Window replacement RAMS

The opening is a hole in the building until the new unit is in and weathered. A joinery RAMS that starts with ‘fit window’ after the old one is already out is the document clients bounce.

Typical scope

  • Immediate cover for the opening
  • Exclusion below
  • Glass handling plan
  • Survey before strip
  • Same-shift weatherproof
  • Occupant briefing

Quick answer

A window replacement RAMS covers removing existing frames and installing new windows on a named elevation. Falls through the opening, glass handling, and the public below are the usual critical controls.

Primary topic: window replacement rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.

What usually goes wrong

These are the operational gaps that make generic Word RAMS fail on the next site.

  • Opening left over lunch

    A classroom with a hole in the wall.

  • Units up a ladder

    No handling plan.

  • Asbestos mastic ignored

    Drilling 1970s frames without a survey.

Example

Front elevation windows over a pavement

Built from one job description. You review and adjust every item before issuing it.

Job description

Replace six timber sashes with double-glazed units at 8 High Pavement, Nottingham. Independent scaffold, pavement licence, opening covered until each unit is weathered, two-person glass lifts, occupants using the rear rooms.

Activities identified

  • General site work
  • Mobile tower or scaffold
  • Manual handling

Method (7 steps)

  1. 1.Arrive and sign in. Arrive at 8 High Pavement, Nottingham, report to the High Pavement Trust site contact, sign in and complete any site induction.
  2. 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
  3. 3.Erect the tower. PASMA-trained operatives erect the mobile tower to the manufacturer's guide and inspect it before use.
  4. 4.Disconnect and remove existing equipment. Disconnect and remove the existing equipment. Lower or carry it using mechanical aids or team lifts as planned.
  5. 5.Install new equipment. Position and fix the new equipment to the manufacturer's instructions.
  6. 6.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
  7. 7.Hand over and sign out. Hand over to the High Pavement Trust site contact, report anything outstanding and sign out.

Main risks (3 in total)

Fall from tower or scaffold, or collapse

Residual Medium

Who: Operatives, people nearby

  • Mobile towers erected by PASMA-trained persons to the manufacturer's guide
  • Scaffold erected by a competent scaffolder and tagged/inspected before use and every 7 days
  • Guard rails, toe boards and brick guards in place on working platforms
  • Castors locked and outriggers fitted; never moved while occupied

Falling objects

Residual Low

Who: People below, other trades, public

  • Exclusion zone set up below the work area with barriers and signage
  • Tools tethered when working at height; materials kept away from edges
  • Banksman or second person controls the area during lifts and removals
  • Hard hats worn in the exclusion zone

Manual handling

Residual Medium

Who: Operatives

  • Use mechanical aids (trolleys, sack trucks, hoists) for heavy items
  • Team lifts for items too heavy or awkward for one person
  • Route planned and cleared before moving items
  • Operatives trained in safe lifting techniques
  • Gloves with good grip and safety footwear

What to get right on this document

Cover as a step

How the hole is made safe in minutes.

Glass is a load

Two-person or hoist, not a one-man lift over a pavement.

Tell the people inside

Even on a domestic job.

What this document has to cover

The opening is a hole in the building until the new unit is in and weathered. A joinery RAMS that starts with ‘fit window’ after the old one is already out is the document clients bounce.

A window replacement rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.

Typical hazards to assess on this job

  • Fall through the opening or from the working platform
  • Glass and frames falling onto the public or garden
  • Manual handling of sealed units
  • Weather entering the room
  • Existing glass breaking during removal
  • Asbestos in old window boards, soffits or mastic on some buildings

Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.

A method sequence that actually protects people

Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.

  • Confirm access (scaffold, tower or MEWP), exclusion below, and a survey of the existing frames
  • Protect the room, brief occupants, set an immediate cover for the opening
  • Remove the old unit onto the platform — never onto a ladder
  • Install, pack, fix and weather the new unit the same shift if possible
  • Internal making-good, trickle vents and ironmongery
  • Remove waste via hoist or down the scaffold, not over the cill

Occupancy and other people

Occupied homes and classrooms sit under the elevation. Exclusion and sheeting below matter as much as the packers. Do not leave an open hole over lunch in a school.

Substances and COSHH

An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:

  • Silicone and PU foams
  • Solvent cleaners
  • Old mastic (possible asbestos — stop if unsurveyed)

How SafeForJob helps

  • Describe this job in plain English and get suggested activities, risks and method steps
  • Edit every line before you download or issue
  • Reuse a previous RAMS and catch old client or site names
  • Attach or create COSHH assessments where hazardous substances appear

What this page is not

This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer window replacement rams document for a named job. You remain responsible for reviewing and issuing it.

Related reading

See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.

Related pages

All rams by job · RAMS by trade · Free RAMS generator

Questions

Do I need a pavement licence?
If you occupy the highway, yes — put it in the RAMS.
What about trickle vents and fire egress?
Follow the specification; the RAMS should not improvise means of escape.
Can I store units in the hallway?
Not if it blocks escape. Write the storage bay.
Secondary glazing instead?
Different method — still an opening and glass handling, but less strip.