RAMS by job · UK
Kitchen first-fix power RAMS
This is not second-fix sockets. You are putting in the bones of a kitchen that will later take three-phase catering kit, and a domestic kitchen RAMS will miss isolator heights, interlocks and grease-zone IP ratings.
Typical scope
- Temporary supply isolated
- Isolator positions as drawn
- Boxes capped against water tests
- Coordination with gas/water
- Appliance labels
- No live bare ends
Quick answer
A kitchen first-fix power RAMS covers containment, supplies and isolators for a commercial or plot kitchen before equipment lands. Isolation of temporary supplies, coordination with gas and water, and a still-building site are the usual issues.
Primary topic: kitchen first fix power rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.
What usually goes wrong
These are the operational gaps that make generic Word RAMS fail on the next site.
Domestic kitchen RAMS
No three-phase, no grease IP.
Water test over open boxes
No cap.
Isolator behind a future fridge
Layout ignored.
Example
Hotel kitchen first-fix before kit lands
Built from one job description. You review and adjust every item before issuing it.
Job description
First-fix power in the new kitchen at Harbourview Hotel, Scarborough. Temporary supply locked off, isolators at the canopy line as drawn, boxes capped before the plumber’s test, fire-stop at the servery wall, chef walk-through Friday only.
Activities identified
- General site work
- Electrical isolation
- Occupied premises or public areas
- Plumbing and heating systems
Method (11 steps)
- 1.Arrive and sign in. Arrive at Harbourview Hotel, Scarborough, report to the Harbourview Hotel site contact, sign in and complete any site induction.
- 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
- 3.Set up the work area. Set up barriers and signage around the work area and keep it clear of other people.
- 4.Isolate the electrical supply. Identify the relevant circuit, isolate, lock off and tag. Prove dead with an approved voltage indicator, proved before and after use.
- 5.Isolate and drain down. Isolate the water/heating supply, allow to cool and drain down the affected section. Confirm isolation before breaking into pipework.
- 6.Install pipework. Install and connect pipework. Use press-fit or mechanical joints in place of hot works where possible.
- 7.Carry out electrical work. Carry out the electrical work on the isolated circuit to BS 7671.
- 8.Test and commission. Test and commission the installation. Record results.
- 9.Remove isolation and re-energise. Confirm the work is complete and everyone is clear, remove locks and re-energise.
- 10.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
- 11.Hand over and sign out. Hand over to the Harbourview Hotel site contact, report anything outstanding and sign out.
Main risks (4 in total)
Electric shock or burns
Residual MediumWho: Operatives, building occupants
- Work carried out dead — no live working
- Safe isolation: isolate, lock off, tag, and prove dead with an approved voltage indicator (GS38) proved before and after
- Only competent, qualified electricians carry out electrical work
- Permit to work obtained where the site requires one
- Personal locks and keys retained by the person working
Members of the public and building occupants
Residual LowWho: Public, customers, staff, residents
- Work area segregated with barriers and clear signage
- Work timed for quieter periods where possible, agreed with the site
- Tools and materials never left unattended in public areas
- Site contact informed of work areas and any disruption
Hot water, hot surfaces and flooding
Residual LowWho: Operatives, occupants
- System isolated, allowed to cool and drained down before work
- Isolation valves identified and tested before breaking into pipework
- Drip trays, buckets and wet vac available
- Gloves when handling recently isolated pipework
Stored pressure
Residual LowWho: Engineers
- Systems depressurised and drained down before breaking into pipework
- Gauges, hoses and valves inspected and rated for the system pressure
- Cylinders secured upright and transported with valves protected
- Eye protection worn when connecting or venting
What to get right on this document
The drawing is the kitchen
Heights and IP now.
Cap against the plumber
Water will come.
Label for the appliance
Not ‘cooker 1’ forever.
What this document has to cover
This is not second-fix sockets. You are putting in the bones of a kitchen that will later take three-phase catering kit, and a domestic kitchen RAMS will miss isolator heights, interlocks and grease-zone IP ratings.
A kitchen first fix power rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.
Typical hazards to assess on this job
- Electric shock on a temporary builder’s supply still live in the same room
- Cuts from containment in a tight kitchen
- Coordination clashes with gas and water first-fix
- Water from pressure tests onto open electrical boxes
- Other trades using your isolators as coat hooks
- Wrong IP or position so a later canopy grease line sits over a socket
Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.
A method sequence that actually protects people
Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.
- Agree the kitchen layout, isolator positions and who is first into the room that day
- Isolate any temporary supply in the zone; lock off
- Install containment and supplies to the drawing; cap boxes against water
- Coordinate with gas/water before closing walls
- Label every isolator for the appliance that will land
- Leave the room safe for the next trade — no live bare ends
Occupancy and other people
Plot kitchens and hotel back-of-house stay a thoroughfare. Write how you keep labour out of a room with open boxes, and that the chef’s visit is escorted.
Substances and COSHH
An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:
- Cutting swarf
- Fire-stopping at kitchen compartment walls
- Sealant on external isolators
How SafeForJob helps
- Describe this job in plain English and get suggested activities, risks and method steps
- Edit every line before you download or issue
- Reuse a previous RAMS and catch old client or site names
- Attach or create COSHH assessments where hazardous substances appear
What this page is not
This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer kitchen first fix power rams document for a named job. You remain responsible for reviewing and issuing it.
Related reading
See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.
Related pages
- RAMS by tradeElectrical RAMSCreate a site-specific electrical RAMS online. Describe the job, review suggested risks like safe isolation and work at height, and download a professional PDF.
- GuidesWhat is a RAMS?RAMS means risk assessment and method statement — usually one site-specific pack for a construction or maintenance job. Practical UK guidance for contractors — with links to free tools.
- Method statementsKitchen fitting method statementSequence for kitchen fitting: services, stone cutting, handling and occupier.
- RAMS by jobConsumer unit replacement RAMSCreate a consumer unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEV charger installation RAMSCreate a ev charger installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobLighting rewire RAMSCreate a lighting rewire rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEICR testing RAMSCreate a eicr method statement for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobRooftop condenser replacement RAMSCreate a rooftop ac unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobSplit system installation RAMSCreate a split system installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
Questions
- Is canopy extract in this RAMS?
- Only if you are wiring interlocks — otherwise attach the HVAC method.
- Gas interlock?
- If you wire it, write the sequence; competence sits with the gas package too.
- Plot house kitchen?
- Smaller load, same cap-and-label discipline.
- Can second-fix reuse this?
- No — equipment landing, tightness and commissioning need their own sequence.