Slate roof replacement RAMS

Pitched slate work is height, falling materials and often a live building below. A flat-roof RAMS that talks about felt and burners is the wrong document.

Typical scope

  • Edge protection named
  • Exclusion below
  • Hoist or gin wheel
  • Weather abort
  • Survey before strip
  • Waste via chute/hoist

Quick answer

A slate roof replacement RAMS is the site-specific pack for stripping and re-covering a pitched slate roof. Fragile surfaces, edge protection, falling materials and manual handling dominate.

Primary topic: slate roof replacement rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.

What usually goes wrong

These are the operational gaps that make generic Word RAMS fail on the next site.

  • Felt-roof RAMS reused

    Burners and flat-roof text on a slate pitch.

  • No exclusion

    Slates dropped into a school playground.

  • Weather ignored

    No wind abort.

Example

Front pitch re-slate over a pavement

Built from one job description. You review and adjust every item before issuing it.

Job description

Strip and re-slate the front pitch at 2 Cathedral View, Durham. Independent scaffold, pavement licence, hoist, no work in high wind, church visitors kept outside the exclusion.

Activities identified

  • General site work
  • Mobile tower or scaffold
  • Lifting operations
  • Outdoor or exposed work

Method (6 steps)

  1. 1.Arrive and sign in. Arrive at 2 Cathedral View, Durham, report to the Cathedral View Trust site contact, sign in and complete any site induction.
  2. 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
  3. 3.Erect the tower. PASMA-trained operatives erect the mobile tower to the manufacturer's guide and inspect it before use.
  4. 4.Carry out the lift. Carry out lifts to the lift plan, with the exclusion zone in place and a trained slinger/signaller directing.
  5. 5.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
  6. 6.Hand over and sign out. Hand over to the Cathedral View Trust site contact, report anything outstanding and sign out.

Main risks (4 in total)

Fall from tower or scaffold, or collapse

Residual Medium

Who: Operatives, people nearby

  • Mobile towers erected by PASMA-trained persons to the manufacturer's guide
  • Scaffold erected by a competent scaffolder and tagged/inspected before use and every 7 days
  • Guard rails, toe boards and brick guards in place on working platforms
  • Castors locked and outriggers fitted; never moved while occupied

Falling objects

Residual Low

Who: People below, other trades, public

  • Exclusion zone set up below the work area with barriers and signage
  • Tools tethered when working at height; materials kept away from edges
  • Banksman or second person controls the area during lifts and removals
  • Hard hats worn in the exclusion zone

Lifting operations

Residual Medium

Who: Operatives, public, other trades

  • Lift planned by a competent person; lift plan in place
  • Lifting equipment and accessories have current LOLER thorough examination
  • Exclusion zone below the lift; nobody under suspended loads
  • Trained slinger/signaller directs the lift
  • Lifts stopped in high winds

Adverse weather

Residual Low

Who: Operatives

  • Forecast checked before work; work at height stopped in high winds
  • Breaks, water and shade in hot weather; warm clothing in cold
  • Sun protection on exposed work in summer

What to get right on this document

Name the access

Scaffold, tower or MEWP — and who inspects it.

Below is part of the job

Garden, pavement or playground exclusion.

Stop for wind

Write the abort, not ‘as safe as possible’.

What this document has to cover

Pitched slate work is height, falling materials and often a live building below. A flat-roof RAMS that talks about felt and burners is the wrong document.

A slate roof replacement rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.

Typical hazards to assess on this job

  • Falls from the eaves or through the roof
  • Slates and tools falling into gardens or pavements
  • Manual handling of slates and battens on ladders/hoists
  • Weather — wind making the roof unsafe
  • Asbestos in old underfelts or ridges on some buildings
  • Public interface at the boundary

Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.

A method sequence that actually protects people

Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.

  • Confirm edge protection, scaffold or MEWP and exclusion below
  • Check surveys before disturbing ridges, flashings or underfelt
  • Strip in bays, load-out via hoist, do not stockpile at the eaves
  • Batton, felt and slate to the specification
  • Ridges, valleys and making good
  • Clear gutters, remove waste, hand over

Occupancy and other people

Housing and churches sit on pavements and gardens. Exclusion and sheeting below are as important as the ridge.

Substances and COSHH

An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:

  • Bitumen/felt residues
  • Possible asbestos in old felts
  • Timber treatment if used

How SafeForJob helps

  • Describe this job in plain English and get suggested activities, risks and method steps
  • Edit every line before you download or issue
  • Reuse a previous RAMS and catch old client or site names
  • Attach or create COSHH assessments where hazardous substances appear

What this page is not

This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer slate roof replacement rams document for a named job. You remain responsible for reviewing and issuing it.

Related reading

See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.

Related pages

All rams by job · RAMS by trade · Free RAMS generator

Questions

Do I need a pavement licence?
If you occupy the highway, yes — put it in the RAMS.
What about bats?
Wildlife constraints are a client/survey issue; do not start strip if a survey is outstanding.
Torch-on valleys?
If you use heat, add hot works — do not hide it in a slate RAMS.
Can I work off ladders?
Not as the main access for a re-cover. Name a proper working platform.