Fire stopping RAMS

Fire-stopping is not ‘mastic in a hole’. A generic fit-out RAMS that never names the tested system, the compartment wall, or how you leave an unfinished opening will fail a clerk of works and a fire engineer.

Typical scope

  • Specified system named
  • Opening surveyed before fill
  • Same-shift close or approved temporary seal
  • Label and photo record
  • Occupied-riser controls
  • Other-trade briefing not to break seals

Quick answer

A fire-stopping RAMS is a site-specific pack for sealing service penetrations and linear gaps so the fire-resisting construction still performs. The critical controls are the specified system, cleanliness of the opening, and not leaving a hole overnight.

Primary topic: fire stopping rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.

What usually goes wrong

These are the operational gaps that make generic Word RAMS fail on the next site.

  • Mastic-as-you-go

    Unspecified product in a compartment wall.

  • Holes left overnight

    Fire strategy broken until Monday.

  • No record

    Clerk of works cannot trace the seal.

Example

Riser fire-stopping on a live ward floor

Built from one job description. You review and adjust every item before issuing it.

Job description

Seal mechanical and electrical penetrations in riser R3, level 2, County Hospital, Lincoln. Specified collars and coated batt only, cupboard locked, temporary seal on two delayed pipes, photos in the fire-stopping log before 06:00.

Activities identified

  • General site work
  • Electrical isolation
  • Occupied premises or public areas

Method (8 steps)

  1. 1.Arrive and sign in. Arrive at Riser R3, County Hospital, Lincoln, report to the County Hospital Estates site contact, sign in and complete any site induction.
  2. 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
  3. 3.Set up the work area. Set up barriers and signage around the work area and keep it clear of other people.
  4. 4.Isolate the electrical supply. Identify the relevant circuit, isolate, lock off and tag. Prove dead with an approved voltage indicator, proved before and after use.
  5. 5.Carry out electrical work. Carry out the electrical work on the isolated circuit to BS 7671.
  6. 6.Remove isolation and re-energise. Confirm the work is complete and everyone is clear, remove locks and re-energise.
  7. 7.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
  8. 8.Hand over and sign out. Hand over to the County Hospital Estates site contact, report anything outstanding and sign out.

Main risks (2 in total)

Electric shock or burns

Residual Medium

Who: Operatives, building occupants

  • Work carried out dead — no live working
  • Safe isolation: isolate, lock off, tag, and prove dead with an approved voltage indicator (GS38) proved before and after
  • Only competent, qualified electricians carry out electrical work
  • Permit to work obtained where the site requires one
  • Personal locks and keys retained by the person working

Members of the public and building occupants

Residual Low

Who: Public, customers, staff, residents

  • Work area segregated with barriers and clear signage
  • Work timed for quieter periods where possible, agreed with the site
  • Tools and materials never left unattended in public areas
  • Site contact informed of work areas and any disruption

What to get right on this document

Name the system

Product, backing, and service type from the tested detail — not ‘intumescent’.

Close the hole the same shift

Temporary fire-resisting seal if the pipe is delayed.

Record every penetration

Label, photo, drawing mark-up.

What this document has to cover

Fire-stopping is not ‘mastic in a hole’. A generic fit-out RAMS that never names the tested system, the compartment wall, or how you leave an unfinished opening will fail a clerk of works and a fire engineer.

A fire stopping rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.

Typical hazards to assess on this job

  • Spread of fire or smoke through an open or wrongly filled penetration
  • Work at height in risers and ceiling voids
  • Dust and unknown services in fire-resisting walls
  • Hot works if using ablative coated batt cutting that generates heat
  • Manual handling of boards, mortar and collars
  • Other trades reopening a sealed penetration the same week

Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.

A method sequence that actually protects people

Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.

  • Confirm the fire strategy drawing and the specified system for each penetration type
  • Survey the opening: size, services, substrate, cleanliness
  • Set local exclusion in occupied floors; protect detection if dusting
  • Install collars, wraps, coated batt or mortar exactly as the system data sheet
  • Label the seal, photograph, and record the location
  • Do not leave an open penetration at the end of the shift — temporary approved seals if the service is not ready

Occupancy and other people

Hospitals, schools and occupied offices stay in use. A riser cupboard is not a workshop — keep doors locked, escape routes clear, and tell the fire warden if a compartment will be open even briefly.

Substances and COSHH

An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:

  • Ablative coatings and mastics
  • Mineral wool / coated batt fibres
  • Mortar and cementitious compounds

How SafeForJob helps

  • Describe this job in plain English and get suggested activities, risks and method steps
  • Edit every line before you download or issue
  • Reuse a previous RAMS and catch old client or site names
  • Attach or create COSHH assessments where hazardous substances appear

What this page is not

This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer fire stopping rams document for a named job. You remain responsible for reviewing and issuing it.

Related reading

See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.

Related pages

All rams by job · RAMS by trade · Free RAMS generator

Questions

Is this the same as fire doors?
No. Doors are a different package. This RAMS is penetrations and linear seals.
Can I use any intumescent mastic?
Only the system tested for that opening, service and substrate.
Do I need a hot works permit?
Not for typical mastic and collars. Cutting coated batt or grinding may add dust and heat — write what you actually do.
Who inspects?
Usually the fire engineer or clerk of works against the record — keep it.