Wet riser RAMS

A wet riser is a life-safety water main, not domestic pipe. A plumbing RAMS that never mentions the fire strategy, inlet breeching or how the fire service still find water will fail the fire engineer.

Typical scope

  • Outage strategy with the responsible person
  • Controlled drain
  • Specified valves and inlet
  • Pressure test
  • Landing valves labelled
  • Stair kept clear

Quick answer

A wet-riser RAMS covers installing or altering a charged fire-fighting main in a named stair or shaft. Isolation of a live main, water damage, and not leaving a building without its riser are the critical controls.

Primary topic: wet riser rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.

What usually goes wrong

These are the operational gaps that make generic Word RAMS fail on the next site.

  • Domestic pipe RAMS reused

    No fire strategy.

  • Main left open overnight

    No water for a fire.

  • Inlet box used as a store

    Fire service cannot find it.

Example

Wet riser alteration in an occupied tower

Built from one job description. You review and adjust every item before issuing it.

Job description

Alter the wet riser in stair A at Harbour Tower, Poole. Responsible person agrees a Saturday outage and extra extinguishers, controlled drain, specified landing valves, pressure test, labels, stair clear, handover before Sunday occupation of upper floors.

Activities identified

  • General site work
  • Mobile tower or scaffold
  • Plumbing and heating systems

Method (8 steps)

  1. 1.Arrive and sign in. Arrive at Stair A, Harbour Tower, Poole, report to the Harbour Tower RTM site contact, sign in and complete any site induction.
  2. 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
  3. 3.Isolate and drain down. Isolate the water/heating supply, allow to cool and drain down the affected section. Confirm isolation before breaking into pipework.
  4. 4.Erect the tower. PASMA-trained operatives erect the mobile tower to the manufacturer's guide and inspect it before use.
  5. 5.Install pipework. Install and connect pipework. Use press-fit or mechanical joints in place of hot works where possible.
  6. 6.Test and commission. Test and commission the installation. Record results.
  7. 7.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
  8. 8.Hand over and sign out. Hand over to the Harbour Tower RTM site contact, report anything outstanding and sign out.

Main risks (4 in total)

Fall from tower or scaffold, or collapse

Residual Medium

Who: Operatives, people nearby

  • Mobile towers erected by PASMA-trained persons to the manufacturer's guide
  • Scaffold erected by a competent scaffolder and tagged/inspected before use and every 7 days
  • Guard rails, toe boards and brick guards in place on working platforms
  • Castors locked and outriggers fitted; never moved while occupied

Falling objects

Residual Low

Who: People below, other trades, public

  • Exclusion zone set up below the work area with barriers and signage
  • Tools tethered when working at height; materials kept away from edges
  • Banksman or second person controls the area during lifts and removals
  • Hard hats worn in the exclusion zone

Hot water, hot surfaces and flooding

Residual Low

Who: Operatives, occupants

  • System isolated, allowed to cool and drained down before work
  • Isolation valves identified and tested before breaking into pipework
  • Drip trays, buckets and wet vac available
  • Gloves when handling recently isolated pipework

Stored pressure

Residual Low

Who: Engineers

  • Systems depressurised and drained down before breaking into pipework
  • Gauges, hoses and valves inspected and rated for the system pressure
  • Cylinders secured upright and transported with valves protected
  • Eye protection worn when connecting or venting

What to get right on this document

The strategy owns the outage

Named measure.

The inlet is for the fire service

Keep it clear and labelled.

Test before you promise it

Records.

What this document has to cover

A wet riser is a life-safety water main, not domestic pipe. A plumbing RAMS that never mentions the fire strategy, inlet breeching or how the fire service still find water will fail the fire engineer.

A wet riser rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.

Typical hazards to assess on this job

  • Building occupied without a working fire-fighting main
  • Flood from a charged main into stairs and floors
  • Falls in a stair shaft while hanging pipe
  • Manual handling of large-bore pipe
  • Incorrect inlet or landing valve so the fire service cannot use it
  • Other trades using the stair as a store while the main is open

Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.

A method sequence that actually protects people

Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.

  • Agree with the responsible person how fire-fighting water is provided during the outage
  • Isolate, drain in a controlled way, protect the stair
  • Install pipe, valves and inlet to the specified standard
  • Pressure-test; do not leave an uncharged promised main overnight without agreement
  • Label landing valves; keep the stair clear
  • Hand over to the responsible person with records

Occupancy and other people

High-rise and hospitals stay occupied. Write the compensation measure — extra extinguishers or a restriction — not ‘it will be back by lunch’.

Substances and COSHH

An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:

  • System water
  • Jointing compounds rated for the main
  • Paint on inlet boxes

How SafeForJob helps

  • Describe this job in plain English and get suggested activities, risks and method steps
  • Edit every line before you download or issue
  • Reuse a previous RAMS and catch old client or site names
  • Attach or create COSHH assessments where hazardous substances appear

What this page is not

This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer wet riser rams document for a named job. You remain responsible for reviewing and issuing it.

Related reading

See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.

Related pages

All rams by job · RAMS by trade · Free RAMS generator

Questions

Is this a dry riser?
Dry risers are normally empty until pumped. Different charge and test — use the dry-riser RAMS.
Sprinklers on the same stack?
Do not hide a sprinkler isolation in this method.
Who talks to the fire service?
The responsible person — name them if the outage is material.
Is this legal advice on the Fire Safety Order?
No. It is a site method you still review.