RAMS by job · UK
DAS installation RAMS
DAS is an in-building radio system, not a Wi-Fi access point. A cabling RAMS that never mentions antenna exclusion zones, rooftop donors or how you keep a hospital ward off a live RF test will fail the radio engineer.
Typical scope
- RF lock-off / test window
- Designed antenna positions
- Fire-stop same visit
- Exclusion below high antennas
- Clinical/occupier abort
- Labels at handover
Quick answer
A DAS (distributed antenna) RAMS covers installing remote units and antennas in a named building. Height in voids, RF discipline, and a live building whose fire alarm and public you must not surprise are the usual controls.
Primary topic: das installation rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.
What usually goes wrong
These are the operational gaps that make generic Word RAMS fail on the next site.
Wi-Fi RAMS reused
No RF lock-off, no donor.
Antenna on a fire-door transom
Strategy.
Live sweep over a theatre list
Occupancy.
Example
Passive DAS in a hospital ward block
Built from one job description. You review and adjust every item before issuing it.
Job description
Install remote antennas on Ward B corridor at Royal Infirmary, Coventry. RF lock-off with the radio owner, Saturday window, designed positions, fire-stop as we go, no live sweep during lists, estates abort number on the permit.
Activities identified
- General site work
- Electrical isolation
- Manual handling
Method (9 steps)
- 1.Arrive and sign in. Arrive at Ward B, Royal Infirmary, Coventry, report to the Trust Estates site contact, sign in and complete any site induction.
- 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
- 3.Isolate the electrical supply. Identify the relevant circuit, isolate, lock off and tag. Prove dead with an approved voltage indicator, proved before and after use.
- 4.Disconnect and remove existing equipment. Disconnect and remove the existing equipment. Lower or carry it using mechanical aids or team lifts as planned.
- 5.Install new equipment. Position and fix the new equipment to the manufacturer's instructions.
- 6.Carry out electrical work. Carry out the electrical work on the isolated circuit to BS 7671.
- 7.Remove isolation and re-energise. Confirm the work is complete and everyone is clear, remove locks and re-energise.
- 8.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
- 9.Hand over and sign out. Hand over to the Trust Estates site contact, report anything outstanding and sign out.
Main risks (2 in total)
Electric shock or burns
Residual MediumWho: Operatives, building occupants
- Work carried out dead — no live working
- Safe isolation: isolate, lock off, tag, and prove dead with an approved voltage indicator (GS38) proved before and after
- Only competent, qualified electricians carry out electrical work
- Permit to work obtained where the site requires one
- Personal locks and keys retained by the person working
Manual handling
Residual MediumWho: Operatives
- Use mechanical aids (trolleys, sack trucks, hoists) for heavy items
- Team lifts for items too heavy or awkward for one person
- Route planned and cleared before moving items
- Operatives trained in safe lifting techniques
- Gloves with good grip and safety footwear
What to get right on this document
RF is planned
Lock-off and a window.
Positions are designed
Do not invent them.
The occupier can abort
Write the number.
What this document has to cover
DAS is an in-building radio system, not a Wi-Fi access point. A cabling RAMS that never mentions antenna exclusion zones, rooftop donors or how you keep a hospital ward off a live RF test will fail the radio engineer.
A das installation rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.
Typical hazards to assess on this job
- Falls from high-level antenna positions
- RF exposure if a donor or high-power unit is live during the works
- Electric shock on remote-unit supplies
- Fire-stopping left open on riser coax
- Dropped antennas onto the public
- Interference with medical or life-safety radio during a live test
Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.
A method sequence that actually protects people
Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.
- Agree RF lock-off and a test window with the radio owner and the occupier
- Set access and exclusion below antenna points
- Install units and antennas to the designed positions — do not ‘improve’ a location onto a fire door
- Fire-stop risers the same visit
- Commission only in the agreed window; abort if a clinical lead says stop
- Hand over labels and remaining open penetrations
Occupancy and other people
Hospitals and stadia stay occupied. Write the test window and that a live DAS test is not done over an MRI or a match-day crowd unless planned.
Substances and COSHH
An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:
- Coax joint compounds
- Fire-stopping mastics
- Cleaning wipes
How SafeForJob helps
- Describe this job in plain English and get suggested activities, risks and method steps
- Edit every line before you download or issue
- Reuse a previous RAMS and catch old client or site names
- Attach or create COSHH assessments where hazardous substances appear
What this page is not
This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer das installation rams document for a named job. You remain responsible for reviewing and issuing it.
Related reading
See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.
Related pages
- RAMS by tradeTelecoms RAMSCreate data cabling rams online for UK sites. Suggested risks and method steps matched to the job — you review every item before issue.
- GuidesWhat is a RAMS?RAMS means risk assessment and method statement — usually one site-specific pack for a construction or maintenance job. Practical UK guidance for contractors — with links to free tools.
- Method statementsMethod statement for electrical worksWrite a method statement for electrical works for a named UK site. Clear sequence, interfaces and controls — review before issue.
- RAMS by jobConsumer unit replacement RAMSCreate a consumer unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEV charger installation RAMSCreate a ev charger installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobLighting rewire RAMSCreate a lighting rewire rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEICR testing RAMSCreate a eicr method statement for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobRooftop condenser replacement RAMSCreate a rooftop ac unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobSplit system installation RAMSCreate a split system installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
Questions
- Is this Wi-Fi?
- No — DAS is typically a cellular/radio distribution system.
- Rooftop donor antenna?
- Add the roof RAMS if you go on the roof.
- Can I use a CAT6 RAMS?
- Copper backhaul may be related; antennas and RF lock-off are this job.
- Who owns the licence?
- The radio operator — you do not invent a test.