Conveyor installation RAMS

A conveyor is machinery with nips, not a racking beam. A racking RAMS that never mentions isolation of a live line, in-running nips or how you stop pickers walking a half-bolted frame will fail.

Typical scope

  • Aisle exclusion
  • Guards before bump-run
  • E-stops tested
  • Sprinkler/escape check
  • FLT banksman
  • No production run until signed

Quick answer

A conveyor-installation RAMS covers landing and commissioning a powered conveyor in a named hall. Lifting of sections, nips, and operations continuing in the next aisle are the critical harms.

Primary topic: conveyor installation rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.

What usually goes wrong

These are the operational gaps that make generic Word RAMS fail on the next site.

  • Racking RAMS reused

    No nips, no motors.

  • Bump-run to ‘see the belt’ without guards

    Nip.

  • Pickers using the frame as a walkway

    Fall.

Example

Sort conveyor in a live hall

Built from one job description. You review and adjust every item before issuing it.

Job description

Install a 30 m sort conveyor in aisle H at Ridings Fulfilment, Wakefield. Night shift, picking diverted, telehandler lift plan, guards before bump-run, e-stops tested, sprinkler droppers checked with FM, no production until signed.

Activities identified

  • General site work
  • Manual handling
  • Lifting operations
  • Plant and vehicle movement
  • Fire alarm or security systems
  • Lone working

Method (10 steps)

  1. 1.Arrive and sign in. Arrive at Aisle H, Ridings Fulfilment, Wakefield, report to the Ridings Fulfilment site contact, sign in and complete any site induction.
  2. 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
  3. 3.Agree fire system isolations. Agree with the responsible person which zones will be isolated and for how long. Put agreed fire-watch arrangements in place.
  4. 4.Carry out the lift. Carry out lifts to the lift plan, with the exclusion zone in place and a trained slinger/signaller directing.
  5. 5.Disconnect and remove existing equipment. Disconnect and remove the existing equipment. Lower or carry it using mechanical aids or team lifts as planned.
  6. 6.Install or replace devices. Install or replace detectors, sounders or security devices in the isolated zones.
  7. 7.Install new equipment. Position and fix the new equipment to the manufacturer's instructions.
  8. 8.Restore fire system. Restore all isolated zones, test the system, inform the responsible person and update the log book.
  9. 9.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
  10. 10.Hand over and sign out. Hand over to the Ridings Fulfilment site contact, report anything outstanding and sign out.

Main risks (5 in total)

Manual handling

Residual Medium

Who: Operatives

  • Use mechanical aids (trolleys, sack trucks, hoists) for heavy items
  • Team lifts for items too heavy or awkward for one person
  • Route planned and cleared before moving items
  • Operatives trained in safe lifting techniques
  • Gloves with good grip and safety footwear

Lifting operations

Residual Medium

Who: Operatives, public, other trades

  • Lift planned by a competent person; lift plan in place
  • Lifting equipment and accessories have current LOLER thorough examination
  • Exclusion zone below the lift; nobody under suspended loads
  • Trained slinger/signaller directs the lift
  • Lifts stopped in high winds

Moving vehicles and plant

Residual Medium

Who: Operatives, public, site staff

  • Pedestrians segregated from vehicle and plant routes
  • Plant operated by trained, authorised operators only
  • Banksman used for reversing and manoeuvring
  • High-visibility clothing worn

Fire alarm or protection out of service

Residual Medium

Who: Building occupants

  • Responsible person informed and isolations agreed before any part of the system is disabled
  • Only the zones being worked on are isolated, for the shortest possible time
  • Fire watch or alternative arrangements while protection is reduced
  • System fully restored and tested before leaving; log book updated

+ 1 more risks in the full RAMS.

What to get right on this document

Guards first

Then it may turn.

Picking is occupancy

Divert it.

E-stops are a handover

Tested, not assumed.

What this document has to cover

A conveyor is machinery with nips, not a racking beam. A racking RAMS that never mentions isolation of a live line, in-running nips or how you stop pickers walking a half-bolted frame will fail.

A conveyor installation rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.

Typical hazards to assess on this job

  • Dropped section onto people in the aisle
  • In-running nips on a bump-run
  • Electric shock on motors and photo-eyes
  • FLT versus pedestrians during the landing
  • Fire detection or sprinklers obstructed by a new high line
  • Operations using the line as a shortcut before guards are on

Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.

A method sequence that actually protects people

Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.

  • Lift plan and a hard exclusion in the aisle — picking diverted
  • Land and bolt sections; guards on before any bump-run
  • Isolate electrics until the line is complete
  • Set photo-eyes and e-stops; test from a position of safety
  • Check sprinklers and escape against the new line
  • Hand over isolation and do not run for production until guards and e-stops are signed

Occupancy and other people

Fulfilment halls do not pause. Write the diverted pick and that agency labour will climb a conveyor as a stair.

Substances and COSHH

An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:

  • Grease
  • Paint touch-up
  • Cleaning solvents on belts

How SafeForJob helps

  • Describe this job in plain English and get suggested activities, risks and method steps
  • Edit every line before you download or issue
  • Reuse a previous RAMS and catch old client or site names
  • Attach or create COSHH assessments where hazardous substances appear

What this page is not

This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer conveyor installation rams document for a named job. You remain responsible for reviewing and issuing it.

Related reading

See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.

Related pages

All rams by job · RAMS by trade · Free RAMS generator

Questions

Is this racking?
No — powered nips and motors.
Do I need PUWER advice?
This page is not legal advice; guards and e-stops still belong in the method.
Who owns the bump-run?
A competent person, guards on, exclusion held.
Fire engineering?
If the line changes smoke or sprinklers, that design sits with the client.