Street lighting column RAMS

This is highway electrical work, not a warehouse lighting RAMS. TM, isolation of DNO or private network supplies, and the public on the footway have to lead the method.

Typical scope

  • TM before work
  • Network isolation procedure
  • Service location for foundations
  • Hinge/lift plan
  • Pedestrian route that does not dump people in the road
  • Test before restore

Quick answer

A street lighting RAMS covers installing, replacing or maintaining columns and lanterns next to live traffic. Overturn of the column or MEWP, electrical isolation, and being struck by vehicles are the critical harms.

Primary topic: street lighting rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.

What usually goes wrong

These are the operational gaps that make generic Word RAMS fail on the next site.

  • Warehouse lighting RAMS

    No TM or DNO isolation.

  • Hinged column over the shop door

    No pedestrian plan.

  • Restore without test

    Live faults on a highway.

Example

Column replacement on a school route

Built from one job description. You review and adjust every item before issuing it.

Job description

Replace two lighting columns on Station Road, Derby, 09:30–14:30. LANTRA TM, pedestrian boarded walkway, DNO isolation as permitted, hiab lift, no work at pick-up, test and restore before leaving.

Activities identified

  • General site work
  • Electrical isolation
  • Manual handling
  • Lifting operations

Method (10 steps)

  1. 1.Arrive and sign in. Arrive at Station Road, Derby, report to the County Highways site contact, sign in and complete any site induction.
  2. 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
  3. 3.Isolate the electrical supply. Identify the relevant circuit, isolate, lock off and tag. Prove dead with an approved voltage indicator, proved before and after use.
  4. 4.Carry out the lift. Carry out lifts to the lift plan, with the exclusion zone in place and a trained slinger/signaller directing.
  5. 5.Disconnect and remove existing equipment. Disconnect and remove the existing equipment. Lower or carry it using mechanical aids or team lifts as planned.
  6. 6.Install new equipment. Position and fix the new equipment to the manufacturer's instructions.
  7. 7.Carry out electrical work. Carry out the electrical work on the isolated circuit to BS 7671.
  8. 8.Remove isolation and re-energise. Confirm the work is complete and everyone is clear, remove locks and re-energise.
  9. 9.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
  10. 10.Hand over and sign out. Hand over to the County Highways site contact, report anything outstanding and sign out.

Main risks (3 in total)

Electric shock or burns

Residual Medium

Who: Operatives, building occupants

  • Work carried out dead — no live working
  • Safe isolation: isolate, lock off, tag, and prove dead with an approved voltage indicator (GS38) proved before and after
  • Only competent, qualified electricians carry out electrical work
  • Permit to work obtained where the site requires one
  • Personal locks and keys retained by the person working

Manual handling

Residual Medium

Who: Operatives

  • Use mechanical aids (trolleys, sack trucks, hoists) for heavy items
  • Team lifts for items too heavy or awkward for one person
  • Route planned and cleared before moving items
  • Operatives trained in safe lifting techniques
  • Gloves with good grip and safety footwear

Lifting operations

Residual Medium

Who: Operatives, public, other trades

  • Lift planned by a competent person; lift plan in place
  • Lifting equipment and accessories have current LOLER thorough examination
  • Exclusion zone below the lift; nobody under suspended loads
  • Trained slinger/signaller directs the lift
  • Lifts stopped in high winds

What to get right on this document

TM is the first step

Not an afterthought when the wagon arrives.

Whose network?

DNO vs private — write the isolation.

Keep walkers on a footway

Do not gift them to traffic.

What this document has to cover

This is highway electrical work, not a warehouse lighting RAMS. TM, isolation of DNO or private network supplies, and the public on the footway have to lead the method.

A street lighting rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.

Typical hazards to assess on this job

  • Struck by a vehicle during setup or while the column is open
  • Electric shock on DNO, private network or internal wiring
  • Column or lantern falling during lift or hinge
  • MEWP overturn at a kerb or cellar
  • Underground services when excavating a new foundation
  • Pedestrians forced into the carriageway by the working space

Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.

A method sequence that actually protects people

Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.

  • Set TM and pedestrian management before the first cone is trusted
  • Isolate and prove dead to the network owner’s procedure
  • Excavate or expose the foundation with service location
  • Lift, plumb, terminate, test and hinge-safe the column
  • Restore the supply only after tests
  • Take down TM in reverse; leave the footway clear

Occupancy and other people

High streets and school routes stay used. A column on a hinge over a pram is a RAMS failure. Write lookouts and that children will treat cones as a game.

Substances and COSHH

An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:

  • Paint and solvents on columns
  • Grease on hinges
  • Concrete if founding a new column

How SafeForJob helps

  • Describe this job in plain English and get suggested activities, risks and method steps
  • Edit every line before you download or issue
  • Reuse a previous RAMS and catch old client or site names
  • Attach or create COSHH assessments where hazardous substances appear

What this page is not

This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer street lighting rams document for a named job. You remain responsible for reviewing and issuing it.

Related reading

See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.

Related pages

All rams by job · RAMS by trade · Free RAMS generator

Questions

Is this NRSWA?
Usually yes on the public highway — competence and permits belong in the RAMS.
Private estate lighting?
Still isolation and public interface; the DNO procedure may not apply.
Can I use a ladder on a column?
Not as the main access for a lantern swap on a live road — name MEWP or hinge.
LED retrofit only?
Still isolation, height and TM — a smaller job is not a free pass.