RAMS by job · UK
Three-phase distribution board RAMS
Energy levels, lock-off discipline and plant-room interfaces are different from a domestic consumer unit. Treating it as ‘another board swap’ is the usual client rejection.
Typical scope
- Isolation plan
- Lock-off devices named
- Arc-flash controls
- Plant-room access
- Torque and labels
- Energise procedure
Quick answer
A three-phase distribution board RAMS is the site-specific pack for installing or replacing a TP&N board. Critical controls are safe isolation of a higher-energy supply, proving dead, and working in plant rooms with other services.
Primary topic: three phase distribution board rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.
What usually goes wrong
These are the operational gaps that make generic Word RAMS fail on the next site.
Domestic method reused
No mention of three-phase proving or lock-off.
Keys not controlled
Someone else re-energises mid-job.
Riser asbestos ignored
Drilling a 1970s cupboard without checking the register.
Example
TP&N board replacement in a warehouse
Built from one job description. You review and adjust every item before issuing it.
Job description
Replace the ground-floor distribution board at Orion Fulfilment, Doncaster. Isolate the incoming 400 V supply, lock off, install a new TP&N board, test and re-energise on a Sunday so picking stays down.
Activities identified
- General site work
- Electrical isolation
- Electrical testing
- Manual handling
Method (10 steps)
- 1.Arrive and sign in. Arrive at Orion Fulfilment, Doncaster, report to the Orion Fulfilment site contact, sign in and complete any site induction.
- 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
- 3.Isolate the electrical supply. Identify the relevant circuit, isolate, lock off and tag. Prove dead with an approved voltage indicator, proved before and after use.
- 4.Disconnect and remove existing equipment. Disconnect and remove the existing equipment. Lower or carry it using mechanical aids or team lifts as planned.
- 5.Install new equipment. Position and fix the new equipment to the manufacturer's instructions.
- 6.Carry out electrical work. Carry out the electrical work on the isolated circuit to BS 7671.
- 7.Test and commission. Test and commission the installation. Record results.
- 8.Remove isolation and re-energise. Confirm the work is complete and everyone is clear, remove locks and re-energise.
- 9.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
- 10.Hand over and sign out. Hand over to the Orion Fulfilment site contact, report anything outstanding and sign out.
Main risks (3 in total)
Electric shock or burns
Residual MediumWho: Operatives, building occupants
- Work carried out dead — no live working
- Safe isolation: isolate, lock off, tag, and prove dead with an approved voltage indicator (GS38) proved before and after
- Only competent, qualified electricians carry out electrical work
- Permit to work obtained where the site requires one
- Personal locks and keys retained by the person working
Electric shock during testing
Residual HighWho: Operatives
- Test dead wherever possible; live testing only where essential
- GS38-compliant test leads and probes, inspected before use
- Barriers or screens to prevent others approaching exposed live parts
- Testing carried out by competent persons only
- Insulated gloves and eye protection where there is an arc-flash risk
Manual handling
Residual MediumWho: Operatives
- Use mechanical aids (trolleys, sack trucks, hoists) for heavy items
- Team lifts for items too heavy or awkward for one person
- Route planned and cleared before moving items
- Operatives trained in safe lifting techniques
- Gloves with good grip and safety footwear
What to get right on this document
Write the isolation plan
Which incomer, who holds keys, how you prove all phases.
Treat the plant room as occupied
Facilities access, heat and noise are part of the RAMS.
Energise is a step
Not an afterthought once the board is ‘finished’.
What this document has to cover
Energy levels, lock-off discipline and plant-room interfaces are different from a domestic consumer unit. Treating it as ‘another board swap’ is the usual client rejection.
A three phase distribution board rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.
Typical hazards to assess on this job
- Arc flash / shock on a three-phase supply
- Stored energy after isolation
- Work in plant rooms with heat, noise and other trades
- Manual handling of boards and trunking
- Dust and drilling for new containment
- Unauthorised access to an open board
Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.
A method sequence that actually protects people
Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.
- Permit and isolation plan agreed with the dutyholder
- Isolate, lock, tag and prove dead on all phases and neutral as required
- Screen the board so others cannot reach live parts if a staged isolate is used
- Install, torque, label and test before energising
- Energise under a controlled procedure, then functional tests
- Handover certificates, keys and remaining live-working restrictions
Occupancy and other people
Plant rooms often stay accessible to facilities staff. Control the door, signage and who may enter while the board is open.
Substances and COSHH
An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:
- Cutting fluid or swarf if drilling steel
- Wipe solvents
- Existing dust including possible asbestos in older risers
How SafeForJob helps
- Describe this job in plain English and get suggested activities, risks and method steps
- Edit every line before you download or issue
- Reuse a previous RAMS and catch old client or site names
- Attach or create COSHH assessments where hazardous substances appear
What this page is not
This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer three phase distribution board rams document for a named job. You remain responsible for reviewing and issuing it.
Related reading
See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.
Related pages
- RAMS by tradeElectrical RAMSCreate a site-specific electrical RAMS online. Describe the job, review suggested risks like safe isolation and work at height, and download a professional PDF.
- GuidesWhat is a RAMS?RAMS means risk assessment and method statement — usually one site-specific pack for a construction or maintenance job. Practical UK guidance for contractors — with links to free tools.
- Method statementsMethod statement for electrical worksWrite a method statement for electrical works for a named UK site. Clear sequence, interfaces and controls — review before issue.
- RAMS by jobConsumer unit replacement RAMSCreate a consumer unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEV charger installation RAMSCreate a ev charger installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobLighting rewire RAMSCreate a lighting rewire rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEICR testing RAMSCreate a eicr method statement for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobRooftop condenser replacement RAMSCreate a rooftop ac unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobSplit system installation RAMSCreate a split system installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
Questions
- Is GS38 enough?
- You still need an approved voltage indicator proved before and after, plus a method that matches the board.
- Do I need an electrical permit?
- On most commercial sites yes — name it in the method.
- What about generators?
- If a temporary supply is used, include that interface and earthing.
- Can I work live?
- Not as a convenience. Live work needs justification that this RAMS is not trying to provide.