Steel erection RAMS
This is a lifting operation with people at height, not a ‘general construction’ paragraph. If the sequence does not stop someone walking a beam that is not bolted, it is not a method.
Typical scope
- Lift plan attached
- Exclusion under the hook
- Immediate connections
- Access for bolting named
- Wind abort
- Temporary bracing as designed
Quick answer
A steel erection RAMS covers lifting and bolting structural steel on a named frame. The critical controls are the lift plan, exclusion under the load, and a means of connecting without standing on unsecured members.
Primary topic: steel erection rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.
What usually goes wrong
These are the operational gaps that make generic Word RAMS fail on the next site.
Walk the steel
No access method except the beam itself.
No appointed person
‘The driver will figure it out’.
Unbolted overnight
Frame not stable.
Example
Portal frame over a live yard
Built from one job description. You review and adjust every item before issuing it.
Job description
Erect the warehouse portal frame at Orion Fulfilment, Doncaster. Mobile crane, appointed person, yard exclusion during lifts, MEWP for bolting, no walking of members, wind limit in the lift plan.
Activities identified
- General site work
- Working at height (MEWP)
- Lifting operations
- Outdoor or exposed work
Method (7 steps)
- 1.Arrive and sign in. Arrive at Orion Fulfilment, Doncaster, report to the Orion Fulfilment site contact, sign in and complete any site induction.
- 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
- 3.Set up exclusion zone below. Establish an exclusion zone below the work area with barriers and signage before any work at height starts.
- 4.Set up the MEWP. Check ground conditions, position the MEWP, deploy outriggers on spreader plates and complete pre-use checks.
- 5.Carry out the lift. Carry out lifts to the lift plan, with the exclusion zone in place and a trained slinger/signaller directing.
- 6.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
- 7.Hand over and sign out. Hand over to the Orion Fulfilment site contact, report anything outstanding and sign out.
Main risks (4 in total)
Fall from height (MEWP)
Residual MediumWho: Operatives, people below
- MEWP used instead of ladders for access to the work area
- Operator holds a valid IPAF (or equivalent) licence for the machine category
- Pre-use checks completed and recorded; thorough examination (LOLER) in date
- Ground conditions checked; outriggers on spreader plates where required
- Ground-level rescue plan in place and a trained person at ground level
- Full-body harness with short work-restraint lanyard clipped to the basket anchor (boom MEWPs)
Falling objects
Residual LowWho: People below, other trades, public
- Exclusion zone set up below the work area with barriers and signage
- Tools tethered when working at height; materials kept away from edges
- Banksman or second person controls the area during lifts and removals
- Hard hats worn in the exclusion zone
Lifting operations
Residual MediumWho: Operatives, public, other trades
- Lift planned by a competent person; lift plan in place
- Lifting equipment and accessories have current LOLER thorough examination
- Exclusion zone below the lift; nobody under suspended loads
- Trained slinger/signaller directs the lift
- Lifts stopped in high winds
Adverse weather
Residual LowWho: Operatives
- Forecast checked before work; work at height stopped in high winds
- Breaks, water and shade in hot weather; warm clothing in cold
- Sun protection on exposed work in summer
What to get right on this document
The lift is the job
Plan, exclusion, abort.
Connect before you let go
No parked unsecured members.
Bolting access named
MEWP or designed platform — not the flange.
What this document has to cover
This is a lifting operation with people at height, not a ‘general construction’ paragraph. If the sequence does not stop someone walking a beam that is not bolted, it is not a method.
A steel erection rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.
Typical hazards to assess on this job
- Dropped load / crane or telehandler failure
- Falls from steel that is not a working platform
- Crushing during landing and alignment
- Unsecured members collapsing
- Weather — wind abort on lifts
- Public or other trades in the exclusion
Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.
A method sequence that actually protects people
Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.
- Lift plan, appointed person and exclusion agreed before the first piece
- Deliver and shake-out in a segregated laydown
- Lift, land and immediately make connections to the design — no ‘parked’ unsecured steel
- Bolt up from MEWP, MEWP-mounted platform or designed access — not by walking the flange
- Tighten to spec, survey, release the crane only when stable
- Hand over remaining temporary bracing requirements
Occupancy and other people
Housing and retail frames often sit next to live roads and occupied plots. Exclusion at ground is as important as the hook.
Substances and COSHH
An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:
- Paints and primers on steel
- Grease and oils
- Cutting or grinding debris if site-modified (avoid — design first)
How SafeForJob helps
- Describe this job in plain English and get suggested activities, risks and method steps
- Edit every line before you download or issue
- Reuse a previous RAMS and catch old client or site names
- Attach or create COSHH assessments where hazardous substances appear
What this page is not
This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer steel erection rams document for a named job. You remain responsible for reviewing and issuing it.
Related reading
See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.
Related pages
- RAMS by tradeSteel erection RAMSCreate structural steel method statement online for UK sites. Suggested risks and method steps matched to the job — you review every item before issue.
- GuidesWhat is a RAMS?RAMS means risk assessment and method statement — usually one site-specific pack for a construction or maintenance job. Practical UK guidance for contractors — with links to free tools.
- Method statementsLifting operations method statementMethod statement for planned lifts: appointed person, exclusion, weather and landing.
- RAMS by jobConsumer unit replacement RAMSCreate a consumer unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEV charger installation RAMSCreate a ev charger installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobLighting rewire RAMSCreate a lighting rewire rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEICR testing RAMSCreate a eicr method statement for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobRooftop condenser replacement RAMSCreate a rooftop ac unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobSplit system installation RAMSCreate a split system installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
Questions
- Do I need a separate lifting RAMS?
- A combined RAMS is fine if the lift plan is attached and followed.
- BCSA / NGCC?
- Follow the agreed erection method statement from the designer — this page does not replace it.
- Night lifts?
- Add lighting, fatigue and neighbour noise; the exclusion still holds.
- Can I modify a hole on site?
- Not unless the designer agrees — grinding is not improvisation.