Platform lift RAMS
A platform lift is machinery on an accessible route, not a passenger-lift modernisation. A lift-maintenance RAMS that never mentions the pit, the alternative accessible route or how you stop the public using a half-commissioned platform will fail the access officer.
Typical scope
- Alternative accessible route signed
- Pit guarded
- Devices before auto-run
- Not left looking usable if unsigned
- Emergency lowering shown
- Dutyholder isolation brief
Quick answer
A platform-lift RAMS covers installing a vertical platform or short-rise lift on a named access. The pit or ramp, crushing on the platform, and not leaving a disabled route without an alternative are the critical controls.
Primary topic: platform lift rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.
What usually goes wrong
These are the operational gaps that make generic Word RAMS fail on the next site.
Passenger-lift RAMS reused
Wrong machine, no alternative route.
Auto-run in a foyer with visitors watching
Crush.
Old lift isolated, no signed alternative
Access lost.
Example
Short-rise platform in a live library
Built from one job description. You review and adjust every item before issuing it.
Job description
Install a short-rise platform at the foyer change of level, Central Library, Birmingham. Level-access rear entrance signed as the alternative, pit guarded, Sunday install, edges before any auto-run, emergency lower shown to FM, no public use until signed.
Activities identified
- General site work
- Manual handling
- Occupied premises or public areas
Method (7 steps)
- 1.Arrive and sign in. Arrive at Foyer, Central Library, Birmingham, report to the City Libraries site contact, sign in and complete any site induction.
- 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
- 3.Set up the work area. Set up barriers and signage around the work area and keep it clear of other people.
- 4.Disconnect and remove existing equipment. Disconnect and remove the existing equipment. Lower or carry it using mechanical aids or team lifts as planned.
- 5.Install new equipment. Position and fix the new equipment to the manufacturer's instructions.
- 6.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
- 7.Hand over and sign out. Hand over to the City Libraries site contact, report anything outstanding and sign out.
Main risks (2 in total)
Manual handling
Residual MediumWho: Operatives
- Use mechanical aids (trolleys, sack trucks, hoists) for heavy items
- Team lifts for items too heavy or awkward for one person
- Route planned and cleared before moving items
- Operatives trained in safe lifting techniques
- Gloves with good grip and safety footwear
Members of the public and building occupants
Residual LowWho: Public, customers, staff, residents
- Work area segregated with barriers and clear signage
- Work timed for quieter periods where possible, agreed with the site
- Tools and materials never left unattended in public areas
- Site contact informed of work areas and any disruption
What to get right on this document
Keep an accessible way
Signed alternative first.
Edges before auto
Same idea as doors.
It must not look usable
Until signed.
What this document has to cover
A platform lift is machinery on an accessible route, not a passenger-lift modernisation. A lift-maintenance RAMS that never mentions the pit, the alternative accessible route or how you stop the public using a half-commissioned platform will fail the access officer.
A platform lift rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.
Typical hazards to assess on this job
- Fall into an open pit or from a half-installed platform
- Crushing on the platform or under the carriage
- Electric shock on the controller
- Users left with no accessible route during the works
- Dropped glass or gates during the lift
- Public treating a learn-and-run as a working lift
Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.
A method sequence that actually protects people
Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.
- Agree a signed alternative accessible route before the existing lift is isolated
- Guard the pit; isolate power; lock off
- Land the platform with a planned lift; fit gates and edges before any auto-run
- Commission from a position of safety; force and presence devices as specified
- Do not leave the lift in a usable-looking state if it is not signed off
- Hand over isolation, emergency lowering and the remaining defects to the dutyholder
Occupancy and other people
Public buildings still serve wheelchair users. Write the alternative route and that a taped lift with a working-looking button is a RAMS failure.
Substances and COSHH
An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:
- Hydraulic oil if hydraulic
- Grease
- Cleaning solvents on glass gates
How SafeForJob helps
- Describe this job in plain English and get suggested activities, risks and method steps
- Edit every line before you download or issue
- Reuse a previous RAMS and catch old client or site names
- Attach or create COSHH assessments where hazardous substances appear
What this page is not
This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer platform lift rams document for a named job. You remain responsible for reviewing and issuing it.
Related reading
See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.
Related pages
- RAMS by tradeLift engineer RAMSSite-specific RAMS for lift service and install: crushing, falls, isolation and public landings.
- GuidesWhat is a RAMS?RAMS means risk assessment and method statement — usually one site-specific pack for a construction or maintenance job. Practical UK guidance for contractors — with links to free tools.
- Method statementsLifting operations method statementMethod statement for planned lifts: appointed person, exclusion, weather and landing.
- RAMS by jobConsumer unit replacement RAMSCreate a consumer unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEV charger installation RAMSCreate a ev charger installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobLighting rewire RAMSCreate a lighting rewire rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEICR testing RAMSCreate a eicr method statement for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobRooftop condenser replacement RAMSCreate a rooftop ac unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobSplit system installation RAMSCreate a split system installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
Questions
- Is this lift maintenance?
- Maintenance is a visit on an existing lift. This is a new install.
- Passenger lift in a shaft?
- Different package — pit, shaft and notified body. Do not reuse this RAMS.
- Who force-tests?
- The installer competent for that platform; the numbers go on the handover sheet.
- Is this legal advice on accessibility?
- No. Follow the specified alternative route.