Inverter replacement RAMS

An inverter swap is a live PV electrical job, not a consumer-unit change. A rooftop-PV RAMS that never mentions DC still being live after AC isolation or how you stop an untrained person opening the isolator will fail.

Typical scope

  • DC treated as live in daylight
  • Isolation order as designed
  • Handling plan for the unit
  • Connectors not opened under load
  • Export settings as specified
  • Isolators labelled

Quick answer

An inverter-replacement RAMS covers isolating DC and AC, lifting out a failed inverter and commissioning a new unit on a named array. Stored DC, height if wall- or roof-mounted, and the building that still wants power are the core.

Primary topic: inverter replacement rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.

What usually goes wrong

These are the operational gaps that make generic Word RAMS fail on the next site.

  • CU RAMS reused

    No DC.

  • MC4s pulled under load

    Arc.

  • Inverter dropped through a hatch

    No handling plan.

Example

String inverter swap in a school loft

Built from one job description. You review and adjust every item before issuing it.

Job description

Replace the 20 kW inverter at Millfield Primary, Norwich, inset day. DC and AC locked off in order, two-person loft lift, MC4s opened off-load, export settings as the DNO letter, caretaker shown isolators, classrooms on the lighting circuit told.

Activities identified

  • General site work
  • Electrical isolation
  • Manual handling
  • Solar PV and batteries

Method (11 steps)

  1. 1.Arrive and sign in. Arrive at Loft plant, Millfield Primary, Norwich, report to the Millfield Primary site contact, sign in and complete any site induction.
  2. 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
  3. 3.Isolate the electrical supply. Identify the relevant circuit, isolate, lock off and tag. Prove dead with an approved voltage indicator, proved before and after use.
  4. 4.Disconnect and remove existing equipment. Disconnect and remove the existing equipment. Lower or carry it using mechanical aids or team lifts as planned.
  5. 5.Install mounting system and modules. Fix the mounting system to the roof structure, then install modules. Keep DC isolators open.
  6. 6.Install new equipment. Position and fix the new equipment to the manufacturer's instructions.
  7. 7.Connect inverter and DC strings. Install the inverter and AC connection, then connect DC strings last with isolators open.
  8. 8.Test and commission. Test and commission the installation. Record results.
  9. 9.Remove isolation and re-energise. Confirm the work is complete and everyone is clear, remove locks and re-energise.
  10. 10.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
  11. 11.Hand over and sign out. Hand over to the Millfield Primary site contact, report anything outstanding and sign out.

Main risks (3 in total)

Electric shock or burns

Residual Medium

Who: Operatives, building occupants

  • Work carried out dead — no live working
  • Safe isolation: isolate, lock off, tag, and prove dead with an approved voltage indicator (GS38) proved before and after
  • Only competent, qualified electricians carry out electrical work
  • Permit to work obtained where the site requires one
  • Personal locks and keys retained by the person working

Manual handling

Residual Medium

Who: Operatives

  • Use mechanical aids (trolleys, sack trucks, hoists) for heavy items
  • Team lifts for items too heavy or awkward for one person
  • Route planned and cleared before moving items
  • Operatives trained in safe lifting techniques
  • Gloves with good grip and safety footwear

DC electric shock and arc (solar PV / batteries)

Residual High

Who: Installers

  • DC strings connected last; isolators open during installation
  • Never make or break DC connectors under load
  • Modules covered where practical when working on DC wiring
  • Installers competent in PV/battery installation (e.g. MCS-aligned training)
  • Insulated tools and gloves

What to get right on this document

DC stays dangerous

Daylight equals voltage.

Order of isolation is written

AC and DC.

The unit is a lift

Hatch and two people.

What this document has to cover

An inverter swap is a live PV electrical job, not a consumer-unit change. A rooftop-PV RAMS that never mentions DC still being live after AC isolation or how you stop an untrained person opening the isolator will fail.

An inverter replacement rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.

Typical hazards to assess on this job

  • Electric shock on DC strings that remain live in daylight
  • Arc on DC connectors opened under load
  • Dropped inverter from a wall or loft hatch
  • AC back-feed from the grid or a battery
  • Occupants without power if the AC isolator also feeds other circuits
  • Heat and restricted space in a loft plant

Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.

A method sequence that actually protects people

Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.

  • Isolate AC and DC in the designed order; treat DC as live until connectors are opened to the method
  • Lock off; label; exclude others from the isolators
  • Support and lift the old unit; land the new one
  • Terminate, earth, set export and protection as specified
  • Commission; do not leave DC connectors exposed
  • Hand over isolator positions and the remaining defects

Occupancy and other people

Homes and schools still need lights. Write which circuits die and that a loft hatch is not a one-person drop of a 25 kg inverter.

Substances and COSHH

An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:

  • Cleaning wipes on heat sinks
  • Cable-tie debris
  • Battery electrolyte only if a hybrid is in the same visit

How SafeForJob helps

  • Describe this job in plain English and get suggested activities, risks and method steps
  • Edit every line before you download or issue
  • Reuse a previous RAMS and catch old client or site names
  • Attach or create COSHH assessments where hazardous substances appear

What this page is not

This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer inverter replacement rams document for a named job. You remain responsible for reviewing and issuing it.

Related reading

See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.

Related pages

All rams by job · RAMS by trade · Free RAMS generator

Questions

Is this a rooftop module job?
No — this is the inverter only. Attach the roof RAMS if you also walk the array.
Hybrid / battery?
Add battery DC and the battery RAMS if you open that cabinet.
Can I work at dusk to ‘kill DC’?
Voltage falls but isolation is still the method — do not rely on darkness.
Who sets export?
As the DNO / specification — do not invent a limit.