RAMS by job · UK
Chilled water riser RAMS
A wet riser full of glycol is not ‘pipework’. A generic M&E RAMS that never mentions drain-down volume, drip into a live office or same-visit fire-stopping will fail the clerk of works.
Typical scope
- Drain volume agreed
- Floors below briefed
- Pressure test before lagging
- Vapour-tight insulation
- Fire-stop same visit
- Riser locked
Quick answer
A chilled-water riser RAMS covers installing or altering CHW pipework in a vertical riser. Isolation of a live system, water over occupied floors, insulation of cold pipe and fire-stopping of the riser are the core.
Primary topic: chilled water riser rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.
What usually goes wrong
These are the operational gaps that make generic Word RAMS fail on the next site.
LTHW RAMS reused
No vapour seal, wrong fluid.
Drained into the lift lobby
Flood.
Penetration left for the fire-stopper ‘next week’
Strategy open.
Example
CHW riser alteration on a live office
Built from one job description. You review and adjust every item before issuing it.
Job description
Alter the CHW riser at Greyfriars House, Leicester, Saturday. Drain to a 1000 L IBC in the basement, floors 2–4 briefed, pressure test before lagging, vapour seal, fire-stop each slab before 18:00, riser locked.
Activities identified
- General site work
Method (4 steps)
- 1.Arrive and sign in. Arrive at Riser C, Greyfriars House, Leicester, report to the Greyfriars FM site contact, sign in and complete any site induction.
- 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
- 3.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
- 4.Hand over and sign out. Hand over to the Greyfriars FM site contact, report anything outstanding and sign out.
Main risks (0 in total)
What to get right on this document
Glycol is COSHH and pollution
Spill and volume.
Test then lag
Find the leak now.
Close the compartment
Fire-stop as you go.
What this document has to cover
A wet riser full of glycol is not ‘pipework’. A generic M&E RAMS that never mentions drain-down volume, drip into a live office or same-visit fire-stopping will fail the clerk of works.
A chilled water riser rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.
Typical hazards to assess on this job
- Water or glycol flood onto occupied floors
- Electric shock if you clip a live electrical riser
- Falls in a narrow locked riser
- Manual handling of long pipe in a stair
- Condensation and mould if insulation is skipped
- Fire strategy broken by an open riser cupboard
Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.
A method sequence that actually protects people
Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.
- Agree isolation, drain volume and a spill route that is not the lift lobby
- Lock the riser; exclude the floors you could wet
- Cut in, fit, pressure-test before insulation hides the joint
- Insulate vapour-tight; fire-stop every slab the same visit
- Refill, vent, label
- Do not leave the riser unlocked or an open penetration overnight
Occupancy and other people
Offices below will claim for a stained ceiling. Write which floors are told, where the drain lands, and that a failed joint is a stop.
Substances and COSHH
An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:
- Glycol / inhibited CHW
- Insulation adhesives and vapour tape
- Jointing compounds
How SafeForJob helps
- Describe this job in plain English and get suggested activities, risks and method steps
- Edit every line before you download or issue
- Reuse a previous RAMS and catch old client or site names
- Attach or create COSHH assessments where hazardous substances appear
What this page is not
This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer chilled water riser rams document for a named job. You remain responsible for reviewing and issuing it.
Related reading
See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.
Related pages
- RAMS by tradeM&E RAMSCreate mechanical electrical method statement online for UK sites. Suggested risks and method steps matched to the job — you review every item before issue.
- GuidesWhat is a RAMS?RAMS means risk assessment and method statement — usually one site-specific pack for a construction or maintenance job. Practical UK guidance for contractors — with links to free tools.
- Method statementsPlantroom M&E method statementWrite a plantroom method statement for a named UK site. Clear sequence, interfaces and controls — review before issue.
- RAMS by jobConsumer unit replacement RAMSCreate a consumer unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEV charger installation RAMSCreate a ev charger installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobLighting rewire RAMSCreate a lighting rewire rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEICR testing RAMSCreate a eicr method statement for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobRooftop condenser replacement RAMSCreate a rooftop ac unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobSplit system installation RAMSCreate a split system installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
Questions
- Is glycol just water?
- No — COSHH, slip and a pollution incident if it hits a drain.
- Can I use the LTHW RAMS?
- Hot water is a burn risk; CHW is vapour and glycol. Write this one.
- Who owns the drain-down?
- The person who runs that CHW circuit — write them, because they own the volume and the refill.
- Asbestos in old lagging?
- Treat unknown lagging as a stop until it is sampled — chilled risers in 1970s offices often are.