This is not a cable containment RAMS. This job covers replacing a rising electrical main in a multi-storey building, and the control that keeps people safe is isolation of the supply and a locked riser before any joint is opened. If the RAMS never names which floors lose power, how the old main is supported and how the riser stays locked, a principal contractor will send it back.
Typical scope
- Named isolation
- Riser locked
- Landing exclusion
- Fire-stop same visit
- Test before restore
- Open tap-offs recorded
Quick answer
A rising main replacement rams covers replacing a rising electrical main in a multi-storey building on a named UK site. The critical control is isolation of the supply and a locked riser before any joint is opened. Write which floors lose power, how the old main is supported and how the riser stays locked into the sequence — a pack that could describe any cable containment RAMS will not survive a competent review.
Primary topic: rising main replacement rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.
What usually goes wrong
These are the operational gaps that make generic Word RAMS fail on the next site.
Containment RAMS reused
No isolation, no joints.
Riser wedged open
A shortcut.
Fire-stop ‘tomorrow’
Compartment open.
Example
Saturday rising-main swap
Built from one job description. You review and adjust every item before issuing it.
Job description
Replace the rising main in stair B at Harbour View, Aberdeen. 07:00–18:00 isolation, riser locked, two-person lift of lengths, fire-stop at each floor, flats 12–24 on a temporary supply agreed with the housing officer.
Activities identified
- General site work
- Manual handling
- Occupied premises or public areas
Method (7 steps)
- 1.Arrive and sign in. Arrive at Stair B riser, Harbour View, Aberdeen, report to the Harbour View Housing site contact, sign in and complete any site induction.
- 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
- 3.Set up the work area. Set up barriers and signage around the work area and keep it clear of other people.
- 4.Disconnect and remove existing equipment. Disconnect and remove the existing equipment. Lower or carry it using mechanical aids or team lifts as planned.
- 5.Install new equipment. Position and fix the new equipment to the manufacturer's instructions.
- 6.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
- 7.Hand over and sign out. Hand over to the Harbour View Housing site contact, report anything outstanding and sign out.
Main risks (2 in total)
Manual handling
Residual MediumWho: Operatives
- Use mechanical aids (trolleys, sack trucks, hoists) for heavy items
- Team lifts for items too heavy or awkward for one person
- Route planned and cleared before moving items
- Operatives trained in safe lifting techniques
- Gloves with good grip and safety footwear
Members of the public and building occupants
Residual LowWho: Public, customers, staff, residents
- Work area segregated with barriers and clear signage
- Work timed for quieter periods where possible, agreed with the site
- Tools and materials never left unattended in public areas
- Site contact informed of work areas and any disruption
What to get right on this document
The main is dead until proved
Every floor.
The riser is a room
Locked door.
Close the compartment
Same visit.
What this document has to cover
This is not a cable containment RAMS. This job covers replacing a rising electrical main in a multi-storey building, and the control that keeps people safe is isolation of the supply and a locked riser before any joint is opened. If the RAMS never names which floors lose power, how the old main is supported and how the riser stays locked, a principal contractor will send it back.
A rising main replacement rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.
Typical hazards to assess on this job
- Electric shock on a rising main that is still live on another floor
- Dropped lengths crushing people in the riser
- Fire-stopping left open at compartment floors
- Falls from podiums in a narrow shaft
- Other trades using the riser as a shortcut
- Re-energising a floor that still has open tails
Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.
A method sequence that actually protects people
Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.
- Authorised person isolates and proves dead the named main; lock the riser
- Set exclusion at every landing door — not a cone
- Support and cut out the old main; land the new length before making joints
- Fire-stop every compartment the same visit
- Test insulation and continuity before anyone asks to restore
- Hand over torque or joint records and remaining open tap-offs
Occupancy and other people
Flats and offices keep using floors the same riser serves. Write who loses power, for how long, and that the riser door is locked — not wedged.
Substances and COSHH
An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:
- Joint compound
- Fire-stopping mastics
- Cable-cleaning solvents
How SafeForJob helps
- Describe this job in plain English and get suggested activities, risks and method steps
- Edit every line before you download or issue
- Reuse a previous RAMS and catch old client or site names
- Attach or create COSHH assessments where hazardous substances appear
What this page is not
This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer rising main replacement rams document for a named job. You remain responsible for reviewing and issuing it.
Related reading
See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.
Related pages
- RAMS by tradeElectrical RAMSCreate a site-specific electrical RAMS online. Describe the job, review suggested risks like safe isolation and work at height, and download a professional PDF.
- GuidesWhat is a RAMS?RAMS means risk assessment and method statement — usually one site-specific pack for a construction or maintenance job. Practical UK guidance for contractors — with links to free tools.
- Method statementsMethod statement for electrical worksWrite a method statement for electrical works for a named UK site. Clear sequence, interfaces and controls — review before issue.
- RAMS by jobConsumer unit replacement RAMSCreate a consumer unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEV charger installation RAMSCreate a ev charger installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobLighting rewire RAMSCreate a lighting rewire rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEICR testing RAMSCreate a eicr method statement for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobRooftop condenser replacement RAMSCreate a rooftop ac unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobSplit system installation RAMSCreate a split system installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
Questions
- Is this busbar trunking?
- Related energy, different joints. Use the busbar page if it is a bar, not a cable main.
- Can one floor stay live?
- Only if isolation proves it. Write the boundary.
- Who signs fire-stopping?
- Usually the fire package — photograph and label it.
- Live work to keep lifts up?
- Default is isolate. Temporary supplies are a written method.