RAMS by job · UK
Generator installation RAMS
This is a plant lift plus an electrical installation plus a fuel store. A temporary-site-power RAMS that never mentions ATS, flue or bund is not enough for a permanent set.
Typical scope
- Lift plan
- Exhaust vs air intakes
- ATS isolation
- Fuel bund
- Earthing
- Test-run hours agreed
Quick answer
A generator installation RAMS covers placing, connecting and commissioning a standby or temporary generator. Lifting, fuel, exhaust, earthing and changeover (ATS) isolation are the critical controls.
Primary topic: generator installation rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.
What usually goes wrong
These are the operational gaps that make generic Word RAMS fail on the next site.
Temporary genny RAMS reused
No ATS or flue.
Exhaust at the AHU intake
Fumes in the building.
Keys in the set
Anyone can start it live.
Example
Standby set at a hospital energy centre
Built from one job description. You review and adjust every item before issuing it.
Job description
Install a 500 kVA standby generator at County Hospital, Lincoln. Saturday crane, exhaust away from Ward B intakes, ATS lock-off, bunded tank, test run 06:00–07:00 agreed with estates, keys in the dutyholder’s cabinet.
Activities identified
- General site work
- Electrical isolation
- Manual handling
- Lifting operations
- Confined space
- Occupied premises or public areas
Method (12 steps)
- 1.Arrive and sign in. Arrive at Energy centre, County Hospital, Lincoln, report to the County Hospital Estates site contact, sign in and complete any site induction.
- 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
- 3.Set up the work area. Set up barriers and signage around the work area and keep it clear of other people.
- 4.Isolate the electrical supply. Identify the relevant circuit, isolate, lock off and tag. Prove dead with an approved voltage indicator, proved before and after use.
- 5.Confined space permit and gas test. Obtain the permit to work, test the atmosphere and confirm rescue arrangements before anyone enters.
- 6.Carry out the lift. Carry out lifts to the lift plan, with the exclusion zone in place and a trained slinger/signaller directing.
- 7.Disconnect and remove existing equipment. Disconnect and remove the existing equipment. Lower or carry it using mechanical aids or team lifts as planned.
- 8.Install new equipment. Position and fix the new equipment to the manufacturer's instructions.
- 9.Carry out electrical work. Carry out the electrical work on the isolated circuit to BS 7671.
- 10.Remove isolation and re-energise. Confirm the work is complete and everyone is clear, remove locks and re-energise.
- 11.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
- 12.Hand over and sign out. Hand over to the County Hospital Estates site contact, report anything outstanding and sign out.
Main risks (5 in total)
Electric shock or burns
Residual MediumWho: Operatives, building occupants
- Work carried out dead — no live working
- Safe isolation: isolate, lock off, tag, and prove dead with an approved voltage indicator (GS38) proved before and after
- Only competent, qualified electricians carry out electrical work
- Permit to work obtained where the site requires one
- Personal locks and keys retained by the person working
Manual handling
Residual MediumWho: Operatives
- Use mechanical aids (trolleys, sack trucks, hoists) for heavy items
- Team lifts for items too heavy or awkward for one person
- Route planned and cleared before moving items
- Operatives trained in safe lifting techniques
- Gloves with good grip and safety footwear
Lifting operations
Residual MediumWho: Operatives, public, other trades
- Lift planned by a competent person; lift plan in place
- Lifting equipment and accessories have current LOLER thorough examination
- Exclusion zone below the lift; nobody under suspended loads
- Trained slinger/signaller directs the lift
- Lifts stopped in high winds
Confined space
Residual MediumWho: Operatives, rescuers
- Avoid entry — do the work from outside where possible
- Permit to work and confined space trained operatives
- Atmosphere tested before and during entry with a calibrated gas monitor
- Emergency rescue arrangements in place before entry
+ 1 more risks in the full RAMS.
What to get right on this document
Intakes beat convenience
Where the exhaust points.
ATS is isolation
Named, locked.
Fuel is COSHH and fire
Bund and spill.
What this document has to cover
This is a plant lift plus an electrical installation plus a fuel store. A temporary-site-power RAMS that never mentions ATS, flue or bund is not enough for a permanent set.
A generator installation rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.
Typical hazards to assess on this job
- Dropped load when the set is craned or offloaded
- Electric shock on mains, generator and ATS
- Fire and spill from fuel stores
- CO and fumes from exhaust into occupied air intakes
- Noise at the boundary
- Unauthorised start while people are on the terminals
Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.
A method sequence that actually protects people
Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.
- Lift plan, bund position and exhaust direction agreed with the building’s air intakes
- Isolate mains and ATS; lock off; prove dead
- Position, earth, fuel and flue as designed
- Cable, terminate, label
- Commission, including a planned test that does not dump fumes into the building
- Handover keys, interlocks and the fuel COSHH
Occupancy and other people
Hospitals and offices have air intakes and sleepers next door. Exhaust direction and test-run hours are occupancy controls, not commissioning trivia.
Substances and COSHH
An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:
- Diesel
- Engine oils and coolants
- Exhaust emissions (CO, particulates)
How SafeForJob helps
- Describe this job in plain English and get suggested activities, risks and method steps
- Edit every line before you download or issue
- Reuse a previous RAMS and catch old client or site names
- Attach or create COSHH assessments where hazardous substances appear
What this page is not
This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer generator installation rams document for a named job. You remain responsible for reviewing and issuing it.
Related reading
See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.
Related pages
- RAMS by tradeElectrical RAMSCreate a site-specific electrical RAMS online. Describe the job, review suggested risks like safe isolation and work at height, and download a professional PDF.
- GuidesWhat is a RAMS?RAMS means risk assessment and method statement — usually one site-specific pack for a construction or maintenance job. Practical UK guidance for contractors — with links to free tools.
- Method statementsMethod statement for electrical worksWrite a method statement for electrical works for a named UK site. Clear sequence, interfaces and controls — review before issue.
- RAMS by jobConsumer unit replacement RAMSCreate a consumer unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEV charger installation RAMSCreate a ev charger installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobLighting rewire RAMSCreate a lighting rewire rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEICR testing RAMSCreate a eicr method statement for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobRooftop condenser replacement RAMSCreate a rooftop ac unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobSplit system installation RAMSCreate a split system installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
Questions
- Is this the same as temporary site power?
- Related, but ATS, flue and a permanent fuel store change the method.
- Gas generators?
- Different fuel COSHH and flue — do not reuse diesel text.
- Do I need DSEAR?
- Fuel storage may trigger it — get advice; this page is not that assessment.
- Who witnesses the test?
- Name estates; they own the occupancy during a black-building test.