RAMS by job · UK
Intumescent coating RAMS
Intumescent is a tested thickness on a prepared steel, not decoration. A spray-painting RAMS that never mentions DFT checks, the fire strategy or how you stop other trades knocking wet film will fail the fire engineer.
Typical scope
- Specified system only
- Substrate accepted
- DFT measured
- Exclusion of other trades
- Ignition control if solvent
- Batch and thickness recorded
Quick answer
An intumescent-coating RAMS covers applying a specified fire-resisting paint system to named steel. Thickness, COSHH of the coating, and not coating over dirt or the wrong primer are the critical controls.
Primary topic: intumescent coating rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.
What usually goes wrong
These are the operational gaps that make generic Word RAMS fail on the next site.
Decorative paint RAMS reused
No DFT, no fire strategy.
Thinned to spray further
Too thin to protect.
Picking against wet flanges
Film wrecked.
Example
Intumescent on a live warehouse frame
Built from one job description. You review and adjust every item before issuing it.
Job description
Apply the specified water-borne intumescent to haunches in aisle F at Ridings Fulfilment, Wakefield. Night shift, aisle closed, substrate accepted, DFT recorded per member, no thinning, picking diverted, records to the fire engineer.
Activities identified
- General site work
- Lone working
Method (4 steps)
- 1.Arrive and sign in. Arrive at Aisle F, Ridings Fulfilment, Wakefield, report to the Ridings Fulfilment site contact, sign in and complete any site induction.
- 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
- 3.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
- 4.Hand over and sign out. Hand over to the Ridings Fulfilment site contact, report anything outstanding and sign out.
Main risks (1 in total)
Lone working
Residual LowWho: Lone operatives
- Higher-risk tasks (work at height, live work, confined spaces) not carried out alone
- Check-in procedure agreed with the office at set times
- Mobile phone charged and signal checked on arrival
What to get right on this document
Thickness is the protection
Measure it.
The system is tested
Do not substitute.
Keep others off the steel
Until cured.
What this document has to cover
Intumescent is a tested thickness on a prepared steel, not decoration. A spray-painting RAMS that never mentions DFT checks, the fire strategy or how you stop other trades knocking wet film will fail the fire engineer.
An intumescent coating rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.
Typical hazards to assess on this job
- Fire protection missing because the film is too thin or the wrong system
- Inhalation and skin exposure from solvent or water-borne intumescent
- Work at height on steel that is not a platform
- Other trades damaging wet film
- Ignition of solvent-borne coatings
- Occupants in a hall used as a spray booth
Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.
A method sequence that actually protects people
Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.
- Confirm the specified system, steel schedule and a clean, primed substrate — stop if it is not
- Set exclusion and ventilation; ignition control if solvent-borne
- Apply to the specified coats; measure DFT as you go
- Protect wet steel; do not let other trades use it as a rack
- Record batch and thickness
- Hand over and do not hide thin spots with a decorative topcoat
Occupancy and other people
Warehouses stay in pick. Write the closed aisle and that a decorative topcoat is not a way to hide a failed DFT.
Substances and COSHH
An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:
- Intumescent coating (name water- or solvent-borne)
- Specified primer
- Thinners only if the system allows
How SafeForJob helps
- Describe this job in plain English and get suggested activities, risks and method steps
- Edit every line before you download or issue
- Reuse a previous RAMS and catch old client or site names
- Attach or create COSHH assessments where hazardous substances appear
What this page is not
This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer intumescent coating rams document for a named job. You remain responsible for reviewing and issuing it.
Related reading
See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.
Related pages
- RAMS by tradeFire & security RAMSCreate RAMS for fire alarm, CCTV and access control installation: system isolations, ceiling work, occupied buildings. Review every suggestion before issue.
- GuidesWhat is a RAMS?RAMS means risk assessment and method statement — usually one site-specific pack for a construction or maintenance job. Practical UK guidance for contractors — with links to free tools.
- Method statementsSpray painting method statementSequence for spray application: ignition control, RPE, detection permit, fire watch.
- RAMS by jobConsumer unit replacement RAMSCreate a consumer unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEV charger installation RAMSCreate a ev charger installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobLighting rewire RAMSCreate a lighting rewire rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEICR testing RAMSCreate a eicr method statement for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobRooftop condenser replacement RAMSCreate a rooftop ac unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobSplit system installation RAMSCreate a split system installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
Questions
- Is this decorative masonry paint?
- No — fire thickness on steel. Use the masonry RAMS for walls.
- Can I use any intumescent?
- Only the system on the fire strategy and steel schedule.
- SDS enough?
- No. SDS ≠ COSHH — write spray time and who is exposed.
- Who signs DFT?
- The applicator, recorded — the fire engineer may witness.