Directional drilling RAMS
HDD is a steered bore, not a trench and not a diamond core. A vacuum-excavation RAMS that never mentions drill-rig exclusion, drilling fluid or how you stop a frac-out into a cellar will fail the asset owner.
Typical scope
- Bore design and surveys
- Entry/exit exclusion
- Head tracked
- Frac-out plan
- Fluid as waste
- Pits guarded
Quick answer
A directional-drilling RAMS covers a steered bore between named pits for a duct or pipe. Rig reaction, frac-out of mud, existing services and the public at both pits are the critical harms.
Primary topic: directional drilling rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.
What usually goes wrong
These are the operational gaps that make generic Word RAMS fail on the next site.
Trench RAMS reused
No bore, no fluid.
Lost the head and kept pushing
Strike.
Fluid to the kerb gully
Pollution.
Example
HDD under a high street
Built from one job description. You review and adjust every item before issuing it.
Job description
Directionally drill a 40 m fibre duct under High Street, Chester, pit to pit. Utility surveys, tracked head, bentonite contained, frac-out plan for cellars, both pits guarded, shopkeepers briefed, no fluid to gullies, NRSWA TM.
Activities identified
- General site work
- Power tools
- Dust-generating work
- Fibre and data cabling
Method (7 steps)
- 1.Arrive and sign in. Arrive at High Street, Chester, report to the City Fibre Works site contact, sign in and complete any site induction.
- 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
- 3.Drill and fix. Mark out, then drill and fix using on-tool dust extraction. Check for hidden cables and pipes before drilling.
- 4.Install and splice fibre. Route and secure cables, then cleave and splice fibres. Dispose of offcuts in the sharps container.
- 5.Test and commission. Test and commission the installation. Record results.
- 6.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
- 7.Hand over and sign out. Hand over to the City Fibre Works site contact, report anything outstanding and sign out.
Main risks (4 in total)
Hand and power tools
Residual LowWho: Operatives
- Battery or 110V tools used; no 230V tools on site without RCD protection
- Tools inspected before use and PAT tested where applicable
- Guards fitted and used as designed
- Eye protection and gloves suitable for the task
Noise and hand-arm vibration
Residual MediumWho: Operatives, people nearby
- Low-vibration, low-noise tools selected
- Trigger times limited and rotated between operatives
- Noisy work scheduled to reduce disruption to occupants
- Hearing protection worn where noise is high
Dust (including silica)
Residual MediumWho: Operatives, people nearby
- Use pre-formed holes, or methods that create less dust
- On-tool extraction (M- or H-class) or water suppression when cutting or drilling
- Clean up with an M-class vacuum — no dry sweeping
- Face-fit tested RPE (FFP3 or equivalent) worn
Optical fibre — laser light and glass shards
Residual LowWho: Engineers
- Never look into fibre ends or connectors; treat all fibres as live
- Fibre offcuts placed in a dedicated sharps container
- Safety glasses worn when cleaving and splicing
What to get right on this document
Track the head
Lost location is a stop.
Frac-out is planned
Cellars and rivers.
Fluid is waste
Not a gully.
What this document has to cover
HDD is a steered bore, not a trench and not a diamond core. A vacuum-excavation RAMS that never mentions drill-rig exclusion, drilling fluid or how you stop a frac-out into a cellar will fail the asset owner.
A directional drilling rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.
Typical hazards to assess on this job
- Rig reaction or rod strike injuring people at the entry
- Strike of existing gas, HV or fibre along the bore
- Frac-out of drilling fluid into a cellar, drain or river
- Public at open pits
- Manual handling of rods and reamers
- Noise next to homes and hospitals
Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.
A method sequence that actually protects people
Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.
- Confirm the bore design, service surveys and a frac-out plan before the rod turns
- Set exclusion at entry and exit; pit-guard both ends
- Drill to the designed profile; track the head; abort if you lose location
- Contain fluid; legal disposal, not a gully or a brook
- Pull the product; cap ends; do not leave a live pit
- Reinstate; tell neighbours if a frac-out reached them
Occupancy and other people
Urban streets have cellars and basements on the line. Write who is told and that a shop cellar is occupancy, not a surprise mud bath.
Substances and COSHH
An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:
- Drilling fluid / bentonite
- Diesel from the rig
- Spoiled fluid (waste)
How SafeForJob helps
- Describe this job in plain English and get suggested activities, risks and method steps
- Edit every line before you download or issue
- Reuse a previous RAMS and catch old client or site names
- Attach or create COSHH assessments where hazardous substances appear
What this page is not
This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer directional drilling rams document for a named job. You remain responsible for reviewing and issuing it.
Related reading
See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.
Related pages
- RAMS by tradeGroundworks RAMSCreate a groundworks or excavation RAMS online: buried services, trench collapse, plant movement and public interface. Review every suggestion before issue.
- GuidesWhat is a RAMS?RAMS means risk assessment and method statement — usually one site-specific pack for a construction or maintenance job. Practical UK guidance for contractors — with links to free tools.
- Method statementsExcavation method statementWrite a excavation method statement for a named UK site. Clear sequence, interfaces and controls — review before issue.
- RAMS by jobConsumer unit replacement RAMSCreate a consumer unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEV charger installation RAMSCreate a ev charger installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobLighting rewire RAMSCreate a lighting rewire rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEICR testing RAMSCreate a eicr method statement for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobRooftop condenser replacement RAMSCreate a rooftop ac unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobSplit system installation RAMSCreate a split system installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
Questions
- Is this diamond drilling?
- No — HDD is a steered bore, not a core through a slab.
- Vacuum instead?
- Vac is a different exposure method. Use that RAMS if you are exposing, not boring.
- Who owns the design profile?
- The designer — do not steepen it to save a pit.
- River crossing?
- Add permits and a tighter frac-out plan — do not copy a street bore.