How to write a COSHH assessment (UK)

Printing the SDS and calling it COSHH is the classic fail. HSE is explicit: SDS ≠ assessment.

On this page

  • This SDS
  • This task
  • Hierarchy
  • Others exposed
  • Emergency
  • Review

Quick answer

A COSHH assessment describes how you will prevent harm from a hazardous substance on your job. Start from the safety data sheet, then describe quantity, duration, who is exposed and the controls you will actually use.

Primary topic: how to write a coshh assessment. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.

What usually goes wrong

These are the operational gaps that make generic Word RAMS fail on the next site.

  • SDS as COSHH

    Wrong.

  • Mask only

    Hierarchy.

  • Old product sheet

    You’ve switched brand.

What to get right on this document

Task not just product

Duration/who.

Hierarchy

Extract before mask.

Emergency

Eyewash/spill.

What this document has to cover

Printing the SDS and calling it COSHH is the classic fail. HSE is explicit: SDS ≠ assessment.

A how to write a coshh assessment only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.

Typical hazards to assess on this job

  • SDS stapled as the assessment
  • Wrong product (generic ‘paint’)
  • PPE only
  • No duration/quantity
  • Not reviewed when the product changes

Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.

A method sequence that actually protects people

Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.

  • Get the SDS for the product you will use
  • Describe the task (who, how long, how much, where)
  • Apply the hierarchy
  • Write emergency (eyewash, spill, fire)
  • Brief users
  • Review if the product or task changes

Occupancy and other people

Occupied buildings: who else is exposed (staff, public, other trades) belongs in the assessment.

Substances and COSHH

An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:

  • The actual product

How SafeForJob helps

  • Describe this job in plain English and get suggested activities, risks and method steps
  • Edit every line before you download or issue
  • Reuse a previous RAMS and catch old client or site names
  • Attach or create COSHH assessments where hazardous substances appear

What this page is not

This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer how to write a coshh assessment document for a named job. You remain responsible for reviewing and issuing it.

Related reading

See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.

Related pages

All guides · RAMS by trade · Free RAMS generator

Questions

Is an SDS enough?
No.
Process-generated dust?
You still assess — there may be no SDS.
SafeForJob SDS reader?
It extracts fields; you still assess the task.
Legal advice?
No.