Mobile crane lift RAMS

People get hurt in the radius and at the slinging point, not in a generic ‘plant’ paragraph. If the RAMS does not name the crane duty, ground and who can enter the zone, it is not ready.

Typical scope

  • Duty chart and ground assessment
  • Named appointed person
  • Exclusion that holds
  • Slinger/signaller
  • Wind abort
  • Nobody under the load

Quick answer

A mobile crane lift RAMS is the site-specific pack for a planned lift with a mobile crane: ground, radius, exclusion, slinging and abort. The lift plan is the method, not an appendix nobody reads.

Primary topic: mobile crane lift rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.

What usually goes wrong

These are the operational gaps that make generic Word RAMS fail on the next site.

  • Tower-crane RAMS reused

    Wrong machine, wrong ground.

  • Driver as their own slinger in a crowd

    Nobody watching the radius.

  • Outriggers on tarmac over a cellar

    No ground assessment.

Example

Sunday chiller lift over a car park

Built from one job description. You review and adjust every item before issuing it.

Job description

Lift two chillers onto the plant deck at Lakeside Retail, Thurrock. 80 t mobile, outrigger pads over a surveyed slab, car-park exclusion, slinger and signaller, wind limit 8 m/s, hospital loop kept open outside the radius.

Activities identified

  • General site work
  • Refrigerant handling
  • Occupied premises or public areas
  • Outdoor or exposed work

Method (10 steps)

  1. 1.Arrive and sign in. Arrive at Lakeside Retail, Thurrock, report to the Lakeside FM site contact, sign in and complete any site induction.
  2. 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
  3. 3.Set up the work area. Set up barriers and signage around the work area and keep it clear of other people.
  4. 4.Recover refrigerant. Recover the refrigerant into a correctly rated, labelled recovery cylinder. Record quantities in line with F-gas requirements.
  5. 5.Install new equipment. Position and fix the new equipment to the manufacturer's instructions.
  6. 6.Pressure test and evacuate. Pressure test with oxygen-free nitrogen, then evacuate the system before charging.
  7. 7.Charge the system. Charge the system with refrigerant to the manufacturer's specification and leak test all joints.
  8. 8.Test and commission. Test and commission the installation. Record results.
  9. 9.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
  10. 10.Hand over and sign out. Hand over to the Lakeside FM site contact, report anything outstanding and sign out.

Main risks (4 in total)

Refrigerant release

Residual Low

Who: Engineers, building occupants

  • Refrigerant handled only by F-gas certified engineers
  • Refrigerant recovered into correctly rated, labelled recovery cylinders — never vented
  • Good ventilation; no recovery work in enclosed spaces without assessment
  • No ignition sources near flammable (A2L/A3) refrigerants; leak detector in use
  • Cryogenic-rated gloves and eye protection when connecting hoses

Stored pressure

Residual Low

Who: Engineers

  • Systems depressurised and drained down before breaking into pipework
  • Gauges, hoses and valves inspected and rated for the system pressure
  • Cylinders secured upright and transported with valves protected
  • Eye protection worn when connecting or venting

Members of the public and building occupants

Residual Low

Who: Public, customers, staff, residents

  • Work area segregated with barriers and clear signage
  • Work timed for quieter periods where possible, agreed with the site
  • Tools and materials never left unattended in public areas
  • Site contact informed of work areas and any disruption

Adverse weather

Residual Low

Who: Operatives

  • Forecast checked before work; work at height stopped in high winds
  • Breaks, water and shade in hot weather; warm clothing in cold
  • Sun protection on exposed work in summer

What to get right on this document

Ground first

Cellars, ducts, made ground.

The radius is empty

Marshalling, not faith.

Abort is written

Wind and snag, not ‘press on’.

What this document has to cover

People get hurt in the radius and at the slinging point, not in a generic ‘plant’ paragraph. If the RAMS does not name the crane duty, ground and who can enter the zone, it is not ready.

A mobile crane lift rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.

Typical hazards to assess on this job

  • Crane overturn from poor ground, outriggers or overload
  • Load dropping from failed slinging or snagging
  • People struck in the radius
  • Overhead lines and adjacent structures
  • Wind and weather abort ignored
  • Public at the boundary of a short-duration lift

Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.

A method sequence that actually protects people

Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.

  • Appointed person confirms duty chart, ground assessment and permits
  • Set exclusion, signage and a slinger/signaller who is not also walking through the radius
  • Position, pad outriggers, test lift as planned
  • Lift, land, release — nobody under the load
  • If wind, rain or a snag appears, abort to the plan
  • De-rig, reopen the exclusion, record the lift

Occupancy and other people

Retail car parks and hospital loops stay open around the exclusion. A cone line that staff walk through is not a control. Write marshalling of vehicles and pedestrians.

Substances and COSHH

An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:

  • Hydraulic oil
  • Diesel
  • Grease

How SafeForJob helps

  • Describe this job in plain English and get suggested activities, risks and method steps
  • Edit every line before you download or issue
  • Reuse a previous RAMS and catch old client or site names
  • Attach or create COSHH assessments where hazardous substances appear

What this page is not

This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer mobile crane lift rams document for a named job. You remain responsible for reviewing and issuing it.

Related reading

See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.

Related pages

All rams by job · RAMS by trade · Free RAMS generator

Questions

Is a lift plan legally required?
LOLER expects planning of lifting operations. This page is not legal advice; attach the plan.
Contract lift vs CPA?
Write who is appointed person — it changes who owns the method.
Can I use a lorry loader instead?
Different machine, different RAMS. Do not reuse this one blindly.
People in the building below?
If the load passes over occupied space, the exclusion includes that space or you do not lift.