RAMS by job · UK
Kitchen fire suppression RAMS
This is a fire-extinguishing system over ignition and grease, not a canopy hang. A canopy RAMS that never mentions fusible links, gas interlock or how you stop a cook lighting a range under an uncommissioned system will fail.
Typical scope
- Kitchen closed and appliances isolated
- Existing system locked out
- Nozzles as designed
- Gas/electric interlock
- Chef briefing on the pull
- No cooking until live
Quick answer
A kitchen-suppression RAMS covers installing or altering a wet-chemical system over a commercial canopy. The lift of cylinders, discharge onto a range, and a kitchen that still wants to cook are the critical controls.
Primary topic: kitchen fire suppression rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.
What usually goes wrong
These are the operational gaps that make generic Word RAMS fail on the next site.
Canopy RAMS reused
No agent, no interlock.
Fryer lit to ‘test the extract’
Fire without suppression.
Nozzle aimed by eye
Wrong coverage.
Example
Wet chemical over a new range line
Built from one job description. You review and adjust every item before issuing it.
Job description
Install a wet-chemical system over the new range at Queen Street Kitchen, Glasgow. Monday 00:30–07:00, kitchen closed, gas isolated, existing bottles locked out, nozzles as drawn, interlock commissioned, chef shown the pull, no breakfast until signed.
Activities identified
- General site work
- Manual handling
- Using chemicals or products
Method (7 steps)
- 1.Arrive and sign in. Arrive at Queen Street Kitchen, Glasgow, report to the Queen Street Kitchen site contact, sign in and complete any site induction.
- 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
- 3.Disconnect and remove existing equipment. Disconnect and remove the existing equipment. Lower or carry it using mechanical aids or team lifts as planned.
- 4.Install new equipment. Position and fix the new equipment to the manufacturer's instructions.
- 5.Apply products. Apply products as described on the Safety Data Sheet and COSHH assessment, with ventilation and the specified PPE.
- 6.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
- 7.Hand over and sign out. Hand over to the Queen Street Kitchen site contact, report anything outstanding and sign out.
Main risks (2 in total)
Manual handling
Residual MediumWho: Operatives
- Use mechanical aids (trolleys, sack trucks, hoists) for heavy items
- Team lifts for items too heavy or awkward for one person
- Route planned and cleared before moving items
- Operatives trained in safe lifting techniques
- Gloves with good grip and safety footwear
Hazardous substances
Residual MediumWho: Operatives, people nearby
- Use the least hazardous product that does the job
- COSHH assessment in place for each hazardous substance and briefed to operatives
- Good ventilation during and after use
- Substances stored and disposed of as the Safety Data Sheet describes
- Gloves and eye protection as specified on the SDS
What to get right on this document
Cooking waits
System live or a written alternative.
Interlock is the job
Gas and electric.
Nozzles follow the design
Not the nearest thread.
What this document has to cover
This is a fire-extinguishing system over ignition and grease, not a canopy hang. A canopy RAMS that never mentions fusible links, gas interlock or how you stop a cook lighting a range under an uncommissioned system will fail.
A kitchen fire suppression rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.
Typical hazards to assess on this job
- Accidental discharge of wet chemical into eyes and food
- Fire if cooking continues under an incomplete system
- Dropped cylinder in a tight kitchen
- Gas or electric not interlocked so a fire is refuelled
- Hot works or mechanical fixings into a grease duct
- Staff plating under a half-fitted nozzle line
Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.
A method sequence that actually protects people
Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.
- Kitchen closed; isolate gas and electric to the appliances
- Lock out the existing system so it cannot dump on the team
- Fit tanks, pipe and nozzles to the design; do not improvise a nozzle over a new fryer
- Interface gas/electric interlocks as specified
- Commission and reset; brief the chef on manual pull and re-entry
- Do not allow cooking until the system is live or a written alternative is in place
Occupancy and other people
Restaurants run on service. Write the closed hours and that a ‘quick fry’ under an isolated system is a RAMS failure.
Substances and COSHH
An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:
- Wet chemical agent
- Grease and degreasers
- Thread sealants
How SafeForJob helps
- Describe this job in plain English and get suggested activities, risks and method steps
- Edit every line before you download or issue
- Reuse a previous RAMS and catch old client or site names
- Attach or create COSHH assessments where hazardous substances appear
What this page is not
This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer kitchen fire suppression rams document for a named job. You remain responsible for reviewing and issuing it.
Related reading
See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.
Related pages
- RAMS by tradeFire & security RAMSCreate RAMS for fire alarm, CCTV and access control installation: system isolations, ceiling work, occupied buildings. Review every suggestion before issue.
- GuidesWhat is a RAMS?RAMS means risk assessment and method statement — usually one site-specific pack for a construction or maintenance job. Practical UK guidance for contractors — with links to free tools.
- Method statementsKitchen fitting method statementSequence for kitchen fitting: services, stone cutting, handling and occupier.
- RAMS by jobConsumer unit replacement RAMSCreate a consumer unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEV charger installation RAMSCreate a ev charger installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobLighting rewire RAMSCreate a lighting rewire rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEICR testing RAMSCreate a eicr method statement for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobRooftop condenser replacement RAMSCreate a rooftop ac unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobSplit system installation RAMSCreate a split system installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
Questions
- Is this a canopy install?
- The canopy is a different lift. This is the extinguishing system.
- ANSUL vs other brands?
- Write the actual listed system — do not mix nozzles.
- Who resets after a dump?
- A competent engineer — the chef should not recharge it.
- Can the night porter stay?
- Not in the exclusion under cylinders and nozzles.