RAMS by job · UK
Underfloor busway RAMS
This is not a raised-access flooring RAMS. This job covers installing or extending underfloor busway or powertrack in a raised-floor office, and the control that keeps people safe is proving the section dead and controlling open tiles as holes. If the RAMS never names which tiles are open, the prove-dead point and who walks the floor after hours, a principal contractor will send it back.
Typical scope
- Section proved dead
- One tile at a time
- Holes covered when unattended
- Manufacturer joints
- Tiles back before restore
- Tap-off schedule handed over
Quick answer
A underfloor busway rams covers installing or extending underfloor busway or powertrack in a raised-floor office on a named UK site. The critical control is proving the section dead and controlling open tiles as holes. Write which tiles are open, the prove-dead point and who walks the floor after hours into the sequence — a pack that could describe any raised-access flooring RAMS will not survive a competent review.
Primary topic: underfloor busway rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.
What usually goes wrong
These are the operational gaps that make generic Word RAMS fail on the next site.
Flooring RAMS reused
No busway, no prove-dead.
Two rows of tiles open
A trench of holes.
Restore with a tile out
A fall at 07:00.
Example
Powertrack extend on level 2
Built from one job description. You review and adjust every item before issuing it.
Job description
Extend underfloor busway on level 2 at Civic Annex, Lincoln. 20:00–06:00, section locked off, one-tile rule, night-cleaner route taped, tiles back before 06:30 clean, tap-off blanks listed.
Activities identified
- General site work
- Using chemicals or products
- Plumbing and heating systems
- Lone working
Method (8 steps)
- 1.Arrive and sign in. Arrive at Level 2, Civic Annex, Lincoln, report to the Civic Annex FM site contact, sign in and complete any site induction.
- 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
- 3.Isolate and drain down. Isolate the water/heating supply, allow to cool and drain down the affected section. Confirm isolation before breaking into pipework.
- 4.Install pipework. Install and connect pipework. Use press-fit or mechanical joints in place of hot works where possible.
- 5.Apply products. Apply products as described on the Safety Data Sheet and COSHH assessment, with ventilation and the specified PPE.
- 6.Test and commission. Test and commission the installation. Record results.
- 7.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
- 8.Hand over and sign out. Hand over to the Civic Annex FM site contact, report anything outstanding and sign out.
Main risks (4 in total)
Hazardous substances
Residual MediumWho: Operatives, people nearby
- Use the least hazardous product that does the job
- COSHH assessment in place for each hazardous substance and briefed to operatives
- Good ventilation during and after use
- Substances stored and disposed of as the Safety Data Sheet describes
- Gloves and eye protection as specified on the SDS
Hot water, hot surfaces and flooding
Residual LowWho: Operatives, occupants
- System isolated, allowed to cool and drained down before work
- Isolation valves identified and tested before breaking into pipework
- Drip trays, buckets and wet vac available
- Gloves when handling recently isolated pipework
Stored pressure
Residual LowWho: Engineers
- Systems depressurised and drained down before breaking into pipework
- Gauges, hoses and valves inspected and rated for the system pressure
- Cylinders secured upright and transported with valves protected
- Eye protection worn when connecting or venting
Lone working
Residual LowWho: Lone operatives
- Higher-risk tasks (work at height, live work, confined spaces) not carried out alone
- Check-in procedure agreed with the office at set times
- Mobile phone charged and signal checked on arrival
What to get right on this document
Tiles are holes
One at a time.
The section is dead until proved
Not assumed.
Cleaners are occupancy
Write the route.
What this document has to cover
This is not a raised-access flooring RAMS. This job covers installing or extending underfloor busway or powertrack in a raised-floor office, and the control that keeps people safe is proving the section dead and controlling open tiles as holes. If the RAMS never names which tiles are open, the prove-dead point and who walks the floor after hours, a principal contractor will send it back.
An underfloor busway rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.
Typical hazards to assess on this job
- Electric shock on a busway section that is still energised
- Open floor tiles as a fall and a trip for night cleaners
- Crushed fingers landing a length under a desk row
- Dust and unknown services in an old floor void
- Fire-stopping left open at a floor penetration
- Re-energising while a tile is still out
Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.
A method sequence that actually protects people
Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.
- Isolate and prove dead the named section; mark open-tile limits
- Lift one tile at a time; cover holes when you step away
- Land and joint the busway to the manufacturer’s method
- Fire-stop penetrations the same visit
- Replace tiles, test and only then restore
- Hand over residual open tap-offs and the floor-box schedule
Occupancy and other people
Night cleaners and late staff will walk the floor. Write the taped route and that an open tile is a hole, not a convenience.
Substances and COSHH
An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:
- Joint grease
- Fire-stopping mastic
- Void dust — survey older floors
How SafeForJob helps
- Describe this job in plain English and get suggested activities, risks and method steps
- Edit every line before you download or issue
- Reuse a previous RAMS and catch old client or site names
- Attach or create COSHH assessments where hazardous substances appear
What this page is not
This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer underfloor busway rams document for a named job. You remain responsible for reviewing and issuing it.
Related reading
See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.
Related pages
- RAMS by tradeElectrical RAMSCreate a site-specific electrical RAMS online. Describe the job, review suggested risks like safe isolation and work at height, and download a professional PDF.
- GuidesWhat is a RAMS?RAMS means risk assessment and method statement — usually one site-specific pack for a construction or maintenance job. Practical UK guidance for contractors — with links to free tools.
- Method statementsMethod statement for electrical worksWrite a method statement for electrical works for a named UK site. Clear sequence, interfaces and controls — review before issue.
- RAMS by jobConsumer unit replacement RAMSCreate a consumer unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEV charger installation RAMSCreate a ev charger installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobLighting rewire RAMSCreate a lighting rewire rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEICR testing RAMSCreate a eicr method statement for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobRooftop condenser replacement RAMSCreate a rooftop ac unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobSplit system installation RAMSCreate a split system installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
Questions
- Is this the same as raised-access flooring?
- Flooring is the tiles. This RAMS is the live or isolated busway under them.
- Can we leave tiles out overnight?
- No — cover or replace. Cleaners will not read a sign.
- Who proves dead?
- The authorised person named on the pack.
- Asbestos in old voids?
- Check the register before you lift a tile in an older wing.