Gas works method statement

If someone new to the job cannot brief the test from the method, it is not finished.

Typical scope

  • Gas Safe
  • Test step
  • Purge
  • Relight
  • Occupier
  • Certificates

Quick answer

A gas works method statement is the step-by-step ‘how’ that sits with your risk assessment. Isolation, tightness testing, purge and relight should be impossible to skip.

Primary topic: gas works method statement. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.

What usually goes wrong

These are the operational gaps that make generic Word RAMS fail on the next site.

  • Test missing

    Method jumps to ‘complete work’.

  • No occupier brief

    Appliances off.

  • Fuel not named

    LPG vs natural gas.

Example

Meter housing alteration

Built from one job description. You review and adjust every item before issuing it.

Job description

Alter external meter housing pipework at a café, tightness test and relight before service.

Activities identified

  • General site work
  • Outdoor or exposed work

Method (4 steps)

  1. 1.Arrive and sign in. Arrive at Occupied commercial kitchen, report to the High street café site contact, sign in and complete any site induction.
  2. 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
  3. 3.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
  4. 4.Hand over and sign out. Hand over to the High street café site contact, report anything outstanding and sign out.

Main risks (1 in total)

Adverse weather

Residual Low

Who: Operatives

  • Forecast checked before work; work at height stopped in high winds
  • Breaks, water and shade in hot weather; warm clothing in cold
  • Sun protection on exposed work in summer

What to get right on this document

Test is a line in the method

With pass criteria.

Competence

Named.

Occupier

Emergency actions.

What this document has to cover

If someone new to the job cannot brief the test from the method, it is not finished.

A gas works method statement only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.

Typical hazards to assess on this job

  • Gas release
  • Ignition
  • CO after work
  • Public at housings
  • Wrong isolation

Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.

A method sequence that actually protects people

Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.

  • Confirm competence and isolation plan
  • Exclude others
  • Isolate
  • Work
  • Tightness test
  • Purge
  • Relight and analyse
  • Brief occupier
  • Certificates

Occupancy and other people

Occupied kitchens: never leave a capped pipe without telling the occupier.

Substances and COSHH

An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:

  • Fuel gas
  • Jointing compounds

How SafeForJob helps

  • Describe this job in plain English and get suggested activities, risks and method steps
  • Edit every line before you download or issue
  • Reuse a previous RAMS and catch old client or site names
  • Attach or create COSHH assessments where hazardous substances appear

What this page is not

This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer gas works method statement document for a named job. You remain responsible for reviewing and issuing it.

Related reading

See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.

Related pages

All method statements · RAMS by trade · Free RAMS generator

Questions

RAMS or method only?
Clients usually want both together as a RAMS.
Can I copy IGEM?
Your sequence must still name this meter and this site.
Hot works?
Only if you introduce them — do not hide.
Emergency smell of gas?
Occupier brief is part of the method.