COSHH by substance · UK
Zinc chromate primer COSHH assessment
Protective-coat jobs still meet chromate on existing steel. If you grind it as ‘prep’ with no assessment, you have the wrong hierarchy. New work should ask whether a non-chromate primer is specified.
What this assessment usually covers
- Substitution asked
- No casual grind of old chromate
- Enclosure/extract on spray
- SDS RPE
- Hygiene / no take-home
- Hazardous waste
Quick answer
A zinc-chromate-primer COSHH assessment covers remaining chromate primers on steel. Chromium(VI) on many SDS, spray mist, grinding of old coatings and substitution first are why a generic paint-solvent sheet fails. An SDS is not a COSHH assessment.
Primary topic: zinc chromate primer coshh assessment. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.
What usually goes wrong
These are the operational gaps that make generic Word RAMS fail on the next site.
Paint-solvent COSHH reused
Chromate missed.
Angle grind ‘to key’ on old yellow primer
Cr(VI) dust.
SDS PDF as COSHH
Rejected.
What to get right on this document
Ask for a non-chromate spec
Eliminate first.
Old yellow primer is a stop
Until assessed.
SDS informs COSHH
It is not COSHH.
What this document has to cover
Protective-coat jobs still meet chromate on existing steel. If you grind it as ‘prep’ with no assessment, you have the wrong hierarchy. New work should ask whether a non-chromate primer is specified.
A zinc chromate primer coshh assessment only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.
Typical hazards to assess on this job
- Inhalation of chromate mist or grinding dust (classification — follow the SDS)
- Skin sensitisation
- Eye irritation
- Fire of solvent-borne carriers
- Take-home dust on clothing
- Occupants under a blast or grind on a live yard
Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.
A method sequence that actually protects people
Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.
- Substitute non-chromate if the specification allows
- Do not grind old chromate as a cleaning habit — contain, wet or extract
- Spray only with the specified RPE and enclosure
- Ignition control for solvent carriers
- Hygiene: no dusty clothes home; welfare
- Waste as hazardous
Occupancy and other people
Yards and halls stay in use. Grit or mist on a pick face is occupancy as well as COSHH.
Substances and COSHH
An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:
- Zinc chromate primer as named
- Solvent carrier
- Old coating dust
How SafeForJob helps
- Describe this job in plain English and get suggested activities, risks and method steps
- Edit every line before you download or issue
- Reuse a previous RAMS and catch old client or site names
- Attach or create COSHH assessments where hazardous substances appear
What this page is not
This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer zinc chromate primer coshh assessment document for a named job. You remain responsible for reviewing and issuing it.
Related reading
See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.
Related pages
- GuidesSDS vs COSHH assessmentWhy a safety data sheet informs but does not replace your COSHH assessment. Practical UK guidance for contractors — with links to free tools.
- GuidesWhat is a COSHH assessment?COSHH assessments explain how you control hazardous substances for a real task, using the SDS. Practical UK guidance for contractors — with links to free tools.
- RAMS by jobProtective steel coating RAMSCreate a steel coating rams for a named UK site. Unique hazards, method sequence and occupancy notes you review before issue.
- COSHH by substanceDiesel COSHH assessmentDraft a coshh assessment for diesel for UK work. Start from the SDS, apply hierarchy of controls, review before issue.
- COSHH by substanceSilica dust COSHH assessmentDraft a silica dust coshh assessment for UK work. Start from the SDS, apply hierarchy of controls, review before issue.
- COSHH by substanceCement COSHH assessmentDraft a cement coshh assessment for UK work. Start from the SDS, apply hierarchy of controls, review before issue.
- COSHH by substanceR32 refrigerant COSHH assessmentDraft a r32 coshh assessment for UK work. Start from the SDS, apply hierarchy of controls, review before issue.
- COSHH by substanceSolvent adhesive COSHH assessmentDraft a solvent adhesive coshh for UK work. Start from the SDS, apply hierarchy of controls, review before issue.
- COSHH by substanceSolvent-based paint COSHH assessmentDraft a solvent paint coshh assessment for UK work. Start from the SDS, apply hierarchy of controls, review before issue.
All coshh by substance · RAMS by trade · Free RAMS generator
Questions
- Is chromate still specified?
- Sometimes on existing systems — read the spec and the SDS.
- Is an SDS enough?
- No.
- Is this intumescent?
- Different system. This assessment is chromate primer.
- Health surveillance?
- May apply for Cr(VI) processes — get advice.