Ground-mount solar RAMS

This is a construction site with electrical commissioning at the end. A rooftop PV RAMS that talks about eaves is the wrong document.

Typical scope

  • Plant-pedestrian segregation
  • DC isolation
  • Module handling
  • Cable trenches
  • Perimeter fence
  • Commissioning

Quick answer

A ground-mount solar RAMS covers piling or ballasted frames, module handling, DC isolation and construction-site plant on fields or brownfield land. Plant, lifting and DC are the core.

Primary topic: ground mount solar rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.

What usually goes wrong

These are the operational gaps that make generic Word RAMS fail on the next site.

  • Rooftop RAMS reused

    No plant or trench.

  • Strings live while people still laying

    DC not controlled.

  • Open gate

    Public on site.

Example

2 MW field array

Built from one job description. You review and adjust every item before issuing it.

Job description

Install ground-mount PV on Parcel B, Fen Solar, Cambridgeshire. Plant routes, module stillages, DC stringing after frames, trench team segregated, perimeter fence before commissioning.

Activities identified

  • General site work
  • Manual handling
  • Excavation
  • Solar PV and batteries

Method (12 steps)

  1. 1.Arrive and sign in. Arrive at Parcel B, Fen Solar, Cambridgeshire, report to the Fen Solar Ltd site contact, sign in and complete any site induction.
  2. 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
  3. 3.Locate buried services. Review service drawings and scan the area with a CAT and Genny. Mark located services before breaking ground.
  4. 4.Disconnect and remove existing equipment. Disconnect and remove the existing equipment. Lower or carry it using mechanical aids or team lifts as planned.
  5. 5.Excavate. Excavate by hand near located services, then by machine. Support or batter back excavations and keep spoil away from the edge.
  6. 6.Install mounting system and modules. Fix the mounting system to the roof structure, then install modules. Keep DC isolators open.
  7. 7.Install new equipment. Position and fix the new equipment to the manufacturer's instructions.
  8. 8.Connect inverter and DC strings. Install the inverter and AC connection, then connect DC strings last with isolators open.
  9. 9.Test and commission. Test and commission the installation. Record results.
  10. 10.Backfill and reinstate. Backfill in layers, compact, and reinstate the surface. Remove barriers once the area is safe.
  11. 11.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
  12. 12.Hand over and sign out. Hand over to the Fen Solar Ltd site contact, report anything outstanding and sign out.

Main risks (4 in total)

Manual handling

Residual Medium

Who: Operatives

  • Use mechanical aids (trolleys, sack trucks, hoists) for heavy items
  • Team lifts for items too heavy or awkward for one person
  • Route planned and cleared before moving items
  • Operatives trained in safe lifting techniques
  • Gloves with good grip and safety footwear

Excavation collapse and falls into excavations

Residual Medium

Who: Operatives, public

  • Excavations battered back or supported (trench boxes/shoring) where people enter
  • Spoil and plant kept away from the edge
  • Edge protection and barriers around open excavations
  • Excavations inspected at the start of each shift by a competent person

Striking buried services

Residual Medium

Who: Operatives, public

  • Service drawings obtained before digging
  • Area scanned with a CAT and Genny by a trained operator; services marked
  • Trial holes dug by hand near located services (safe digging practice)

DC electric shock and arc (solar PV / batteries)

Residual High

Who: Installers

  • DC strings connected last; isolators open during installation
  • Never make or break DC connectors under load
  • Modules covered where practical when working on DC wiring
  • Installers competent in PV/battery installation (e.g. MCS-aligned training)
  • Insulated tools and gloves

What to get right on this document

It is a construction site

Segregation and welfare.

DC is live energy

When strings become live, write it.

The fence is a control

When it goes up in the sequence.

What this document has to cover

This is a construction site with electrical commissioning at the end. A rooftop PV RAMS that talks about eaves is the wrong document.

A ground mount solar rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.

Typical hazards to assess on this job

  • Plant versus people on uneven ground
  • Manual handling of modules
  • DC shock during stringing
  • Excavation for cables
  • Public or livestock at the fence line
  • Weather — wind on large modules

Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.

A method sequence that actually protects people

Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.

  • Set the site: welfare, exclusion, plant routes
  • Install frames to design
  • Module lift and string with DC isolation discipline
  • Trench, cable, backfill
  • Inverter commission, fence and signage
  • Demobilise waste and compound

Occupancy and other people

Fields attract walkers and livestock. Fencing and gates are a RAMS control, not just a programme item.

Substances and COSHH

An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:

  • Diesel
  • Module films/adhesives
  • Dust from trenching

How SafeForJob helps

  • Describe this job in plain English and get suggested activities, risks and method steps
  • Edit every line before you download or issue
  • Reuse a previous RAMS and catch old client or site names
  • Attach or create COSHH assessments where hazardous substances appear

What this page is not

This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer ground mount solar rams document for a named job. You remain responsible for reviewing and issuing it.

Related reading

See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.

Related pages

All rams by job · RAMS by trade · Free RAMS generator

Questions

Do I need a separate trench RAMS?
You can combine if excavation controls are full; otherwise attach it.
Wind abort?
Yes for module handling — write it.
Brownfield contamination?
Surveys first; the RAMS should not start blind.
Grid connection later?
Still isolate and label unfinished DC.