RAMS by job · UK
Solar module cleaning RAMS
Cleaning is access plus live DC, not a window wipe. A facade-cleaning RAMS that never mentions not standing on glass, isolators or how you stop runoff into a roof outlet will fail the asset owner.
Typical scope
- Do not walk modules
- Exclusion below
- Water off isolators
- Specified chemistry only
- Carport bays closed if over cars
- No pressure-wash on junctions
Quick answer
A solar-module-cleaning RAMS covers washing an array on a named roof or carport. Height, DC still live, water on electrics and not walking a fragile module are the critical controls.
Primary topic: solar panel cleaning rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.
What usually goes wrong
These are the operational gaps that make generic Word RAMS fail on the next site.
Window-clean RAMS reused
Walking glass, no DC.
Pressure-washer on MC4s
Water in live DC.
Bays open under a carport wash
Cars and people.
Example
Carport array wash over a retail park
Built from one job description. You review and adjust every item before issuing it.
Job description
Wash the solar carport at Riverside Retail, Preston, Sunday 07:00–10:00. Bays 1–20 closed, water-fed pole from the deck not the glass, no chemical, water kept off inverters, pedestrians via the east aisle, no pressure-wash on junctions.
Activities identified
- General site work
- Electrical isolation
- Occupied premises or public areas
- Using chemicals or products
- Solar PV and batteries
Method (11 steps)
- 1.Arrive and sign in. Arrive at Riverside Retail, Preston, report to the Riverside Retail FM site contact, sign in and complete any site induction.
- 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
- 3.Set up the work area. Set up barriers and signage around the work area and keep it clear of other people.
- 4.Isolate the electrical supply. Identify the relevant circuit, isolate, lock off and tag. Prove dead with an approved voltage indicator, proved before and after use.
- 5.Install mounting system and modules. Fix the mounting system to the roof structure, then install modules. Keep DC isolators open.
- 6.Apply products. Apply products as described on the Safety Data Sheet and COSHH assessment, with ventilation and the specified PPE.
- 7.Connect inverter and DC strings. Install the inverter and AC connection, then connect DC strings last with isolators open.
- 8.Test and commission. Test and commission the installation. Record results.
- 9.Remove isolation and re-energise. Confirm the work is complete and everyone is clear, remove locks and re-energise.
- 10.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
- 11.Hand over and sign out. Hand over to the Riverside Retail FM site contact, report anything outstanding and sign out.
Main risks (4 in total)
Electric shock or burns
Residual MediumWho: Operatives, building occupants
- Work carried out dead — no live working
- Safe isolation: isolate, lock off, tag, and prove dead with an approved voltage indicator (GS38) proved before and after
- Only competent, qualified electricians carry out electrical work
- Permit to work obtained where the site requires one
- Personal locks and keys retained by the person working
Members of the public and building occupants
Residual LowWho: Public, customers, staff, residents
- Work area segregated with barriers and clear signage
- Work timed for quieter periods where possible, agreed with the site
- Tools and materials never left unattended in public areas
- Site contact informed of work areas and any disruption
Hazardous substances
Residual MediumWho: Operatives, people nearby
- Use the least hazardous product that does the job
- COSHH assessment in place for each hazardous substance and briefed to operatives
- Good ventilation during and after use
- Substances stored and disposed of as the Safety Data Sheet describes
- Gloves and eye protection as specified on the SDS
DC electric shock and arc (solar PV / batteries)
Residual HighWho: Installers
- DC strings connected last; isolators open during installation
- Never make or break DC connectors under load
- Modules covered where practical when working on DC wiring
- Installers competent in PV/battery installation (e.g. MCS-aligned training)
- Insulated tools and gloves
What to get right on this document
Glass is not a walkway
Poles or designated paths.
DC is still there
Water off connectors.
Below is closed
Bays or playground.
What this document has to cover
Cleaning is access plus live DC, not a window wipe. A facade-cleaning RAMS that never mentions not standing on glass, isolators or how you stop runoff into a roof outlet will fail the asset owner.
A solar panel cleaning rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.
Typical hazards to assess on this job
- Falls from the roof or carport
- Walking or kneeling on modules — glass failure and a fall through
- Electric shock if water is forced into connectors
- Dropped tools onto people or cars below
- Chemical runoff into drains
- Public at a carport while you wash above windscreens
Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.
A method sequence that actually protects people
Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.
- Confirm access, edge protection and whether DC isolation is required for this method
- Set exclusion below; close carport bays if you are over cars
- Clean from the designated walkways or a water-fed pole — not by walking the glass
- Use only the specified water or chemical; no pressure-washer on junctions
- Keep water off isolators and inverters
- Stand down the exclusion; do not leave a slippery carport
Occupancy and other people
Carports and school roofs stay next to people. Write the closed bays and that a pole from a playground is not a method if children are below.
Substances and COSHH
An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:
- Specified cleaning chemical if any
- Bird droppings (biological)
- Roof dirt (characterise if industrial)
How SafeForJob helps
- Describe this job in plain English and get suggested activities, risks and method steps
- Edit every line before you download or issue
- Reuse a previous RAMS and catch old client or site names
- Attach or create COSHH assessments where hazardous substances appear
What this page is not
This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer solar panel cleaning rams document for a named job. You remain responsible for reviewing and issuing it.
Related reading
See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.
Related pages
- RAMS by tradeSolar PV RAMSCreate solar pv rams online for UK sites. Suggested risks and method steps matched to the job — you review every item before issue.
- GuidesWhat is a RAMS?RAMS means risk assessment and method statement — usually one site-specific pack for a construction or maintenance job. Practical UK guidance for contractors — with links to free tools.
- Method statementsSolar PV method statementWrite a solar panel method statement for a named UK site. Clear sequence, interfaces and controls — review before issue.
- RAMS by jobConsumer unit replacement RAMSCreate a consumer unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEV charger installation RAMSCreate a ev charger installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobLighting rewire RAMSCreate a lighting rewire rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEICR testing RAMSCreate a eicr method statement for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobRooftop condenser replacement RAMSCreate a rooftop ac unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobSplit system installation RAMSCreate a split system installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
Questions
- Is this facade cleaning?
- Related water and height, different live DC and fragile glass.
- Do I isolate DC?
- If the method requires it, write it — many pole washes do not, but connectors still hate jets.
- Bird guano?
- Add COSHH — do not dry-brush it off the glass.
- Who owns access?
- The roof or carport owner — do not improvise a walkway.