Facade cleaning RAMS

This is chemicals plus height plus a live street, not a window wipe. A cradle-cleaning RAMS that never mentions run-off to a gully, etching of glass or how you stop acid entering an air intake will fail.

Typical scope

  • Named chemical and dilution
  • Run-off not to a clean gully
  • Intakes and windows protected
  • Exclusion at ground
  • No on-site concentrating
  • Pavement left non-slip

Quick answer

A facade-cleaning RAMS covers washing or chemically cleaning a named elevation from a bosun’s chair, MEWP or scaffold. Height, chemical run-off onto the public, and the building’s intakes are the critical controls.

Primary topic: facade cleaning rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.

What usually goes wrong

These are the operational gaps that make generic Word RAMS fail on the next site.

  • Window-clean RAMS reused

    No chemical run-off.

  • Mix strengthened ‘because it is dirty’

    Etch and burns.

  • Run-off to the kerb gully

    Pollution.

Example

Stone clean over a café street

Built from one job description. You review and adjust every item before issuing it.

Job description

Clean the Portland elevation at 14 High Pavement, Nottingham. Specified mild alkali, MEWP, boarded walkway, café tables in, run-off to a lined gully not the clean kerb, intakes on the roof covered, no stronger mix on site.

Activities identified

  • General site work
  • Working at height (MEWP)
  • Roof work
  • Excavation

Method (10 steps)

  1. 1.Arrive and sign in. Arrive at 14 High Pavement, Nottingham, report to the High Pavement Estates site contact, sign in and complete any site induction.
  2. 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
  3. 3.Set up exclusion zone below. Establish an exclusion zone below the work area with barriers and signage before any work at height starts.
  4. 4.Locate buried services. Review service drawings and scan the area with a CAT and Genny. Mark located services before breaking ground.
  5. 5.Set up the MEWP. Check ground conditions, position the MEWP, deploy outriggers on spreader plates and complete pre-use checks.
  6. 6.Access the roof. Access the roof via the agreed route. Confirm edge protection is in place and identify any fragile areas before moving onto the roof.
  7. 7.Excavate. Excavate by hand near located services, then by machine. Support or batter back excavations and keep spoil away from the edge.
  8. 8.Backfill and reinstate. Backfill in layers, compact, and reinstate the surface. Remove barriers once the area is safe.
  9. 9.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
  10. 10.Hand over and sign out. Hand over to the High Pavement Estates site contact, report anything outstanding and sign out.

Main risks (7 in total)

Fall from height (MEWP)

Residual Medium

Who: Operatives, people below

  • MEWP used instead of ladders for access to the work area
  • Operator holds a valid IPAF (or equivalent) licence for the machine category
  • Pre-use checks completed and recorded; thorough examination (LOLER) in date
  • Ground conditions checked; outriggers on spreader plates where required
  • Ground-level rescue plan in place and a trained person at ground level
  • Full-body harness with short work-restraint lanyard clipped to the basket anchor (boom MEWPs)

Falling objects

Residual Low

Who: People below, other trades, public

  • Exclusion zone set up below the work area with barriers and signage
  • Tools tethered when working at height; materials kept away from edges
  • Banksman or second person controls the area during lifts and removals
  • Hard hats worn in the exclusion zone

Fall from roof edge

Residual Medium

Who: Operatives

  • Plan work to be done from below or from a MEWP where possible
  • Edge protection (guard rails) or parapet of adequate height in place before work starts
  • Safe access route to the roof agreed with the site; roof hatch secured open
  • Where collective protection isn't possible, use a fall-restraint system with suitable anchors
  • Work stops in high winds, ice or heavy rain

Fall through fragile roof or rooflight

Residual Medium

Who: Operatives

  • Treat all roof sheets and rooflights as fragile unless confirmed otherwise by the site
  • Rooflights covered or protected with suitable mesh or barriers
  • Staging or crawling boards used; no walking directly on sheets
  • Safety netting or fall arrest below where required

+ 3 more risks in the full RAMS.

What to get right on this document

The dilution is the method

Do not invent a stronger mix.

Catch the water

It is waste.

Intakes beat convenience

Cover them.

What this document has to cover

This is chemicals plus height plus a live street, not a window wipe. A cradle-cleaning RAMS that never mentions run-off to a gully, etching of glass or how you stop acid entering an air intake will fail.

A facade cleaning rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.

Typical hazards to assess on this job

  • Falls from the access system
  • Chemical burns and run-off into eyes at ground
  • Pollution of a surface-water drain
  • Damage to glass, stone or aluminium from the wrong mix
  • Aerosol into open windows and AHU intakes
  • Public walking the drop zone

Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.

A method sequence that actually protects people

Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.

  • Name the access, the chemical and a waste-water route that is not a clean gully
  • Set exclusion and protect openings and intakes
  • Apply from the top down to the method; do not increase concentration on site
  • Catch run-off; neutralise if specified
  • Rinse; inspect glass and stone before you leave a bay
  • Stand down the exclusion; do not leave a slippery pavement

Occupancy and other people

High streets stay open. Write the boarded walkway and that a café will put tables out under your drop unless you stop them.

Substances and COSHH

An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:

  • Named facade chemical (acid or alkaline — write the actual)
  • Neutraliser if used
  • Bird droppings if pre-cleaned

How SafeForJob helps

  • Describe this job in plain English and get suggested activities, risks and method steps
  • Edit every line before you download or issue
  • Reuse a previous RAMS and catch old client or site names
  • Attach or create COSHH assessments where hazardous substances appear

What this page is not

This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer facade cleaning rams document for a named job. You remain responsible for reviewing and issuing it.

Related reading

See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.

Related pages

All rams by job · RAMS by trade · Free RAMS generator

Questions

Is this the same as cradle window cleaning?
Related access, different chemistry and run-off. Use this if you are washing stone or metal.
Listed stone?
Follow the specification — the RAMS should not invent an acid.
SDS enough?
No. SDS ≠ COSHH; write dilution, time and who is at ground.
Do I need a pavement licence?
If you occupy the highway, yes — put it in the RAMS.