Kitchen fitting method statement

If gas isolation is not a step, it will be skipped.

Typical scope

  • Isolation
  • Stone controls
  • Handling
  • Tests
  • Relight competence
  • Waste

Quick answer

A kitchen fitting method statement is the sequence from isolation through strip, units, worktops and tests. Services and silica should appear as steps, not footnotes.

Primary topic: kitchen fitting method statement. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.

What usually goes wrong

These are the operational gaps that make generic Word RAMS fail on the next site.

  • No isolation step

    Live services.

  • Indoor dry stone cut

    Silica.

  • No relight

    Occupier unsafe.

Example

Domestic refit

Built from one job description. You review and adjust every item before issuing it.

Job description

Occupied house, quartz wet-cut outdoors, family upstairs.

Activities identified

  • General site work
  • Power tools
  • Occupied premises or public areas
  • Outdoor or exposed work

Method (6 steps)

  1. 1.Arrive and sign in. Arrive at Occupied kitchen, report to the Homeowner site contact, sign in and complete any site induction.
  2. 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
  3. 3.Set up the work area. Set up barriers and signage around the work area and keep it clear of other people.
  4. 4.Drill and fix. Mark out, then drill and fix using on-tool dust extraction. Check for hidden cables and pipes before drilling.
  5. 5.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
  6. 6.Hand over and sign out. Hand over to the Homeowner site contact, report anything outstanding and sign out.

Main risks (4 in total)

Hand and power tools

Residual Low

Who: Operatives

  • Battery or 110V tools used; no 230V tools on site without RCD protection
  • Tools inspected before use and PAT tested where applicable
  • Guards fitted and used as designed
  • Eye protection and gloves suitable for the task

Noise and hand-arm vibration

Residual Medium

Who: Operatives, people nearby

  • Low-vibration, low-noise tools selected
  • Trigger times limited and rotated between operatives
  • Noisy work scheduled to reduce disruption to occupants
  • Hearing protection worn where noise is high

Members of the public and building occupants

Residual Low

Who: Public, customers, staff, residents

  • Work area segregated with barriers and clear signage
  • Work timed for quieter periods where possible, agreed with the site
  • Tools and materials never left unattended in public areas
  • Site contact informed of work areas and any disruption

Adverse weather

Residual Low

Who: Operatives

  • Forecast checked before work; work at height stopped in high winds
  • Breaks, water and shade in hot weather; warm clothing in cold
  • Sun protection on exposed work in summer

What to get right on this document

Prove dead / isolate gas

Named competence.

Cut outdoors or wet

Silica.

Tests

Water, electric, gas.

What this document has to cover

If gas isolation is not a step, it will be skipped.

A kitchen fitting method statement only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.

Typical hazards to assess on this job

  • Services
  • Silica
  • Stairs
  • Occupier
  • Leaks

Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.

A method sequence that actually protects people

Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.

  • Isolate/prove
  • Protect home
  • Strip
  • First fix
  • Units
  • Worktops with cutting controls
  • Test/relight
  • Handover

Occupancy and other people

Family in the house: keep a route, no live tails over lunch.

Substances and COSHH

An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:

  • Silica
  • Silicone
  • Foam

How SafeForJob helps

  • Describe this job in plain English and get suggested activities, risks and method steps
  • Edit every line before you download or issue
  • Reuse a previous RAMS and catch old client or site names
  • Attach or create COSHH assessments where hazardous substances appear

What this page is not

This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer kitchen fitting method statement document for a named job. You remain responsible for reviewing and issuing it.

Related reading

See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.

Related pages

All method statements · RAMS by trade · Free RAMS generator

Questions

Commercial?
Add nights and grease.
Who isolates gas?
Gas Safe.
Appliances via stairs?
Write the route.
Waste?
Same day.