This is life-safety ventilation, not a toilet extract. A general HVAC RAMS that never mentions the fire-engineer interface, cause-and-effect or how the building stays occupied during the swap will fail.
Typical scope
- Outage strategy with the responsible person
- Named circuit only
- Shaft opening guarded
- Cause-and-effect preserved
- Witness / commission
- No unagreed ‘hand’ overnight
Quick answer
A smoke-extract fan RAMS covers installing or replacing a fan that is part of a smoke-control system. The lift, electrical isolation, the fire strategy and not leaving the building without its designed extract are the critical controls.
Primary topic: smoke extract fan rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.
What usually goes wrong
These are the operational gaps that make generic Word RAMS fail on the next site.
Toilet-extract RAMS reused
No fire strategy.
Whole smoke panel isolated
Building blind.
Shaft left open for the next visit
A hole in the fire strategy.
Example
Roof smoke fan swap on an occupied car park
Built from one job description. You review and adjust every item before issuing it.
Job description
Replace SEF-2 on the roof of Riverside MSCP, Preston. Saturday, responsible person agrees level 3 closed as compensation, isolate the fan only, crane from the closed deck, shaft curb guarded, cause-and-effect witnessed before Sunday opening.
Activities identified
- General site work
- Roof work
- Manual handling
- Lifting operations
Method (9 steps)
- 1.Arrive and sign in. Arrive at Roof, Riverside MSCP, Preston, report to the Riverside Retail FM site contact, sign in and complete any site induction.
- 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
- 3.Set up exclusion zone below. Establish an exclusion zone below the work area with barriers and signage before any work at height starts.
- 4.Access the roof. Access the roof via the agreed route. Confirm edge protection is in place and identify any fragile areas before moving onto the roof.
- 5.Carry out the lift. Carry out lifts to the lift plan, with the exclusion zone in place and a trained slinger/signaller directing.
- 6.Disconnect and remove existing equipment. Disconnect and remove the existing equipment. Lower or carry it using mechanical aids or team lifts as planned.
- 7.Install new equipment. Position and fix the new equipment to the manufacturer's instructions.
- 8.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
- 9.Hand over and sign out. Hand over to the Riverside Retail FM site contact, report anything outstanding and sign out.
Main risks (6 in total)
Fall from roof edge
Residual MediumWho: Operatives
- Plan work to be done from below or from a MEWP where possible
- Edge protection (guard rails) or parapet of adequate height in place before work starts
- Safe access route to the roof agreed with the site; roof hatch secured open
- Where collective protection isn't possible, use a fall-restraint system with suitable anchors
- Work stops in high winds, ice or heavy rain
Fall through fragile roof or rooflight
Residual MediumWho: Operatives
- Treat all roof sheets and rooflights as fragile unless confirmed otherwise by the site
- Rooflights covered or protected with suitable mesh or barriers
- Staging or crawling boards used; no walking directly on sheets
- Safety netting or fall arrest below where required
Falling objects
Residual LowWho: People below, other trades, public
- Exclusion zone set up below the work area with barriers and signage
- Tools tethered when working at height; materials kept away from edges
- Banksman or second person controls the area during lifts and removals
- Hard hats worn in the exclusion zone
Adverse weather
Residual LowWho: Operatives
- Forecast checked before work; work at height stopped in high winds
- Breaks, water and shade in hot weather; warm clothing in cold
- Sun protection on exposed work in summer
+ 2 more risks in the full RAMS.
What to get right on this document
The strategy owns the outage
Named person, named measure.
Isolate the fan, not the system
Unless planned.
Commission is life safety
Rotation and signal, not ‘it spins’.
What this document has to cover
This is life-safety ventilation, not a toilet extract. A general HVAC RAMS that never mentions the fire-engineer interface, cause-and-effect or how the building stays occupied during the swap will fail.
A smoke extract fan rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.
Typical hazards to assess on this job
- Dropped fan on a roof or in a shaft
- Electric shock on a circuit that also serves other life-safety kit
- Building occupied without its smoke-control provision
- Work in a smoke shaft — falls and confined access
- Incorrect rotation or controls so the system fails a witness test
- Public at a roof edge or shaft opening
Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.
A method sequence that actually protects people
Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.
- Agree with the responsible person how smoke control is maintained or the building is managed during the outage
- Isolate only the named fan; do not kill the panel unless planned
- Lift and fix the fan; guard the shaft opening
- Wire to the cause-and-effect; label
- Commission airflow and controls; witness if the project requires it
- Do not leave a shaft open or a system in ‘hand’ overnight without agreement
Occupancy and other people
Offices and car parks stay occupied. Write the compensation measure — extra marshals, restricted floors — not ‘it will be quick’.
Substances and COSHH
An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:
- Sealants at the curb
- Paint on new guards
- Insulation if acoustic wrapping
How SafeForJob helps
- Describe this job in plain English and get suggested activities, risks and method steps
- Edit every line before you download or issue
- Reuse a previous RAMS and catch old client or site names
- Attach or create COSHH assessments where hazardous substances appear
What this page is not
This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer smoke extract fan rams document for a named job. You remain responsible for reviewing and issuing it.
Related reading
See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.
Related pages
- RAMS by tradeHVAC RAMSCreate HVAC and refrigeration RAMS online: rooftop units, split systems, refrigerant recovery and brazing. Suggested risks and method steps you review before issue.
- GuidesWhat is a RAMS?RAMS means risk assessment and method statement — usually one site-specific pack for a construction or maintenance job. Practical UK guidance for contractors — with links to free tools.
- Method statementsHVAC installation method statementWrite a hvac installation method statement for a named UK site. Clear sequence, interfaces and controls — review before issue.
- RAMS by jobConsumer unit replacement RAMSCreate a consumer unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEV charger installation RAMSCreate a ev charger installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobLighting rewire RAMSCreate a lighting rewire rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEICR testing RAMSCreate a eicr method statement for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobRooftop condenser replacement RAMSCreate a rooftop ac unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobSplit system installation RAMSCreate a split system installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
Questions
- Is this the same as an AOV?
- Related smoke-control family, different kit — use the smoke-vent RAMS for vents.
- Do I need a fire-engineer sign-off?
- Often yes for a change; this page does not replace that.
- Can we run on one fan?
- Only if the design allows — write that as the occupancy control.
- Inverter on the fan?
- Add electrical isolation of the drive; stored energy.