Flue system installation RAMS
A flue is a hot combustion path through other people’s rooms. A boiler RAMS that never mentions the roof terminal, fire-stopping of the enclosure or how you stop downdraught into a bedroom will fail.
Typical scope
- Appliance isolated and cold
- Roof access and exclusion
- Supports as designed
- Fire enclosure same visit
- Same-day weather at the terminal
- Commission with the appliance
Quick answer
A flue-system RAMS covers installing a rigid or twin-wall flue from a boiler, generator or kitchen appliance through a building and roof. Height, combustion products, fire separation and the public below are the critical harms.
Primary topic: flue installation rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.
What usually goes wrong
These are the operational gaps that make generic Word RAMS fail on the next site.
Boiler RAMS reused
No shaft, no terminal.
Open flue overnight
Fumes into a bedroom.
Terminal left unweathered
Water down the shaft.
Example
Twin-wall flue through a hotel shaft
Built from one job description. You review and adjust every item before issuing it.
Job description
Install a twin-wall flue from the basement boiler to the roof at Harbourview Hotel, Scarborough. Boiler isolated, shaft exclusion, supports as drawn, fire-stop each floor the same day, roof terminal weathered before 16:00, commission with the gas engineer.
Activities identified
- General site work
- Roof work
- Manual handling
- Occupied premises or public areas
- Plumbing and heating systems
Method (12 steps)
- 1.Arrive and sign in. Arrive at Harbourview Hotel, Scarborough, report to the Harbourview Hotel site contact, sign in and complete any site induction.
- 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
- 3.Set up the work area. Set up barriers and signage around the work area and keep it clear of other people.
- 4.Set up exclusion zone below. Establish an exclusion zone below the work area with barriers and signage before any work at height starts.
- 5.Isolate and drain down. Isolate the water/heating supply, allow to cool and drain down the affected section. Confirm isolation before breaking into pipework.
- 6.Access the roof. Access the roof via the agreed route. Confirm edge protection is in place and identify any fragile areas before moving onto the roof.
- 7.Disconnect and remove existing equipment. Disconnect and remove the existing equipment. Lower or carry it using mechanical aids or team lifts as planned.
- 8.Install new equipment. Position and fix the new equipment to the manufacturer's instructions.
- 9.Install pipework. Install and connect pipework. Use press-fit or mechanical joints in place of hot works where possible.
- 10.Test and commission. Test and commission the installation. Record results.
- 11.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
- 12.Hand over and sign out. Hand over to the Harbourview Hotel site contact, report anything outstanding and sign out.
Main risks (8 in total)
Fall from roof edge
Residual MediumWho: Operatives
- Plan work to be done from below or from a MEWP where possible
- Edge protection (guard rails) or parapet of adequate height in place before work starts
- Safe access route to the roof agreed with the site; roof hatch secured open
- Where collective protection isn't possible, use a fall-restraint system with suitable anchors
- Work stops in high winds, ice or heavy rain
Fall through fragile roof or rooflight
Residual MediumWho: Operatives
- Treat all roof sheets and rooflights as fragile unless confirmed otherwise by the site
- Rooflights covered or protected with suitable mesh or barriers
- Staging or crawling boards used; no walking directly on sheets
- Safety netting or fall arrest below where required
Falling objects
Residual LowWho: People below, other trades, public
- Exclusion zone set up below the work area with barriers and signage
- Tools tethered when working at height; materials kept away from edges
- Banksman or second person controls the area during lifts and removals
- Hard hats worn in the exclusion zone
Adverse weather
Residual LowWho: Operatives
- Forecast checked before work; work at height stopped in high winds
- Breaks, water and shade in hot weather; warm clothing in cold
- Sun protection on exposed work in summer
+ 4 more risks in the full RAMS.
What to get right on this document
The route is a fire path
Enclosure and stops as specified.
Cold before you break in
Isolation of the appliance.
Terminal is height and weather
Same day.
What this document has to cover
A flue is a hot combustion path through other people’s rooms. A boiler RAMS that never mentions the roof terminal, fire-stopping of the enclosure or how you stop downdraught into a bedroom will fail.
A flue installation rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.
Typical hazards to assess on this job
- Falls from the roof at the terminal
- Burns from a flue you thought was isolated
- Fire if the enclosure or clearances are ignored
- Combustion products leaking into occupied rooms
- Dropped sections down a shaft onto people
- Public at the terminal over a pavement
Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.
A method sequence that actually protects people
Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.
- Confirm the appliance is isolated and cold; agree the route and fire enclosure
- Set roof access and exclusion below the terminal
- Build the flue from the appliance out; support as designed — no hanging unsecured lengths
- Fire-stop and enclose as specified the same visit you open a compartment
- Weather the terminal the same day
- Commission with the appliance engineer; do not leave an open flue overnight
Occupancy and other people
Flats and hotels have bedrooms on the other side of a shaft. Write how you test for leakage and that you do not run the appliance as a ‘check’ while joints are open.
Substances and COSHH
An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:
- Joint sealants specified for the system
- Insulation in the enclosure
- Lead or flashing compounds at the roof
How SafeForJob helps
- Describe this job in plain English and get suggested activities, risks and method steps
- Edit every line before you download or issue
- Reuse a previous RAMS and catch old client or site names
- Attach or create COSHH assessments where hazardous substances appear
What this page is not
This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer flue installation rams document for a named job. You remain responsible for reviewing and issuing it.
Related reading
See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.
Related pages
- RAMS by tradeHVAC RAMSCreate HVAC and refrigeration RAMS online: rooftop units, split systems, refrigerant recovery and brazing. Suggested risks and method steps you review before issue.
- GuidesWhat is a RAMS?RAMS means risk assessment and method statement — usually one site-specific pack for a construction or maintenance job. Practical UK guidance for contractors — with links to free tools.
- Method statementsHVAC installation method statementWrite a hvac installation method statement for a named UK site. Clear sequence, interfaces and controls — review before issue.
- RAMS by jobConsumer unit replacement RAMSCreate a consumer unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEV charger installation RAMSCreate a ev charger installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobLighting rewire RAMSCreate a lighting rewire rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEICR testing RAMSCreate a eicr method statement for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobRooftop condenser replacement RAMSCreate a rooftop ac unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobSplit system installation RAMSCreate a split system installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
Questions
- Is this Gas Safe?
- The appliance connection usually is; the flue still needs the specified system. This is not a competence ruling.
- Generator flue?
- Add exhaust temperature, CO and intake separation — do not copy a boiler flue blindly.
- Existing asbestos flashed terminal?
- Survey before you break the roof.
- Can I use any twin-wall?
- Only the system specified for that appliance and fuel.