RAMS by job · UK
Medical gas alteration RAMS
This is a clinical life-support system, not compressed air in a workshop. An M&E RAMS that never mentions gas identity, permit-to-work or how you avoid starving a ward of oxygen will fail the authorised person (MGPS).
Typical scope
- AP (MGPS) permit
- Clinical workaround
- Identity tests
- Oil-free oxygen discipline
- Outlet labels
- Handover to the AP only
Quick answer
A medical-gas alteration RAMS covers cutting in or extending a medical gas pipeline on a named ward or theatre. Identity of the gas, isolation integrity, cleanliness and the patients who still need the gas are the critical controls.
Primary topic: medical gas rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.
What usually goes wrong
These are the operational gaps that make generic Word RAMS fail on the next site.
Workshop air RAMS reused
Wrong gas, no AP.
Cut in because ‘the valve is shut’
Not proved.
Oil pump used to pressure-test oxygen
Fire.
Example
Oxygen branch to a new bay
Built from one job description. You review and adjust every item before issuing it.
Job description
Extend oxygen to bay 4 on Ward B at Royal Infirmary, Coventry. AP (MGPS) permit, bay on cylinders, oil-free cut-in, identity and leak tests as specified, outlets labelled, handover to the AP before any patient use.
Activities identified
- General site work
- Manual handling
- Power tools
- Plumbing and heating systems
Method (10 steps)
- 1.Arrive and sign in. Arrive at Ward B, Royal Infirmary, Coventry, report to the Trust Estates site contact, sign in and complete any site induction.
- 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
- 3.Isolate and drain down. Isolate the water/heating supply, allow to cool and drain down the affected section. Confirm isolation before breaking into pipework.
- 4.Disconnect and remove existing equipment. Disconnect and remove the existing equipment. Lower or carry it using mechanical aids or team lifts as planned.
- 5.Drill and fix. Mark out, then drill and fix using on-tool dust extraction. Check for hidden cables and pipes before drilling.
- 6.Install new equipment. Position and fix the new equipment to the manufacturer's instructions.
- 7.Install pipework. Install and connect pipework. Use press-fit or mechanical joints in place of hot works where possible.
- 8.Test and commission. Test and commission the installation. Record results.
- 9.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
- 10.Hand over and sign out. Hand over to the Trust Estates site contact, report anything outstanding and sign out.
Main risks (5 in total)
Manual handling
Residual MediumWho: Operatives
- Use mechanical aids (trolleys, sack trucks, hoists) for heavy items
- Team lifts for items too heavy or awkward for one person
- Route planned and cleared before moving items
- Operatives trained in safe lifting techniques
- Gloves with good grip and safety footwear
Hand and power tools
Residual LowWho: Operatives
- Battery or 110V tools used; no 230V tools on site without RCD protection
- Tools inspected before use and PAT tested where applicable
- Guards fitted and used as designed
- Eye protection and gloves suitable for the task
Noise and hand-arm vibration
Residual MediumWho: Operatives, people nearby
- Low-vibration, low-noise tools selected
- Trigger times limited and rotated between operatives
- Noisy work scheduled to reduce disruption to occupants
- Hearing protection worn where noise is high
Hot water, hot surfaces and flooding
Residual LowWho: Operatives, occupants
- System isolated, allowed to cool and drained down before work
- Isolation valves identified and tested before breaking into pipework
- Drip trays, buckets and wet vac available
- Gloves when handling recently isolated pipework
+ 1 more risks in the full RAMS.
What to get right on this document
Identity is the job
Test it.
The AP owns the permit
Named.
Oil and oxygen do not meet
Tools and method.
What this document has to cover
This is a clinical life-support system, not compressed air in a workshop. An M&E RAMS that never mentions gas identity, permit-to-work or how you avoid starving a ward of oxygen will fail the authorised person (MGPS).
A medical gas rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.
Typical hazards to assess on this job
- Wrong gas or crossed pipelines
- Isolation that does not hold — starving patients or releasing gas
- Fire in an oxygen-enriched area
- Contamination of a medical pipeline with oil or dirt
- Hot works on a live ward
- Noise and access in a clinical space
Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.
A method sequence that actually protects people
Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.
- AP (MGPS) permit, identity and isolation proved before any cut
- Agree the clinical workaround — cylinders or a diverted bay
- Cut in with cleanliness controls; no oil on oxygen kit
- Purge, test identity and leak to HTM sequence as specified
- Label every outlet; do not leave an unlabelled stub
- Hand over only to the AP — not a ward clerk
Occupancy and other people
Wards stay full. Write which bays are off, where the cylinders sit, and that you do not store oil tools in an oxygen bay.
Substances and COSHH
An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:
- The medical gas itself (oxygen enrichment is a fire risk)
- Degreasers approved for oxygen service
- Solder / brazing gases if used
How SafeForJob helps
- Describe this job in plain English and get suggested activities, risks and method steps
- Edit every line before you download or issue
- Reuse a previous RAMS and catch old client or site names
- Attach or create COSHH assessments where hazardous substances appear
What this page is not
This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer medical gas rams document for a named job. You remain responsible for reviewing and issuing it.
Related reading
See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.
Related pages
- RAMS by tradeM&E RAMSCreate mechanical electrical method statement online for UK sites. Suggested risks and method steps matched to the job — you review every item before issue.
- GuidesWhat is a RAMS?RAMS means risk assessment and method statement — usually one site-specific pack for a construction or maintenance job. Practical UK guidance for contractors — with links to free tools.
- Method statementsLive environment method statementHow to sequence work while the public and staff stay in the building.
- RAMS by jobConsumer unit replacement RAMSCreate a consumer unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEV charger installation RAMSCreate a ev charger installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobLighting rewire RAMSCreate a lighting rewire rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEICR testing RAMSCreate a eicr method statement for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobRooftop condenser replacement RAMSCreate a rooftop ac unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobSplit system installation RAMSCreate a split system installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
Questions
- Is this HTM 02 legal advice?
- No. Follow the trust’s MGPS permit and competent persons.
- Can a general fitter do this?
- Only if they are competent for MGPS — this page does not make them so.
- Medical air vs oxygen?
- Write the actual gas; methods differ.
- Who tells the ward?
- The clinical lead named on the permit.