Pressurisation unit RAMS
This is the machine that stops a sealed system collapsing or lifting a relief. A booster RAMS that never mentions system pressure, dosing or how you avoid filling a dirty system with raw mains will fail.
Typical scope
- Designed cold-fill pressure
- Backflow protection
- Controlled depressurise
- Temporary heat if needed
- Leak check at pressure
- Set-point labelled
Quick answer
A pressurisation-unit RAMS covers installing or swapping the unit that maintains pressure on a sealed heating or CHW system. Isolation of a live system, water damage and wrong fill chemistry are the usual harms.
Primary topic: pressurisation unit rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.
What usually goes wrong
These are the operational gaps that make generic Word RAMS fail on the next site.
Booster RAMS reused
Wrong machine, wrong pressure.
Filled to 4 bar ‘to be safe’
Relief lifting.
Raw mains into a glycol system
Chemistry wrecked.
Example
Sealed-system pressurisation in a school
Built from one job description. You review and adjust every item before issuing it.
Job description
Swap the pressurisation unit at Millfield Primary, Norwich, during a Friday inset. System held on a temporary fill bottle, cold-fill set to 1.2 bar as designed, backflow as specified, leak check, caretaker shown the labelled set-point.
Activities identified
- General site work
- Manual handling
Method (6 steps)
- 1.Arrive and sign in. Arrive at Plant room, Millfield Primary, Norwich, report to the Millfield Primary site contact, sign in and complete any site induction.
- 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
- 3.Disconnect and remove existing equipment. Disconnect and remove the existing equipment. Lower or carry it using mechanical aids or team lifts as planned.
- 4.Install new equipment. Position and fix the new equipment to the manufacturer's instructions.
- 5.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
- 6.Hand over and sign out. Hand over to the Millfield Primary site contact, report anything outstanding and sign out.
Main risks (1 in total)
Manual handling
Residual MediumWho: Operatives
- Use mechanical aids (trolleys, sack trucks, hoists) for heavy items
- Team lifts for items too heavy or awkward for one person
- Route planned and cleared before moving items
- Operatives trained in safe lifting techniques
- Gloves with good grip and safety footwear
What to get right on this document
Pressure is designed
Write the number.
Backflow is water regs
Do not tee a hose.
Heat is occupancy
Temporary fill or a timed outage.
What this document has to cover
This is the machine that stops a sealed system collapsing or lifting a relief. A booster RAMS that never mentions system pressure, dosing or how you avoid filling a dirty system with raw mains will fail.
A pressurisation unit rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.
Typical hazards to assess on this job
- Flood from a relief or a broken flexible on first fill
- Electric shock on the unit isolator
- Wrong pressure blowing a valve or collapsing a boiler
- Raw mains into a treated system (corrosion and hygiene)
- Manual handling in a packed plant room
- Building losing heat because the system was drained without a plan
Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.
A method sequence that actually protects people
Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.
- Agree isolation and whether the system must stay up on a temporary fill
- Isolate, depressurise in a controlled way, cap flexibles
- Fit the new unit, connect break-tank or mains with the specified backflow
- Set cold-fill pressure to the design; dose only as the water-quality spec
- Check for leaks at running pressure; label the set-point
- Hand over the fill pressure and the do-not-crank instruction
Occupancy and other people
Schools in January cannot lose heat for a ‘quick swap’. Write the temporary arrangement and who is told if radiators go cold.
Substances and COSHH
An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:
- System inhibitors / glycol
- Raw mains water (backflow)
- Cleaning wipes
How SafeForJob helps
- Describe this job in plain English and get suggested activities, risks and method steps
- Edit every line before you download or issue
- Reuse a previous RAMS and catch old client or site names
- Attach or create COSHH assessments where hazardous substances appear
What this page is not
This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer pressurisation unit rams document for a named job. You remain responsible for reviewing and issuing it.
Related reading
See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.
Related pages
- RAMS by tradePlumbing RAMSCreate plumbing and heating RAMS online: boiler swaps, pipework, unvented cylinders and drain-downs. Suggested risks and method steps, reviewed by you.
- GuidesWhat is a RAMS?RAMS means risk assessment and method statement — usually one site-specific pack for a construction or maintenance job. Practical UK guidance for contractors — with links to free tools.
- Method statementsPlumbing method statementWrite a plumbing method statement for a named UK site. Clear sequence, interfaces and controls — review before issue.
- RAMS by jobConsumer unit replacement RAMSCreate a consumer unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEV charger installation RAMSCreate a ev charger installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobLighting rewire RAMSCreate a lighting rewire rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEICR testing RAMSCreate a eicr method statement for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobRooftop condenser replacement RAMSCreate a rooftop ac unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobSplit system installation RAMSCreate a split system installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
Questions
- Is this a booster set?
- No. Boosters serve domestic cold water; this holds a sealed heating/CHW system.
- Do I drain the whole system?
- Only if you must — write the volume and inhibitor top-up.
- Glycol systems?
- Add COSHH and a no-mains-hose rule.
- Who owns the set-point?
- The plant operator — label it so the next person does not crank it.