Dry riser test RAMS
A test puts water into a normally dry pipe. A wet-riser RAMS that never mentions a pump at the inlet, a burst onto a stair, or how you stop the public using a flooded escape will fail.
Typical scope
- Alternative escape signed
- Specified test pressure
- Inlet exclusion
- Landing watch
- Main left dry
- Responsible person told
Quick answer
A dry-riser-test RAMS covers periodic pressure testing or repair of a dry fire main. Water on stairs, access at inlets and landing valves, and the building that must still evacuate are the usual harms.
Primary topic: dry riser test rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.
What usually goes wrong
These are the operational gaps that make generic Word RAMS fail on the next site.
Wet-riser install RAMS reused
Wrong charge state.
Tested to ‘see what it takes’
Overpressure.
Stair left wet for the evening commute
Slips.
Example
Annual dry-riser test on a live tower
Built from one job description. You review and adjust every item before issuing it.
Job description
Pressure-test the dry riser in stair B at Harbour Tower, Poole. Saturday 08:00–12:00, stair A as the alternative, inlet on the closed lay-by, specified pressure only, landing watch, drained dry, RTM signed.
Activities identified
- General site work
- Mobile tower or scaffold
Method (5 steps)
- 1.Arrive and sign in. Arrive at Stair B, Harbour Tower, Poole, report to the Harbour Tower RTM site contact, sign in and complete any site induction.
- 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
- 3.Erect the tower. PASMA-trained operatives erect the mobile tower to the manufacturer's guide and inspect it before use.
- 4.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
- 5.Hand over and sign out. Hand over to the Harbour Tower RTM site contact, report anything outstanding and sign out.
Main risks (2 in total)
Fall from tower or scaffold, or collapse
Residual MediumWho: Operatives, people nearby
- Mobile towers erected by PASMA-trained persons to the manufacturer's guide
- Scaffold erected by a competent scaffolder and tagged/inspected before use and every 7 days
- Guard rails, toe boards and brick guards in place on working platforms
- Castors locked and outriggers fitted; never moved while occupied
Falling objects
Residual LowWho: People below, other trades, public
- Exclusion zone set up below the work area with barriers and signage
- Tools tethered when working at height; materials kept away from edges
- Banksman or second person controls the area during lifts and removals
- Hard hats worn in the exclusion zone
What to get right on this document
The pressure is specified
Do not exceed it.
The stair is an escape
Alternative first.
Leave it dry
A dry riser that stays wet is a different system.
What this document has to cover
A test puts water into a normally dry pipe. A wet-riser RAMS that never mentions a pump at the inlet, a burst onto a stair, or how you stop the public using a flooded escape will fail.
A dry riser test rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.
Typical hazards to assess on this job
- Burst hose or landing valve flooding a stair
- Falls on a wet escape
- Vehicle and public at the inlet on the street
- Incorrect test pressure wrecking the main
- Building in occupation with a stair out of use
- Manual handling of test pumps and hoses
Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.
A method sequence that actually protects people
Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.
- Agree which stair is under test and the alternative escape
- Set exclusion at the inlet and protect the stair finishes
- Connect and test to the specified pressure — not ‘a bit more to be sure’
- Watch every landing for weeps; stop if a valve blows
- Drain the main fully so it is dry again
- Reinstate inlet boxes; tell the responsible person the stair is back
Occupancy and other people
Occupied towers still need that stair. Write the alternative escape and that a wet terrazzo is a closed stair until dried.
Substances and COSHH
An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:
- Test water (once dirty, it is waste)
- Grease on inlet threads
- Paint touch-up on boxes
How SafeForJob helps
- Describe this job in plain English and get suggested activities, risks and method steps
- Edit every line before you download or issue
- Reuse a previous RAMS and catch old client or site names
- Attach or create COSHH assessments where hazardous substances appear
What this page is not
This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer dry riser test rams document for a named job. You remain responsible for reviewing and issuing it.
Related reading
See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.
Related pages
- RAMS by tradeFire & security RAMSCreate RAMS for fire alarm, CCTV and access control installation: system isolations, ceiling work, occupied buildings. Review every suggestion before issue.
- GuidesWhat is a RAMS?RAMS means risk assessment and method statement — usually one site-specific pack for a construction or maintenance job. Practical UK guidance for contractors — with links to free tools.
- Method statementsFire alarm installation method statementWrite a fire alarm method statement for a named UK site. Clear sequence, interfaces and controls — review before issue.
- RAMS by jobConsumer unit replacement RAMSCreate a consumer unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEV charger installation RAMSCreate a ev charger installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobLighting rewire RAMSCreate a lighting rewire rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEICR testing RAMSCreate a eicr method statement for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobRooftop condenser replacement RAMSCreate a rooftop ac unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobSplit system installation RAMSCreate a split system installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
Questions
- Is this an install?
- No — this is a test visit. Use the wet-riser RAMS if you are altering pipe.
- Who provides the pump?
- Name them — and the pressure they will not exceed.
- Do I need TM at the inlet?
- If the inlet is on the highway, yes.
- Failed test?
- The responsible person owns the building’s compensation — tell them immediately.