

Not after.

What this document has to cover

A skid is a lift plus a wet isolation, not a small circulator swap. A valve RAMS that never mentions the hoist, inertia bases or how you keep a hospital circuit up on the sister set will fail.

A pump skid rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.

Typical hazards to assess on this job

  • Dropped skid in a plant room or through a hatch
  • Scald or flood from isolations that do not hold
  • Crushing on alignment and coupling
  • Electric shock on the package isolator
  • Vibration wrecking pipework if alignment is skipped
  • Process or heat lost because both duty and standby were taken

Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.

A method sequence that actually protects people

Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.

  • Agree which pump stays on and a lift plan for the skid
  • Isolate, prove holding, drain the package only
  • Lift out; protect the hatch; land the new skid on the specified bases
  • Align, couple, electrical connections, guards on before any bump-run
  • Commission pressures and vibration
  • Hand over guards, isolations and remaining defects

Occupancy and other people

Energy centres keep serving the building. Write the sister-set strategy and that a hatch over a corridor is excluded below.

Substances and COSHH

An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:

  • System fluid
  • Coupling grease
  • Paint on new bases

How SafeForJob helps

  • Describe this job in plain English and get suggested activities, risks and method steps
  • Edit every line before you download or issue
  • Reuse a previous RAMS and catch old client or site names
  • Attach or create COSHH assessments where hazardous substances appear

What this page is not

This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer pump skid rams document for a named job. You remain responsible for reviewing and issuing it.

Related reading

See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.

Related pages

All rams by job · RAMS by trade · Free RAMS generator

Questions

Is this a booster set?
Boosters are potable water packages. This is a heating/CHW skid — do not mix hygiene text.
Do I need a separate lifting RAMS?
One pack is fine when the hatch hoist, SWL and banksman sit in this sequence.
Inverter on the motor?
Add stored energy and isolation of the drive.
Who signs alignment?
The fitter, recorded — not a thumbs-up.