Method statement · UK
Timber frame erection method statement
A carpentry method that starts with second-fix doors is the wrong phase. If the sequence does not immediately brace panels and keep people off an unguarded floor cassette, it is not an erection method.
Typical scope
- Lift plan and wind abort
- Immediate bracing
- Edge protection as the floor grows
- Timber store off escapes
- Boundary exclusion
- Openings marked
Quick answer
A timber-frame erection method statement is the sequence for standing designed panels and floors on a named plot: lift, immediate temporary bracing, edge protection as the floor grows, and fire of stored timber.
Primary topic: timber frame method statement. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.
What usually goes wrong
These are the operational gaps that make generic Word RAMS fail on the next site.
Second-fix carpentry method reused
No brace, no lift.
Panel stood and left for lunch unbraced
Wind.
Opening in a cassette unmarked
Fall through.
Example
Plot 18 timber frame on a live development
Built from one job description. You review and adjust every item before issuing it.
Job description
Erect the timber frame on Plot 18, Willow Grange, Kettering. Telehandler lift plan, wind abort 25 mph, immediate bracing as the drawing, cassette edges as floors land, timber store in the plot garage not the close, neighbour on Plot 17 occupied.
Activities identified
- General site work
- Lifting operations
- Plant and vehicle movement
- Occupied premises or public areas
Method (6 steps)
- 1.Arrive and sign in. Arrive at Plot 18, Willow Grange, Kettering, report to the Willow Grange Developments site contact, sign in and complete any site induction.
- 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
- 3.Set up the work area. Set up barriers and signage around the work area and keep it clear of other people.
- 4.Carry out the lift. Carry out lifts to the lift plan, with the exclusion zone in place and a trained slinger/signaller directing.
- 5.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
- 6.Hand over and sign out. Hand over to the Willow Grange Developments site contact, report anything outstanding and sign out.
Main risks (3 in total)
Lifting operations
Residual MediumWho: Operatives, public, other trades
- Lift planned by a competent person; lift plan in place
- Lifting equipment and accessories have current LOLER thorough examination
- Exclusion zone below the lift; nobody under suspended loads
- Trained slinger/signaller directs the lift
- Lifts stopped in high winds
Moving vehicles and plant
Residual MediumWho: Operatives, public, site staff
- Pedestrians segregated from vehicle and plant routes
- Plant operated by trained, authorised operators only
- Banksman used for reversing and manoeuvring
- High-visibility clothing worn
Members of the public and building occupants
Residual LowWho: Public, customers, staff, residents
- Work area segregated with barriers and clear signage
- Work timed for quieter periods where possible, agreed with the site
- Tools and materials never left unattended in public areas
- Site contact informed of work areas and any disruption
What to get right on this document
Brace before you let go
As designed.
The growing floor needs an edge
Immediately.
Storage is fire
Not the neighbour’s hedge.
What this document has to cover
A carpentry method that starts with second-fix doors is the wrong phase. If the sequence does not immediately brace panels and keep people off an unguarded floor cassette, it is not an erection method.
A timber frame method statement only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.
Typical hazards to assess on this job
- Collapse of unbraced panels in wind
- Falls from an incomplete floor cassette
- Dropped panel on the lift
- Fire of stacked timber next to a plot still occupied by a neighbour
- Public at a plot boundary
- Nail-gun injury and falling offcuts
Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.
A method sequence that actually protects people
Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.
- Lift plan and a wind abort before the first panel
- Stand, immediately brace as the TW/design — no ‘parked’ panels
- Floor cassettes with edge protection as the floor grows; no unmarked openings
- Store timber off escapes and away from neighbouring occupied plots
- Exclusion at the boundary; waste daily
- Hand over remaining bracing requirements
Occupancy and other people
Housing developments stay lived in on adjacent plots. Write the boundary and that a stacked frame in a shared close is a fire load.
Substances and COSHH
An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:
- Treated timber
- Solvent treatments if applied on site
- Expanding foam and sealants
How SafeForJob helps
- Describe this job in plain English and get suggested activities, risks and method steps
- Edit every line before you download or issue
- Reuse a previous RAMS and catch old client or site names
- Attach or create COSHH assessments where hazardous substances appear
What this page is not
This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer timber frame method statement document for a named job. You remain responsible for reviewing and issuing it.
Related reading
See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.
Related pages
- RAMS by jobDormer construction RAMSCreate a dormer construction rams for a named UK site. Unique hazards, method sequence and occupancy notes you review before issue.
- GuidesHow to write a method statementA practical sequence for writing a method statement that a principal contractor will actually read.
- RAMS by tradeFit-out RAMSCreate a fit-out or shopfitting RAMS online: partitions, ceilings, dust, occupied premises and out-of-hours work. Reviewed by you before issue.
- Method statementsMethod statement for electrical worksWrite a method statement for electrical works for a named UK site. Clear sequence, interfaces and controls — review before issue.
- Method statementsHVAC installation method statementWrite a hvac installation method statement for a named UK site. Clear sequence, interfaces and controls — review before issue.
- Method statementsPlumbing method statementWrite a plumbing method statement for a named UK site. Clear sequence, interfaces and controls — review before issue.
- Method statementsRoofing method statementWrite a roofing method statement for a named UK site. Clear sequence, interfaces and controls — review before issue.
- Method statementsExcavation method statementWrite a excavation method statement for a named UK site. Clear sequence, interfaces and controls — review before issue.
- Method statementsFit-out method statementWrite a fit out method statement for a named UK site. Clear sequence, interfaces and controls — review before issue.
Questions
- Is this carpentry and joinery?
- Joinery is first and second fix. This method is erection of the frame.
- Who designs temporary bracing?
- The frame designer / TW — do not invent it.
- Crane instead of telehandler?
- Write the actual lift.
- Fire engineering on a timber site?
- Follow the site fire plan; storage discipline still sits in this sequence.